Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Kiosse Corporation’s May operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours.
Standard Units Costs | Total Actual Costs | ||||||
---|---|---|---|---|---|---|---|
Direct material | |||||||
Standard (3 lb. @ $2.00/lb.) | $6 | ||||||
Actual (6,200 lb. @ $2.20/lb.) | $13,640 | ||||||
Direct labor | |||||||
Standard (0.5 hr. @ $14/hr.) | $7 | ||||||
Actual (980 hrs. @ $13.70/hr.) | 13,426 | ||||||
Variable overhead | |||||||
Standard (0.5 hr. @ $4/hr.) | $2 | ||||||
Actual | - | 4,200 | |||||
Total | $15 | $31,266 |
Assume that the 6,200 lb. of materials purchased were all used in producing the 2,000 completed units. Determine the materials price and efficiency variances, labor rate and efficiency variances, and variable overhead spending and efficiency variances.
Do not use negative signs with any of your answers. Next to each variance answer, select either "F" for Favorable or "U" for Unfavorable.
Materials Variances | ||
---|---|---|
Actual cost: | Answer | |
Split cost: | Answer | |
Standard cost: | Answer | |
Materials price | Answer | AnswerFU |
Materials efficiency | Answer | AnswerFU |
Labor Variances | ||
---|---|---|
Actual cost: | Answer | |
Split cost: | Answer | |
Standard cost: | Answer | |
Labor rate | Answer | AnswerFU |
Labor efficiency | Answer | AnswerFU |
Variable Overhead Variances | ||
---|---|---|
Actual cost: | Answer | |
Split cost: | Answer | |
Standard cost: | Answer | |
Variable overhead spending | Answer | AnswerFU |
Variable overhead efficiency | Answer | AnswerFU |
Below answer complete relates to multiple Material , labour and overhead variance ,, Pleas see line by line .
Thank you .
The following summarized manufacturing data relate to Kiosse Corporation’s May operations | |||||
Finished units of product | 2,000 | ||||
Normal capacity - Direct Labour hrs | 1,100 | ||||
Standard Unit cost | Total Actual cost | ||||
Direct material | Rate | ||||
Standard | 3 lb | $2/lb | $6 | ||
Actual | 6200lb | $2.2/lb | $13640 | ||
Direct Labour | |||||
Standard | 0.5 hrs | $14/ hr | $ 7 | ||
Actual | 980 hrs | $13.70/ hr | $13426 | ||
Variable Overhead | |||||
Standard | 0.5 hrs | $4/ hr | $ 2 | ||
Actual | $4200 | ||||
Assume that 6200 lb of material completely used | |||||
in production of 2000 completed Units | |||||
Material price variance | |||||
( Standard price - Actual price) * Actual Quantity | |||||
Standard price $/lb | 2 | ||||
Actual price $/lb | 2.2 | ||||
Actual Quantity | 6200 | ||||
Material price variance $ | -1240 | Unfavorable | |||
(2-2.2)*6200 | |||||
Material Efficiency variance | |||||
( Standard Qty on Actual output - Actual Quantity) * Standard price | |||||
Standard price $/lb | 2 | ||||
Actual Quantity | 6200 | ||||
Standard Qty on Actual output | |||||
(3lb*2000 Unit) | 6000 | ||||
Material Efficiency variance $ | -400 | Unfavorable | |||
(6000-6200)*2 | |||||
Labour rate variance | |||||
( Standard rate - Actual rate ) * Actual Hrs | |||||
Standard rate $/ hr | 14 | ||||
Actual \rate $/ hr | 13.7 | ||||
Actual hrs | 980 | ||||
Labour rate variance $ | 294 | Favorable | |||
(14-13.7)*980 | |||||
Labour Efficiency ' variance | |||||
( Standard hrs on Actual output - Actual Hrs) * Standard rate / hr | |||||
Standard Hr on Actual output | |||||
(0.5hr*2000 Unit) | 1000 | ||||
Actual hrs | 980 | ||||
Standard rate $/ hr | 14 | ||||
Labour Efficiency ' variance $ | 280 | Favorable | |||
(1000-980)*14 | |||||
Variable OH rate variance | |||||
( Standard rate - Actual rate ) * Actual Hrs | |||||
Standard $/hr | 4 | ||||
Actual hrs | 980 | ||||
Standrate rate*Actual hrs $ | 3920 | ||||
Actual rate $ | 4200 | ||||
Variable OH rate variance | -280 | Unfavorable | |||
($3920-$4200) | |||||
Variable OH Efficiency variance | |||||
( Standard Hrs - Actual Hrs ) * Standard rate | |||||
Standard hrs | 1000 | ||||
Actual Hrs | 980 | ||||
Standard rate $/ hr | 14 | ||||
Variable OH Efficiency variance | 280 | Favorable | |||
(1000-980)*$14/hr |
Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Kiosse Corporation’s May...
Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Kiosse Corporation's May operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs $13,640 Direct material Standard (3 lb. @ $2.00/lb.) Actual (6,200 lb. @ $2.20/lb.) Direct labor Standard (0.5 hr. @ $14/hr.) Actual (980 hrs. @ $13.70/hr.) Variable overhead Standard (0.5 hr. @ $4/hr.) Actual Total 13,426 $15 4,200 $31,266 Assume that...
Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Kiosse Corporation's May operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs Direct material $6 Standard (3 lb. @ $2.00/lb.) Actual (6,200 lb. @ $2.20/lb.) Direct labor $13,640 $7 Standard (0.5 hr. @ $14/hr.) Actual (980 hrs. @ $13.70/hr.) Variable overhead 13,426 Standard (0.5 hr. @ $4/hr.) Actual 4,200 $31,266 Total $15...
Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Thomas Corporation’s April operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs Direct material Standard (2 lb. @ $9.00/lb.) $18 Actual (4,200 lb. @ $10.20/lb.) $42,840 Direct labor Standard (0.5 hr. @ $24/hr.) $12 Actual (950 hrs. @ $23.40/hr.) 22,230 Variable overhead Standard (0.5 hr. @ $6/hr.) $3 Actual - 6,450 Total...
Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Steffan Corporation's April operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs Direct material Standard (2 lb. @ $9.50/lb.) $19 Actual (4,200 lb. @ $10.20/lb.) $42,840 Direct labor Standard (0.5 hr. @ $24/hr.) $12 Actual (970 hrs. @ $23.40/hr.) 22,698 Variable overhead Standard (0.5 hr. @ $6/hr.) Actual 6,200 Total $71,738 Assume...
Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Steffan Corporation's April operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs Direct material Standard (2 lb. @ $9.50/lb.) $19 Actual (4,200 lb. @ $10.20/lb.) $42,840 Direct labor Standard (0.5 hr. @ $24/hr.) $12 Actual (970 hrs. @ $23.40/hr.) 22,698 Variable overhead Standard (0.5 hr. @ $6/hr.) $3 6,200 Actual $34 $71,738...
Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Thomas Corporation's April operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs $38 $83,160 $17 Direct material Standard (2 lb. @ $19.00/lb.) Actual (4,200 lb. @ $19.80/lb.) Direct labor Standard (0.5 hr. @ $34/hr.) Actual (950 hrs. @ $33.00/hr.) Variable overhead Standard (0.5 hr. @ $16/hr.) Actual Total 31,350 $8 16,450 $130,960...
Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Thomas Corporation's April operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs $34 $74,760 Direct material Standard (2 lb. @ $17.00/lb.) Actual (4,200 lb. @ $17.80/lb.) Direct labor Standard (0.5 hr. @ $32/hr.) Actual (950 hrs. @ $31/hr.) Variable overhead Standard (0.5 hr. @ $14/hr.) $16 29,450 $7 Actual 14,450 $118,660 Total...
Question text Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Thomas Corporation's April operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs Direct material Standard (2 lb. @ $17.00/lb.) $34 Actual (4,200 lb. @ $17.80/lb.) $74,760 Direct labor Standard (0.5 hr. @ $32/hr.) $16 Actual (950 hrs. @ $31/hr.) 29,450 Variable overhead Standard (0.5 hr. @ $14/hr.) $7 Actual -...
Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Thomas Corporation's April operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs Direct material Standard (2 lb. @ $18.00/lb.) $36 Actual (4,200 lb. @ $19/lb.) $79,800 Direct labor Standard (0.5 hr. @ $33/hr.) $16.50 Actual (950 hrs. @ $32.20/hr.) 30,590 Variable overhead Standard (0.5 hr. @ $15/hr.) $7.50 Actual - 15,450 Total...
Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Thomas Corporation's April operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs Direct material Standard (2 lb. @ $18.00/lb.) $36 Actual (4,200 lb. @ $19/lb.) $79,800 Direct labor Standard (0.5 hr. @ $33/hr.) $16.50 Actual (950 hrs. @ $32.20/hr.) 30,590 Variable overhead Standard (0.5 hr. @ $15/hr.) $7.50 Actual 15,450 Total $60...