Question

Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Kiosse Corporation’s May...

Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Kiosse Corporation’s May operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours.

Standard Units Costs Total Actual Costs
Direct material
Standard (3 lb. @ $2.00/lb.) $6
Actual (6,200 lb. @ $2.20/lb.) $13,640
Direct labor
Standard (0.5 hr. @ $14/hr.) $7
Actual (980 hrs. @ $13.70/hr.) 13,426
Variable overhead
Standard (0.5 hr. @ $4/hr.) $2
Actual - 4,200
Total $15 $31,266

Assume that the 6,200 lb. of materials purchased were all used in producing the 2,000 completed units. Determine the materials price and efficiency variances, labor rate and efficiency variances, and variable overhead spending and efficiency variances.

Do not use negative signs with any of your answers. Next to each variance answer, select either "F" for Favorable or "U" for Unfavorable.

Materials Variances
Actual cost: Answer
Split cost: Answer
Standard cost: Answer
Materials price Answer AnswerFU
Materials efficiency Answer AnswerFU
Labor Variances
Actual cost: Answer
Split cost: Answer
Standard cost: Answer
Labor rate Answer AnswerFU
Labor efficiency Answer AnswerFU
Variable Overhead Variances
Actual cost: Answer
Split cost: Answer
Standard cost: Answer
Variable overhead spending Answer AnswerFU
Variable overhead efficiency Answer AnswerFU
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Below answer complete relates to multiple Material , labour and overhead variance ,, Pleas see line by line .

Thank you .

The following summarized manufacturing data relate to Kiosse Corporation’s May operations
Finished units of product                         2,000
Normal capacity - Direct Labour hrs                         1,100
Standard Unit cost Total Actual cost
Direct material Rate
Standard 3 lb $2/lb $6
Actual 6200lb $2.2/lb $13640
Direct Labour
Standard 0.5 hrs $14/ hr $ 7
Actual 980 hrs $13.70/ hr $13426
Variable Overhead
Standard 0.5 hrs $4/ hr $ 2
Actual $4200
Assume that 6200 lb of material completely used
in production of 2000 completed Units
Material price variance
( Standard price - Actual price) * Actual Quantity
Standard price $/lb 2
Actual price $/lb 2.2
Actual Quantity 6200
Material price variance $ -1240 Unfavorable  
(2-2.2)*6200
Material Efficiency variance
( Standard Qty on Actual output - Actual Quantity) * Standard price
Standard price $/lb 2
Actual Quantity 6200
Standard Qty on Actual output
(3lb*2000 Unit) 6000
Material Efficiency variance $ -400 Unfavorable  
(6000-6200)*2
Labour rate variance
( Standard rate - Actual rate ) * Actual Hrs
Standard rate $/ hr 14
Actual \rate $/ hr 13.7
Actual hrs 980
Labour rate variance $ 294 Favorable  
(14-13.7)*980
Labour Efficiency ' variance
( Standard hrs on Actual output - Actual Hrs) * Standard rate / hr
Standard Hr on Actual output
(0.5hr*2000 Unit) 1000
Actual hrs 980
Standard rate $/ hr 14
Labour Efficiency ' variance $ 280 Favorable  
(1000-980)*14
Variable OH rate variance
( Standard rate - Actual rate ) * Actual Hrs
Standard $/hr 4
Actual hrs 980
Standrate rate*Actual hrs $ 3920
Actual rate $ 4200
Variable OH rate variance -280 Unfavorable  
($3920-$4200)
Variable OH Efficiency variance
( Standard Hrs - Actual Hrs ) * Standard rate
Standard hrs 1000
Actual Hrs 980
Standard rate $/ hr 14
Variable OH Efficiency variance 280 Favorable  
(1000-980)*$14/hr
Add a comment
Know the answer?
Add Answer to:
Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Kiosse Corporation’s May...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Kiosse Corporation's May...

    Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Kiosse Corporation's May operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs $13,640 Direct material Standard (3 lb. @ $2.00/lb.) Actual (6,200 lb. @ $2.20/lb.) Direct labor Standard (0.5 hr. @ $14/hr.) Actual (980 hrs. @ $13.70/hr.) Variable overhead Standard (0.5 hr. @ $4/hr.) Actual Total 13,426 $15 4,200 $31,266 Assume that...

  • Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Kiosse Corporation's May...

    Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Kiosse Corporation's May operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs Direct material $6 Standard (3 lb. @ $2.00/lb.) Actual (6,200 lb. @ $2.20/lb.) Direct labor $13,640 $7 Standard (0.5 hr. @ $14/hr.) Actual (980 hrs. @ $13.70/hr.) Variable overhead 13,426 Standard (0.5 hr. @ $4/hr.) Actual 4,200 $31,266 Total $15...

  • Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Thomas Corporation’s April...

    Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Thomas Corporation’s April operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs Direct material Standard (2 lb. @ $9.00/lb.) $18 Actual (4,200 lb. @ $10.20/lb.) $42,840 Direct labor Standard (0.5 hr. @ $24/hr.) $12 Actual (950 hrs. @ $23.40/hr.) 22,230 Variable overhead Standard (0.5 hr. @ $6/hr.) $3 Actual - 6,450 Total...

  • Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Steffan Corporation's April...

    Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Steffan Corporation's April operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs Direct material Standard (2 lb. @ $9.50/lb.) $19 Actual (4,200 lb. @ $10.20/lb.) $42,840 Direct labor Standard (0.5 hr. @ $24/hr.) $12 Actual (970 hrs. @ $23.40/hr.) 22,698 Variable overhead Standard (0.5 hr. @ $6/hr.) Actual 6,200 Total $71,738 Assume...

  • Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Steffan Corporation's April...

    Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Steffan Corporation's April operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs Direct material Standard (2 lb. @ $9.50/lb.) $19 Actual (4,200 lb. @ $10.20/lb.) $42,840 Direct labor Standard (0.5 hr. @ $24/hr.) $12 Actual (970 hrs. @ $23.40/hr.) 22,698 Variable overhead Standard (0.5 hr. @ $6/hr.) $3 6,200 Actual $34 $71,738...

  • Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Thomas Corporation's April...

    Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Thomas Corporation's April operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs $38 $83,160 $17 Direct material Standard (2 lb. @ $19.00/lb.) Actual (4,200 lb. @ $19.80/lb.) Direct labor Standard (0.5 hr. @ $34/hr.) Actual (950 hrs. @ $33.00/hr.) Variable overhead Standard (0.5 hr. @ $16/hr.) Actual Total 31,350 $8 16,450 $130,960...

  • Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Thomas Corporation's April...

    Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Thomas Corporation's April operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs $34 $74,760 Direct material Standard (2 lb. @ $17.00/lb.) Actual (4,200 lb. @ $17.80/lb.) Direct labor Standard (0.5 hr. @ $32/hr.) Actual (950 hrs. @ $31/hr.) Variable overhead Standard (0.5 hr. @ $14/hr.) $16 29,450 $7 Actual 14,450 $118,660 Total...

  • Question text Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Thomas...

    Question text Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Thomas Corporation's April operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs Direct material Standard (2 lb. @ $17.00/lb.) $34 Actual (4,200 lb. @ $17.80/lb.) $74,760 Direct labor Standard (0.5 hr. @ $32/hr.) $16 Actual (950 hrs. @ $31/hr.) 29,450 Variable overhead Standard (0.5 hr. @ $14/hr.) $7 Actual -...

  • Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Thomas Corporation's April...

    Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Thomas Corporation's April operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs Direct material Standard (2 lb. @ $18.00/lb.) $36 Actual (4,200 lb. @ $19/lb.) $79,800 Direct labor Standard (0.5 hr. @ $33/hr.) $16.50 Actual (950 hrs. @ $32.20/hr.) 30,590 Variable overhead Standard (0.5 hr. @ $15/hr.) $7.50 Actual - 15,450 Total...

  • Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Thomas Corporation's April...

    Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Thomas Corporation's April operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs Direct material Standard (2 lb. @ $18.00/lb.) $36 Actual (4,200 lb. @ $19/lb.) $79,800 Direct labor Standard (0.5 hr. @ $33/hr.) $16.50 Actual (950 hrs. @ $32.20/hr.) 30,590 Variable overhead Standard (0.5 hr. @ $15/hr.) $7.50 Actual 15,450 Total $60...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT