Stone Age Surfboards is a small manufacturer of two types of popular low-tide surfboards, the Graystone...

Stone Age Surfboards is a small manufacturer of two types of popular low-tide surfboards, the Graystone and the Lava models. The manufacturing process consists of two departments: fabrication and finishing. The fabrication department has 8 skilled workers, each of whom works 9.25 hours per day. The finishing department has 5 workers, each of whom works a 6-hour shift per day. Each pair of Graystone surfboards requires 2.5 labor hours in the fabrication department and 2 labor hours in finishing. The Lava model requires 4.2 labor-hours in fabrication and 3.6 labor-hours in finishing. The company operates 6 days a week. It makes a per unit profit of $40 on the Graystone model and $60 on the Lava model. The company anticipates selling at least twice as many Lava models as Graystone models.



What is the total profit generated?

What will be the total profit contribution from Lava surfboards?

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Stone Age Surfboards Data Product Graystone Department Fabrication Finishing 2.5 Lava 4.2 3.6 Limitation (Hours) 74 30 2 Prof

Add a comment
Know the answer?
Add Answer to:
Stone Age Surfboards is a small manufacturer of two types of popular low-tide surfboards, the Graystone...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Stone Age Surfboards is a small manufacturer of two types of popular low-tide surfboards, the Graystone...

    Stone Age Surfboards is a small manufacturer of two types of popular low-tide surfboards, the Graystone and the Lava models. The manufacturing process consists of two departments: fabrication and finishing. The fabrication department has 8 skilled workers, each of whom works 9.25 hours per day. The finishing department has 5 workers, each of whom works a 6-hour shift per day. Each pair of Graystone surfboards requires 2.5 labor hours in the fabrication department and 2 labor hours in finishing. The...

  • Use the following information to answer the following question(s), using the SUMPRODUCT function. Stone Age Surfboards...

    Use the following information to answer the following question(s), using the SUMPRODUCT function. Stone Age Surfboards is a small manufacturer of two types of popular high-tide surfboards, the Rockwell and the Limestone models. The manufacturing process consists of two departments: fabrication and finishing. The fabrication department has 15 skilled workers, each of whom works 5 hours per day. The finishing department has 5 workers, who also work a 5-hour shift. Each pair of Rockwell surfboards requires 3 labor hours in...

  • The question is: If the company adds an additional worker in the finishing department, what will...

    The question is: If the company adds an additional worker in the finishing department, what will happen? The question is: If the company adds an additional worker in the finishing department, what will happen? Multiple choice answer options are below. The answer is either A, B, C or D. A.) profit will increase by $120 B.) profit will increase by $20 C.) the optimal solution will not change D.) the company will produce 20 additional surfboards Beach Boys Surfers is...

  • Use the scenario given below to answer the following question(s) Ray Inc. manufactures two types of...

    Use the scenario given below to answer the following question(s) Ray Inc. manufactures two types of gaming consoles, the sp2 hybrid and the sp3 hybrid models. The manufacturing process consists of two principal departments: design and production. The design department has 58 skilled workers, each of whom works 7 hours per day. The production department has 25 workers, who also work a 7-hour shift. On an average, to produce a sp2 hybrid, Ray Inc. requires 3.5 labor hours for design...

  • A small company manufactures three different electronic components for computers. Component A req...

    A small company manufactures three different electronic components for computers. Component A requires 2 hours of fabrication and 1 hour of assembly; component B requires 3 hours of fabrication and 1 hour of assembly, and component C requires 2 hours of fabrication and 2 hours of assembly. The company has up to 950 labor-hours of fabrication time and 700 labor-hours of assembly time available per week. The profit on each component, A, B, and C, is $7, $8, and $10,...

  • b) A manufacturing of UT CUver Sheet mak ng company makes two models A and B...

    b) A manufacturing of UT CUver Sheet mak ng company makes two models A and B of a product. Each piece Model A requires 9 labor hours for fabricating and 1 labor hour for finishing. Each piece of Model B requires 12 labor hours for fabricating and 3 labor hours for finishing For fabricating and finishing, the maximum labor hours available are 180 and 30 respectively. The company makes a profit of AED 8000 on each piece of model A...

  • Cost Assignment and IT Bunker Company produces two types of glucose monitors (basic and advanced). Both...

    Cost Assignment and IT Bunker Company produces two types of glucose monitors (basic and advanced). Both pass through two producing departments: Fabrication and Assembly. Bunker also has an Inspection Department that is responsible for testing monitors to ensure that they perform within prespecified tolerance ranges (a sampling procedure is used). Budgeted data for the three departments are as follows: Inspection Fabrication Assembly Overhead $560,000 $840,000 $238,000 Number of tests 35,000 105,000 Direct labor hours 84,000 42,000 In the Fabrication Department,...

  • A computer parts manufacturer produces two types of monitors—monochrome and color. There are two ...

    A computer parts manufacturer produces two types of monitors—monochrome and color. There are two production lines, one for each type of monitor. The monochrome monitor line has a daily capacity of 700 units per day. The color monitor line has a daily capacity of 500 units per day. In department A, the LCD panels are produced for both monitor lines. In department A, the production of monochrome LCD requires one hour of labor, and a color monitor requires two hours...

  • A company manufactures two types of electric hedge trimmers, one of which is cordless. The cord-type...

    A company manufactures two types of electric hedge trimmers, one of which is cordless. The cord-type trimmer requires 2 hours to make, and the cordless model requires 4 hours. The company has only 800 work hours to use in manufacturing each day, and the packaging department can package only 300 trimmers per day. If the company profits are $36.50 for the cord-type model and $73.00 for the cordless model, how many of each type should the company produce per day...

  • Formulate the LP Problem, but do NOT solve: A furniture manufacturer makes armchairs and benches. The...

    Formulate the LP Problem, but do NOT solve: A furniture manufacturer makes armchairs and benches. The company has a maximum of 200 labor hours available in the Cutting Department, a maximum of 480 labor hours available in the Finishing Department, and a maximum of 150 labor hours available in the Packaging Department. Each armchair requires two hours in the Cutting Department, four hours in the Finishing Department and one hour in the Packaging Department. Each bench requires one hour in...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT