Solution 1:
Variable Overhead Cost Variance | ||||||||||||
Actual Cost | Standard cost for actual quantity | Standard Cost | ||||||||||
AH * | AR = | AH * | SR = | SH * | SR = | |||||||
575000 | $2.82 | $1,624,000.00 | 575000 | $2.80 | $1,610,000.00 | 609000 | $2.80 | $1,705,200.00 | ||||
$14,000.00 | U | $95,200.00 | F | |||||||||
Variable overhead rate variance | Variable overhead efficiency variance | |||||||||||
Variable overhead rate variance | $14,000.00 | U | ||||||||||
Variable overhead efficiency variance | $95,200.00 | F | ||||||||||
Variable overhead cost variance | $81,200.00 | F |
Solution 2:
Fixed Overhead Cost Variance | ||||||||||||
Actual Fixed OH Cost | Budgeted Fixed Overhead | Standard Cost (FOH Applies) | ||||||||||
SH* | BR | |||||||||||
$866,000.00 | $783,000.00 | 609000 | $1.20 | $730,800.00 | ||||||||
$83,000.00 | U | $52,200.00 | U | |||||||||
Fixed overhead Budget Variance | Fixed overhead volume variance | |||||||||||
Fixed overhead Budget Variance | $83,000.00 | U | ||||||||||
Fixed overhead volume variance | $52,200.00 | U | ||||||||||
Total Fixed overhead variance | $135,200.00 | U |
Solution 3:
Overhead controllable variance | ||
Variable Overhead rate Variance | $14,000.00 | Unfavorable |
Variable overhead efficiency variance | $95,200.00 | Favorable |
Fixed overhead spending variance | $83,000.00 | Unfavorable |
Overhead controllable variance | $1,800.00 | Unfavorable |
Required information Use the following information for the Exercises below. The following information applies to the...
Required information (The following information applies to the questions displayed below.] Sedona Company set the following standard costs for one unit of its product for this year. Direct material (20 Ibs. $3.30 per Ib.) Direct labor (15 hrs. @ $6.00 per hr.) Variable overhead (15 hrs. @ $2.80 per hr.) Fixed overhead (15 hrs. $1.20 per hr.) Total standard cost $ 66.00 90.00 42.00 18.00 $216.00 The $4.00 ($2.80 + $1.20) total overhead rate per direct labor hour is based...
Required information The following information applies to the questions displayed below) Sedona Company set the following standard costs for one unit of its product for this year Direct material (30 lbs. @ $2.20 per Ib.) Direct labor (10 hrs. @ $4.60 per hr.) Variable overhead (10 hrs. $3.20 per hr.) Fixed overhead (18 hrs. $1.50 per hr.) Total standard cost $ 66. 46.00 30.00 15.00 $157.00 The $4.50 ($3.00 + $1.50) total overhead rate per direct labor hour is based...
Required information Use the following information for the Exercises below. The following information applies to the questions displayed below) Sedona Company set the following standard costs for one unit of its product for 2017 Direct material (30 lbs. 52.20 per Ib.) Direct labor (10 hrs. @ $4.60 per hr.) Factory variable overhead (10 hrs. @ $3.00 per hr.) Factory fixed overhead (10 hrs. @ $1.50 per hr.) Standard cost $66.00 46.88 30.00 15.00 $157.ee The $4.50 ($3.00+ $1.50) total overhead...
Use the following information for the Exercises below. [The following information applies to the questions displayed below.) Sedona Company set the following standard costs for one unit of its product for 2017. Direct material (30 lbs. @ $2.50 per lb.) Direct labor (20 hrs. @ $4.80 per hr.) Factory variable overhead (20 hrs. @ $2.30 per hr.) Factory fixed overhead (20 hrs. @ $1.20 per hr.) Standard cost $ 75.00 96.00 46.00 24.00 $241.00 The $3.50 ($2.30 + $1.20) total...
Sedona Company set the following standard costs for one unit of its product for this year Direct material (30 Ibs.@ $2.20 per Ib.) Direct labor (10 hrs. @ $4.60 per hr.) Variable overhead (10 hrs. @ $3.00 per hr.) Fixed overhead (10 hrs. @ $1.50 per hr.) $66.00 46.00 30.00 15.00 $157.00 Total standard cost The $4.50 ($3.00+ $1.50) total overhead rate per direct labor hour is based on an expected operating level equal to 70% of the factory's capacity...
Required Information [The following information applies to the questions displayed below] Sedona Company set the following standard costs for one unit of its product for this year. Direct material (30 lbs. $2.50 per Ib. ) Direct labor (20 hrs. $4.80 per hr.) Variable overhead (20 hrs. $2.30 per hr.) Fixed overhead (20 hrs. $1.20 per hr.) Total standard cost $75.00 96.00 46.00 24.ee $241.00 The $3.50 ($2.30 + $1.20) total overhead rate per direct labor hour is based on an...
Sedona Company set the following standard costs for one unit of its product for this year. Direct material (20 Ibs. @ $3.30 per Ib.) Direct labor (15 hrs. @ $6.00 per hr.) Variable overhead (15 hrs. @ $2.80 per hr.) Fixed overhead (15 hrs. @ $1.20 per hr.) Total standard cost $ 66.00 90.00 42.00 18.00 $216.00 The $4.00 ($2.80 + $1.20) total overhead rate per direct labor hour is based on an expected operating level equal to 75% of...
Required information The following Information applies to the questions displayed below] Sedona Company set the following standard costs for one unlt of Its product for 2017 Direct aterial (20 Ibs. $3.30 per Ib. Direct labor (15 hrs. $6.00 per hr.) Eactory variable overhead (15 hrs. $2.80 per hr.) Factory fixed overhead (15 hs $1.20 per hr.) Standard cost 66.00 90.00 42.00 1B.00 $216.00 The $400 ($280-$120) total overhead rate per direct labor hour is based on an expected operating level...
Required information [The following information applies to the questions displayed below.] Sedona Company set the following standard costs for one unit of its product for 2017. Direct material (20 Ibs. @ $3.20 per Ib.) $ 64.00 Direct labor (10 hrs. @ $8.30 per hr.) 83.00 Factory variable overhead (10 hrs. @ $4.70 per hr.) 47.00 Factory fixed overhead (10 hrs. @ $2.30 per hr.) 23.00 Standard cost $ 217.00 The $7.00 ($4.70 + $2.30) total overhead rate per direct labor...
HOW DO I CALCULATE? Sedona Company set the following standard costs for one unit of its product for this year. Direct material (30 Ibs. $2.20 per Ib.) Direct labor (20 hrs. $4.20 per hr.) Variable overhead (20 hrs. $2.20 per hr.) Fixed overhead (20 hrs. $1.10 per hr.) $ 66.00 84.00 44.00 22.00 $216.00 Total standard cost The $3.30 ($2.20 +$1.10) total overhead rate per direct labor hour is based on an expected operating level equal to 60% of the...