Question

Heaton Steel Company is a steel manufacturer. It has three departments. Department A is responsible for...

Heaton Steel Company is a steel manufacturer. It has three departments. Department A is responsible for melting the scrap metal. Afterwards, the molten metals are transferred to Department B. Department B will then pours the molten metal into ingot casting. Ingot castings are transferred to Department C. Department C sands off any sharp edges and package the castings for shipment to customers. Data for Department A for January are:

Department A: Costs of Beginning Work-in-Process (January 1st)

  • Scrap Metal (5,000 tons)                                            $6,000
  • Labor work for melting the metal                              $5,000
  • Factory Overhead                                                       $500

Department A: Costs Added in January

  • Scrap Metal (67,000 tons)                                          $80,000
  • Labor                                                                          $130,000
  • Factory Overhead                                                       $4,500

Additional information

  • 68,000 tons of molten metals transferred to Department B
  • January 31st: 50% complete as to conversion costs

Complete the Cost Production Report Below

ç Inputs ➔

=

ç Outputs ➔

Unit Calculations

Beginnin g WIP Inventory

Add Current Month

Equals Total Production

Completed Transfer Out

Add Ending WIP Inventory

Total Outputs

Direct Materials Whole Units

% Equivalent Completed

Conversion Equivalent Units

ç Inputs ➔

Cost of Production per Unit

ç Outputs ➔

Cost Calculations

Beginnin g WIP Inventory

Add Current Month

Equals Total Production

Completed Transfer Out

Add Ending WIP Inventory

Total Outputs

Direct Materials Units

Direct Materials Cost

Conversion Units

Direct Labor

Manufacturing Overhead

Total Conversion Cost

Total

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solutions:

Complete the Cost Production Report Below
ç Inputs ➔ = ç Outputs ➔
Unit Calculations Beginnin g WIP Inventory Add Current Month Equals Total Production Completed Transfer Out Add Ending WIP Inventory Total Outputs
Direct Materials Whole Units 5000 67000 72000 68000 4000 72000
% Equivalent Completed 100% 50%
Conversion Equivalent Units 68000 2000 70000
ç Inputs ➔ Cost of Production per Unit ç Outputs ➔
Cost Calculations Beginnin g WIP Inventory Add Current Month Equals Total Production Completed Transfer Out Add Ending WIP Inventory Total Outputs
Direct Materials Units 5000 67000 72000 68000 4000 72000
Direct Materials Cost 6000 80000 86000 1.2 81222 4778 86000
Conversion Units 68000 2000
Direct Labor 5000 130000 135000 1.93 131143 3857 135000
Manufacturing Overhead 500 4500 5000 0.07 4857 143 5000
Total Conversion Cost 5500 134500 140000 2.00 136000 4000 140000
Total 11500 214500 226000 217222 8778 226000

Notes:

Material cost per unit is calculated as Total Costs / Total units = 86000/72000

Direct Labor and Overhead costs = Total Costs / Equivalent Units = 135000/70000 and 5000/70000

Equivalent Units = 50% complete as to conversion costs = 68000 + 50%*4000 = 70000

Add a comment
Know the answer?
Add Answer to:
Heaton Steel Company is a steel manufacturer. It has three departments. Department A is responsible for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Naus Steel Company has two departments. Casting and Rolling. In the Rolling Department, ingots from the...

    Naus Steel Company has two departments. Casting and Rolling. In the Rolling Department, ingots from the Casting Department are rolled into steel sheet. The Rolling Department received 4,000 CONS from the Casting Department in October. During October. the Rolling Department completed 3,00 tons, including 200 tons of work in process on October 1. The ending work in process inventory on October 31 was 300 tons. The Rolling Department of Kraus Steel Company had 200 tons in beginning work in process...

  • Problem1 – Process costing Timing Tech, a manufacturing company, has two departments: Production department and Finishing...

    Problem1 – Process costing Timing Tech, a manufacturing company, has two departments: Production department and Finishing department. Goods completed in the Production department are immediately sent to the Finishing department. The following data pertains to the Production department. Physical Direct Material Direct Labor Units Cost Cost Beg. WIP inventory (Jan. 1 2014) 200,000 units $ 200,000 $ 315,000 Units Started during the year 1,000,000 units Costs incurred during the year $1,300,000 $1,995,000 End. WIP inventory (Dec. 31 2014) 300,000 units...

  • LDR Manufacturing produces a pesticide chemical and uses process costing. There are three processing departments—Mixing, Refining,...

    LDR Manufacturing produces a pesticide chemical and uses process costing. There are three processing departments—Mixing, Refining, and Packaging. On January 1, 2014, the first department, Mixing, had no beginning inventory. During January, 40,000 fl. oz. of chemicals were started in production. Of these, 32,000 fl. oz. were completed and 8,000 fl. oz. remained in process. Management estimates that the in-process units are approximately 60% complete. In the Mixing Department, all direct materials are added at the beginning of the production...

  • Problem 6-46 FIFO Method; Two Departments [LO 6-2, 6-5, 6-6] Bhatti Company produces plastic photo frames....

    Problem 6-46 FIFO Method; Two Departments [LO 6-2, 6-5, 6-6] Bhatti Company produces plastic photo frames. Two departments, molding and finishing, are involved in the manufacturing. The E molding department fills the molds with hot liquid plastic that is left to cool and then opens them. The finishing department removes the plastic frame from the mold and strips the edges of the frames of extra plastic. The following information is available for the month of January: Work-in-Process Inventory Molding department...

  • Production Report, No Beginning Inventory Softkin Company manufactures sun protection lotion. The Mixing Department, the first...

    Production Report, No Beginning Inventory Softkin Company manufactures sun protection lotion. The Mixing Department, the first process department, mixes the chemicals required for the repellant. The following data are for the current year: Work in process, January 1 — Gallons started 450,000 Gallons transferred out 378,000 Direct materials cost $900,000 Direct labor cost $1,785,600 Overhead applied $2,678,400 Direct materials are added at the beginning of the process. Ending inventory is 95 percent complete with respect to direct labor and overhead....

  • Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 3,000 tons in...

    Equivalent Units of Materials Cost The Rolling Department of Kraus Steel Company had 3,000 tons in beginning work in process inventory (60% complete) on October 1. During October, 50,800 tons were completed. The ending work in process inventory on October 31 was 2,500 tons (50% complete). What are the total equivalent units for direct materials for October if materials are added at the beginning of the process? units Equivalent Units of Conversion Costs The Rolling Department of Kraus Steel Company...

  • Badgersize company

    Badgersize Company has the following information for its Forming Department for the month of August:Work in Process Inventory, August 1: 20,000 unitsDirect materials: 100% complete $ 80,000Conversion: 20% complete 24,000Balance in work in process, August 1 $ 104,000Units started during August 50,000Units completed and transferred in August 60,000Work in process (70% complete), August 31 ?Costs charged to Work in Process in AugustDirect materials $ 150,000Conversion costs:Direct labor $ 120,000Overhead applied 132,000Total conversion $ 252,000Assume materials are added at the start...

  • Cost of Production Report The Cutting Department of Karachi Carpet Company provides the following data for...

    Cost of Production Report The Cutting Department of Karachi Carpet Company provides the following data for January. Assume that all materials are added at the beginning of the process. Work in process, January 1, 14,000 units, 75% completed $168,000* *Direct materials (14,000 x $7.80) $109,200 Conversion (14,000 x 75% * $5.60) 58,800 $168,000 Materials added during January from Weaving Department, 215,600 units $1,714,020 Direct labor for January 525,344 Factory overhead for January 642,086 Goods finished during January (includes goods in...

  • Cost of Production Report The Cutting Department of Karachi Carpet Company provides the following data for...

    Cost of Production Report The Cutting Department of Karachi Carpet Company provides the following data for January. Assume that all materials are added at the beginning of the process. Work in process, January 1, 14,000 units, 75% completed $168,000* *Direct materials (14,000 x $7.80) $109,200 Conversion (14,000 x 75% * $5.60) 58,800 $168,000 Materials added during January from Weaving Department, 215,600 units $1,714,020 Direct labor for January 525,344 Factory overhead for January 642,086 Goods finished during January (includes goods in...

  • Scribners Corporation produces fine papers in three production departments-Pulping, Drying, and Finishing. In the Pulping Department,...

    Scribners Corporation produces fine papers in three production departments-Pulping, Drying, and Finishing. In the Pulping Department, raw materials such as wood fiber and rag cotton are mechanically and chemically treated to separate their fibers. The result is a thick slurry of fibers. In the Drying Department, the wet fibers transferred from the Pulping Department are laid down on porous webs, pressed to remove excess liquid, and dried in ovens. In the Finishing Department, the dried paper is coated, cut, and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT