Lorrimer Company has a job-order cost system. The following debits (credits) appeared in the Work-in-Process account for the month of June.
June 1, balance | $12,000 | |
June 30, direct materials | 50,000 |
During the month of June, direct labor totaled $30,000 and $24,000 of overhead was applied to production. Finished Goods was debited $100,000 during June.
Lorrimer Company applies overhead at a predetermined rate of 80% of direct labor cost. Job number 83, the only job still in process at the end of June, has been charged with manufacturing overhead of $3,400. What was the amount of direct materials charged to Job number 83?
a.$3,400
b.$4,250
c.$7,580
d.$8,350
Calculate ending work in process :
Beginning work in process | 12000 |
Direct material | 50000 |
Direct labor | 30000 |
Applied overhead | 24000 |
Cost of goods manufactured | -100000 |
Ending work in process | 16000 |
Overhead applied = 3400
Direct labor = 3400*100/80 = 4250
Direct material = 16000-3400-4250 = 8350
So answer is d) $8350
Lorrimer Company has a job-order cost system. The following debits (credits) appeared in the Work-in-Process account...
Mary's Landscaping uses a job order cost system. The following debits (credits) appeared in Work- in-Process Inventory for August: August 1 For the month For the month For the month For the month Description Balance Direct materials Direct labor Factory overhead To finished goods Amount $ 12,500 81,000 54,000 43,200 (162,000) Mary's applies overhead to production at a predetermined rate of 80 percent based on direct labor cost. Job 3318, which was started during August and is the only job...
Mary's Landscaping uses a job order cost system. The following debits (credits) appeared in Work-in-Process Inventory for August: Description Amount August 1 Balance $ 13,700 For the month Direct materials 81,100 For the month Direct labor 54,800 For the month Factory overhead 46,032 For the month To finished goods ( 161,800 ) Mary's applies overhead to production at a predetermined rate of 84 percent based on direct labor cost. Job 3318, which was started during August and is the only...
Birk Co. uses a job order costing system. The following debits (credits) appeared in Birk's work-in-process account for the month of April: April Description Amount 1 Balance $ 6,000 30 Direct materials 25,000 30 Direct labor 16,500 30 Factory overhead 13,300 30 To finished goods (49,500) Birk applies overhead to production at a predetermined rate of 80% of direct labor cost. Job No. 5, the only job still in process on April 30 has...
1. Turco Products uses a job order cost system. The following debits (credits) appeared in Work-in-Process Inventory for September: Description Amount September 1 Balance $ 27,300 For the month Direct materials 162,900 For the month Direct labor 101,600 For the month Factory overhead 77,216 For the month To finished goods ( 318,200 ) Turco applies overhead to production at a predetermined rate of 76 percent based on direct labor cost. Job 9-27, the only job still in process at the...
Wojtek Co. has a job order cost system. The following debits (credits) appeared in the work in process account for the month of August: Date Description Amount Aug 1 Opening balance $10205 Aug 31 Direct materials 61133 Aug 31 Direct labour 44893 Aug 31 Manufacturing Overhead 35914.4 Aug 31 To finished goods (124894) Job # 910, the only job still in process at the end of August has been charged with direct materials of $4043. What was the amount of...
Howard Corporation has a job order costing system. The following debits (credits) appear in the firm's work in process account for the month of June: $12 000 $40 000 $30 000 June 1, Balance June 30, Direct materials June 30, Direct labour June 30, overhead applied$27 000 June 30, to finished goods($100 000) Overhead is applied at 90 per cent of direct labour cost. There is only one job still in process at the end of June, and this job...
d overhead ek in Process 39. MK Company uses a job order costing system and applies overhead to jobs at a predetermined a 45% of direct labor cost. For the month of July, the following debits (credits) were in the Work in Pa account: $40,000 Beginning balance Direct materials 200,000 Direct labor 160,000 Manufacturing overhead 72,000 Cost of goods manufactured (438,000) Job A300, the only job in process at the end of July, was charged with manufacturing overhead of $9,000....
Coronado Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $ 24,000, direct labor $ 14,400, and manufacturing overhead $ 19,200. As of January 1, Job 49 had been completed at a cost of $ 108,000 and was part of finished goods inventory....
Pepper Products uses a job costing system. The company applies manufacturing overhead using a predetermined rate based on direct materials. The following debits foredits appeared in Work in Process for April April 1 For the month For the month For the month For the month Balance Direct materials Direct labor Manufacturing overhead To finished goods $37,600 41,800 90,240 (171, eee) Job 1947, the only job still in production at the end of April has been charged $4.600 in direct materials...
Coronado Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On Janu 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $24.000, direct labor $14,400, and manufacturing overhead $19,200. As of January 1, Job 49 had been completed at a cost of $108,000 and was part of finished goods inventory. There was a $18,000...