P8-30 Integrative—Risk, return, and CAPM Wolff Enterprises must consider several investment projects, A through E, using the capital asset pricing model (CAPM) and itsgraphical representation, the security market line (SML). Relevant information is presented in the following table.
Item Rate of return Beta, ?
Risk-free asset 9% 0.00
Market portfolio 14% 1.00
Project A — 1.50
Project B — 0.75
Project C — 2.00
Project D — 0.00
Project E — -0.5

a) Calculate (1) the required rate of return and (2) the risk premium for each project, given its level of nondiversifiable risk.
b) Use your findings in part a) to draw the security market line (required return relative to nondiversifiable risk).
c) Discuss the relative nondiversifiable risk of projects A through E.
d) Assume that recent economic events have caused investors to become less risk- averse, causing the market return to decline by 2%, to 12%. Calculate the new requiredreturns for assets A through E, and draw the new security market line on the same set of axes that you used in part b)
e) Compare your findings in parts a) and b) with those in part d) What conclusion can you draw about the impact of a decline in investor risk aversion on the requiredreturns of risky assets?

1 0
Add a comment Improve this question Transcribed image text
Answer #1

Hi, If you like my answer rate me lifesaver first...that way only I can earn points. Thanks

Market premium = 14% - 9% = 5%

Stock A return = 9% + 0.5 * 5% = 11.5%
Stock B return = 9% + 0.75 * 5% = 12.75%
Stock C return = 9% + 2 * 5% = 19%
Stock D return = 9% + 0 * 5% = 9%
Stock E return = 9% - 0.5 * 5% = 6.5%

SML will be a straight line from 9% to 14% with weights varying from 0 to 100%

Add a comment
Answer #2

a.

1. Required Return = RF + beta* [RM - RF]

= 9% + 1.0 [14% - 9%]

= 9% + 1.0 [5%]

= 9% + 5%

= 14%

2. Risk premium for the market = RM - RF

= 14% - 9%

= 5%



d. RM = 12% - 2% = 10%

Required Return (A) = RF + beta* [RM - RF]

= 9% + 1.50 [10% - 9%]

= 9% + 1.50 [1%]

= 9% + 1.5%

= 10.5%

Required Return (B) = RF + beta* [RM - RF]

= 9% + 0.75 [10% - 9%]

= 9% + 0.75 [1%]

= 9% + 0.75%

= 9.75%

Required Return (C) = RF + beta* [RM - RF]

= 9% + 2 [10% - 9%]

= 9% + 2 [1%]

= 9% + 2%

= 11%

Required Return (D) = RF + beta* [RM - RF]

= 9% + 0 [10% - 9%]

= 9% + 0 [1%]

= 9% + 0%

= 9%

Required Return (E) = RF + beta* [RM - RF]

= 9% + -0.5 [10% - 9%]

= 9% + -0.5 [1%]

= 9% + -0.5%

= 8.5%

Add a comment
Know the answer?
Add Answer to:
Problem
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Wolff Enterprises must consider several investment projects. A through E, using the capital asset pricing model...

    Wolff Enterprises must consider several investment projects. A through E, using the capital asset pricing model (CAPM) and its graphical representation., the security market line (SML). Relevant information is presented in the following table. item rate of return Bets, b risk free asset 9% 0.00 market portfolio 14(1.00 Project A, beta,b(.50, Project B (0.75), Project C, beta,b (2.00), Project D, beta, b(0.00), Project E, beta, b(-0.50) a. calculate (1) the required rate of return and (2) the risk premium for...

  • Integrative—​Risk, return, and CAPM Wolff Enterprises must consider one investment project using the capital asset pricing...

    Integrative—​Risk, return, and CAPM Wolff Enterprises must consider one investment project using the capital asset pricing model​ (CAPM). Relevant information is presented in the following table. Item Rate of return ​Beta, b ​Risk-free asset 10​% 0.00 Market portfolio 14​% 1.00 Project 0.67 a.  Calculate the required rate of return for the​ project, given its level of nondiversifiable risk. b.  Calculate the risk premium for the​ project, given its level of nondiverisifiable risk. Integrative—​Risk, return, and CAPM Wolff Enterprises must consider...

  • Integrative—​Risk, ​return, and CAPM   Wolff Enterprises must consider one investment project using the capital asset pricing...

    Integrative—​Risk, ​return, and CAPM   Wolff Enterprises must consider one investment project using the capital asset pricing model​ (CAPM). Relevant information is presented in the following table. Item Rate of return ​Beta, b ​Risk-free asset 9​% 0.00 Market portfolio 15​% 1.00 Project 1.13 a.  Calculate the required rate of return for the​ project, given its level of nondiversifiable risk. b.  Calculate the risk premium for the​ project, given its level of nondiverisifiable risk. a.  The required rate of return for the...

  • 8. Changes to the security market line Aa Aa E The following graph plots the current...

    8. Changes to the security market line Aa Aa E The following graph plots the current security market line (SML) and indicates the return that investors require from holding stock from Happy Corp. (HC). Based on the graph, complete the table that follows. REQUIRED RATE OF RETURN (Percent) Return on HC's Stock 0.0 0.5 1.0 1.5 2.0 RISK (Beta) Value CAPM Elements Risk-free rate (TRF) Market risk premium (RPM) Happy Corp. stock's beta Required rate of return on Happy Corp....

  • Assignment 08 - Risk and Rates of Return 8. Changes to the security market line The...

    Assignment 08 - Risk and Rates of Return 8. Changes to the security market line The following graph plots the current security market line (SML) and indicates the return that investors require from Molding stock from Happy Corp. (HC). Based on the graph, complete the table that follows REQUIRED RATE OF RETURN Percent Returns RISK (Betal CAPM Elements Value Risk-free rate( ) Market risk premium (RPM) Happy Corp. stock's beta Required rate of retum on Happy Corp. stock An analyst...

  • The following graph plots the current security market line (SML) and indicates the return that investors...

    The following graph plots the current security market line (SML) and indicates the return that investors require from holding stock from Happy Corp. (HC). Based on the graph, complete the table that follows. REQUIRED RATE OF RETURN (Percent) 20.0 16.0 12.0 Return on HC's Stock 8.0 4.0 0.0 0.5 1.0 1.5 2.0 RISK (Betal CAPM Elements Value Risk-free rate (FRF) 4.0% Market risk premium (RPM) 4.4% Happy Corp. stock's beta 2.2% Required rate of return on 7.6% Happy Corp. stock...

  • 8. Changes to the security market line The following graph plots the current security market line...

    8. Changes to the security market line The following graph plots the current security market line (SML) and indicates the return that investors require from holding stock from Happy Corp. (HC). Based on the graph, complete the table that follows. REQUIRED RATE OF RETURN (Percent) 20.0 16.0 12.0 Return on HC's Stock 1 8.0 4.0 0.0 0.5 1.0 1.5 2.0 RISK (Beta) Value CAPM Elements Risk-free rate (PRF) Market risk premium (RPM) Happy Corp. stock's beta Required rate of return...

  • 4. Changes to the security market line The following graph plots the current security market line (SML) and indi...

    4. Changes to the security market line The following graph plots the current security market line (SML) and indicates the return that investors require from holding stock from Happy Corp. (HC). Based on the graph, complete the table that follows. REQUIRED RATE OF RETURN (Percenti 20.0 16.0 Return on HC's Stock 12.0 8.0 4.0 0.0 0.5 10 1.5 2.0 RISK (Betal CAPM Elements Value Risk-free rate (rar) Market risk premium (RPe) Happy Corp. stock's beta Required rate of return on...

  • 8. Changes to the security market line The following graph plots the current security market line...

    8. Changes to the security market line The following graph plots the current security market line (SML) and indicates the return that investors require from holding stock from Happy Corp. (HC). Based on the graph, complete the table that follows. REQUIRED RATE OF RETURN (Percent) 20.0 16.0 12.0 Return on HC's Stock 1 8.0 4.0 0.0 0.5 1.0 1.5 2.0 RISK (Beta) Value CAPM Elements Risk-free rate (PRF) Market risk premium (RPM) Happy Corp. stock's beta Required rate of return...

  • Ch 08: Assignment - Risk and Rates of Return 11. Changes to the security market line...

    Ch 08: Assignment - Risk and Rates of Return 11. Changes to the security market line The following graph plots the current security market line (SML) and indicates the return that investors require from holding stock from Happy Corp. (HC). Based on the graph, complete the table that follows: REQUIRED RATE OF RETURN (Percent) Return on HC's Stock RISK (Beta) Ch 08: Assignment - Risk and Rates of Return RISK (Beta) Value 4.05 CAPM Elements Risk-free rate (TRF) Market risk...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT