Question

16 of 16 (11 complete) HW Score: 56.88%, 11.38 of 20 pts Score: 0 of 1 pt P10-28 (book/static) Question Help Problems with IR

0 0
Add a comment Improve this question Transcribed image text
Answer #1

NPV = present value of cash inflow- the present value of cash outflow.

Discounted at the cost of capital/required rate of return.

NPV must be positive to accept the project.

If the projects are mutually exclusive then the project with highest net present value will be preferred.

a.
NPV at 0% = {1,690,000+[2,225,025/(1.0)^2]}-[3,887,000/(1.0)^1] = $28025

NPV at 5% = {1,690,000+[2,225,025/(1.05)^2]}-[3,887,000/(1.05)^1] = $6258.50

NPV at 7.5% = {1,690,000+[2,225,025/(1.075)^2]}-[3,887,000/(1.075)^1] = -$427.25

NPV at 10% = {1,690,000+[2,225,025/(1.10)^2]}-[3,887,000/(1.10)^1] =- $4772.73

NPV at 15% = {1,690,000+[2,225,025/(1.15)^2]}-[3,887,000/(1.15)^1] = -$7561.44

NPV at 20% = {1,690,000+[2,225,025/(1.20)^2]}-[3,887,000/(1.20)^1] = -4,010.41

NPV at 22.5% = {1,690,000+[2,225,025/(1.225)^2]}-[3,887,000/(1.225)^1] = -$329.03

NPV at 25% = {1,690,000+[2,225,025/(1.25)^2]}-[3,887,000/(1.25)^1] = +$4416

NPV at 30% = {1,690,000+[2,225,025/(1.30)^2]}-[3,887,000/(1.30)^1] = +$16,582.84

b. The NPV profile is decreasing with increase in discount rate. After a certain point it is reversing the trend i.e it is increasing with an increase in discount rate.
So IRR of this project can be ambiguous Because IRR does not measure the absolute return of the project, As IRR is just a relative measure.

c. IRR: It is the discount rate at which the present value of projects cash outflows (cost) is equal to the present value of projects cash inflow.

IRR of the project = {1,690,000+[2,225,025/(1+IRR)^2]}=[3,887,000/(1+IRR)^1]

IRR = 7.31%

The IRR must be above the cost of capital (15%) in order to accept the project.

We need to reject this project as per IRR rule.

The reason why it is difficult to take decision with internal rate of return rule:
The decision taken by IRR rule may not always be correct due to the following reasons as it can have a conflicting issue with other capital budgeting techniques.

The NPV and IRR can lead to a conflicting decision because
1. The distribution of cash flow in the projects.
2. The size of the project.


NPV absolute measure whereas IRR is a relative measure.
NPV gives absolute dollar returns.
IRR are reinvest the cash flow at IRR rate, which is not true and hence not a better technique.

Npv is a better technique then compared to the internal rate of return.

d. the project should not be accepted because net present value is negative (-$7561.44) at 15% discount rate.

Add a comment
Know the answer?
Add Answer to:
16 of 16 (11 complete) HW Score: 56.88%, 11.38 of 20 pts Score: 0 of 1...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problems with IRR White Rock Services Inc. has an opportunity to make an investment with the...

    Problems with IRR White Rock Services Inc. has an opportunity to make an investment with the following projected cash flows. Year         Cash Flow 0              $1,680,000 1              -3,885,000 2              2,225,021 a. Calculate the NPV at the following discount rates and plot an NPV profile for this​ investment: 0​%, 5​%, 7.5​%, 10​%, 15%​, 20​%, 22.5​%, 25​%, 30​%. b. What does the NPV profile tell you about this​ investment's IRR? c. If the company follows the IRR decision rule and their cost of...

  • core: 0 of 2 pts 7-2 (book/static) 7of 10 (3 complete) HW Score: 30%, 6 of...

    core: 0 of 2 pts 7-2 (book/static) 7of 10 (3 complete) HW Score: 30%, 6 of 20 pts E Question Help ou are considering investing in a start up company. The founder asked you for $200,000 today and you expect to get $1,000,000 in 9 years Given the iskiness of the investment opportunity, your cost of capital is 20%. What is the NPV of the investment opportunity? Should you undertake the investment pportunity? Calculate the IRR and use it to...

  • Score: 0 of 2 pts 6 of 8 (0 complete) HW Score: 0%, 0 of 16...

    Score: 0 of 2 pts 6 of 8 (0 complete) HW Score: 0%, 0 of 16 pts i Question Help * Examine the following hypothesis test with n 16, s 5, and x 27 Ho: μ 32 Ha: μ < 32 α : 0.01 a. State the decision rule in terms of the critical value of the test statistic. b. State the calculated value of the test statistic. c. State the conclusion a. State the decision rule. Select the correct...

  • White Rock Services Inc. has an opportunity to make an investment with the following projected cash...

    White Rock Services Inc. has an opportunity to make an investment with the following projected cash flows. Year Cash Flow 0 ​$1600000, - 13887000, 2225025 a. Calculate the NPV at the following discount rates and plot an NPV profile for this​ investment: 0​%, 5​%, 7.5​%, 10​%, 15 %​, 20​%, 22.5​%, 25​%, 30​%.,

  • Score: 0 of 1 pt 5 of 14 (0 complete) v HW Score: 0%, 0 of...

    Score: 0 of 1 pt 5 of 14 (0 complete) v HW Score: 0%, 0 of 14 pts P9-21 (similar to) Question Help Comparing all methods. Given the following after-tax cash flow on a new toy for Tyler's Toys, find the project's payback period, NPV, and IRR. The appropriate discount rate for the project is 8%. If the cutoff period is 6 years for major projects, determine whether management will accept or reject the project under the three different decision...

  • Problems with the IRR method Acme Oscillators is considering an investment project that has the following...

    Problems with the IRR method Acme Oscillators is considering an investment project that has the following rather unusual cash flow pattern. Year AWNIO Cash Flow $100 - 460 793 - 602.3 171.3 a. Calculate the project's NPV at each of the following discount rates: 0%, 5%, 10%, 20%, 30%, 40%, 50%. b. What do the calculations tell you about this project's IRR? The IRR rule tells managers to invest if a project's IRR is greater than the cost of capital....

  • Homework: Assignment 5 Save 1 a 12 concerning to Score: 2.5 of 5 pts 12 of...

    Homework: Assignment 5 Save 1 a 12 concerning to Score: 2.5 of 5 pts 12 of 18 (18 complete) HW Score: 69.32%, 69.32 of 100 pts w Score: 62%, co s % P10-6 (similar to) Question Help NPV for varying costs of capital LePew Cosmetics is evaluating a new fragrance-mixing machine. The machine requires an initial investment of $380,000 and will generate after-tax cash inflows of $62,250 per year for 8 years. If the cost of capital is 13%, calculate...

  •  Acme Oscillators is considering an investment project that has the following rather unusual cash flow pattern....

     Acme Oscillators is considering an investment project that has the following rather unusual cash flow pattern. Year Cash Flow 0 ​$100 1 −460 2 791 3 −602.6 4 171.6 a. Calculate the​ project's NPV at each of the following discount​ rates: 0​%, 5​%, 10​%, 20​%, 30%​, 40​%, 50​%. b. What do the calculations tell you about this​ project's IRR? The IRR rule tells managers to invest if a​ project's IRR is greater than the cost of capital. If Acme​ Oscillators'...

  • 15 20 percem! ll ll IS JU Pellent 12. NPV versus IRR (LO1, 5] Garage, Inc.,...

    15 20 percem! ll ll IS JU Pellent 12. NPV versus IRR (LO1, 5] Garage, Inc., has identified the following tu exclusive projects: Year Cash Flow (A) -$43,500 21,400 18,500 13,800 7,600 Cash Flow (B) -$43,500 6,400 14,700 22,800 25,200 a. What is the IRR for each of these projects? Using the IRR de project should the company accept? Is this decision necessarily con b. If the required return is 11 percent, what is the NPV for each of Which...

  • Acme Oscillators is considering an investment project that has the following rather unusual cash flow pattern....

    Acme Oscillators is considering an investment project that has the following rather unusual cash flow pattern. Year Cash Flow 0 ​$100 1 −460 2 791 3 −602.6 4 171.6 a. Calculate the​ project's NPV at each of the following discount​ rates: 30%​, 40​%, 50​%. b. What do the calculations tell you about this​ project's IRR? The IRR rule tells managers to invest if a​ project's IRR is greater than the cost of capital. If Acme​ Oscillators' cost of capital is...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT