Ans is e - None of the above.
Project A is with negative returns so no point investing there
Project B and Project C both are with Positive returns.
Project B can give positive NPV if discounted at 8.5% which is highest of the range given the question. So this project should be accepted.
0 | 1 | 2 | 3 | NPV | |
PV B | -50 | 32.25806 | 29.73094 | -11.7436 | 0.245378 |
Project C is also with positive NPV if discounted at 7.5% but negative at 8% and above. however as per question range might go somewhere between 0 to 8.5% and 7.5% is in between so this project should be accepted.
0 | 1 | 2 | 3 | NPV | |
PV C | -25 | 16.74419 | 15.57599 | -7.24465 | 0.075528 |
However in options combination of B and C is not given so answer is None of the above.
13. NDR is a company that is deciding between three projects, High, Medium, and Low. The...
5. You are deciding between two mutually exclusive investment projects. Both require the same upfront investment of $9.8 million. Investment A will generate $2 million per year in perpetuity (starting from the end of the first year) and Investment B will generate $1.45 million per year at the end of first year and, after the first year, its revenue will grow at 2.6% per year in perpetuity. The discount rate is 7.8%. a) Which project has a higher IRR? [7.5...
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Year 1 Year 2 Year 3 Year 4 Project A Year 0 - $50 - $100 $27 $19 $18 $38 $21 $49 $17 $58 В a. What are the IRRS of the two projects? b. If your discount rate is 4.8%, what are the NPVS of the two projects? c. Why do IRR and NPV rank the two projects differently?
Walsh Company is considering three independent projects, each of which requires a $4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 16% IRR = 18% Project M (medium risk): Cost of capital = 13% IRR = 12% Project L (low risk): Cost of capital = 7% IRR = 10% Note that the projects' costs of capital vary because the projects have...
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 - $50 $18 $19 $17 - $101 $21 $40 $51 $26 $59 a. What are the IRRs of the two projects? b. If your discount rate is 5.1%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What...
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): a. What are the IRRs of the two projects? The IRR for project A is ______%. (Round to one decimal place.) The IRR for project B is ______%. (Round to one decimal place.) b. If your discount rate is 4.8 %, what are the NPVs of the two projects? If your discount rate is 4.8%, the NPV for project A...
You are choosing between two projects. The cash flows for the projects are given in the following table (s million) Project Year 1 Year 3 Year 0 -$50 - $99 Year 2 $20 $25 $18 Year 4 $16 $19 $442 $49 a. What are the IRRs of the two projects? b. If your discount rate is 53% what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What are the...
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 0 - $49 - $101 Year 1 $26 $18 Year 2 $19 $42 Year 3 $21 $52 Year 4 $17 $61 a. What are the IRRs of the two projects? b. If your discount rate is 5.2%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What...
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 0 - $50 - $100 Year 1 $25 $18 Year 2 $20 $38 Year 3 $19 $48 Year 4 $16 $60 a. What are the IRRs of the two projects? b. If your discount rate is 5.4%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What...
Walsh Company is considering three independent projects, each of which requires a $4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 15% IRR = 22% Project M (medium risk): Cost of capital = 11% IRR = 13% Project L (low risk): Cost of capital = 7% IRR = 8% Note that the projects' costs of capital vary because the projects have...
You are choosing between two projects. The cash flows for the projects are given in the following table (s million): Project Year 0 Year 1 Year 2 - $50 $26 $22 - $98 $18 $41 Year 3 $18 $48 Year 4 $16 $58 a. What are the IRRs of the two projects? b. If your discount rate is 5.2%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently?