Walsh Company is considering three independent projects, each of which requires a $4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here:
Project H (high risk): | Cost of capital = 15% | IRR = 22% |
Project M (medium risk): | Cost of capital = 11% | IRR = 13% |
Project L (low risk): | Cost of capital = 7% | IRR = 8% |
Note that the projects' costs of capital vary because the projects have different levels of risk. The company's optimal capital structure calls for 35% debt and 65% common equity, and it expects to have net income of $14,215,500. If Walsh establishes its dividends from the residual dividend model, what will be its payout ratio? Round your answer to two decimal places.
%
The company is considering three individual projects with varied risks i.e. high risk, medium risk and low risk.
It wants to know the the payout ratio in case of each of the projects based on residual dividend model. In case of residual dividend model cost of equity and IRR are irrelevant.
Company's desired capital structure is 35% Debt and 65% Equity.
Residual dividend is calculated as follow -
Residual Dividend = Net Income - (Target Equity Ratio X Total capital Investment required)
Payout Ratio = Dividend Paid / Total capital Investment
Accordingly, total capital investment required for three projects amount to $4 million X 3 = $12 million.
Expected Net Income = $14,215,500
Dividend = $14,215,500 - ( 65% X 12 million)
= $6,415,500
Payout ratio = $6,415,500 / %12,000,000
= 53%
Walsh Company is considering three independent projects, each of which requires a $4 million investment. The...
Walsh Company is considering three independent projects, each of which requires a $4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 16% IRR = 18% Project M (medium risk): Cost of capital = 13% IRR = 12% Project L (low risk): Cost of capital = 7% IRR = 10% Note that the projects' costs of capital vary because the projects have...
Walsh Company is considering three independent projects, each of which requires a $4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital -15% TRR - 22% Project M (medium risk): Cost of capital -11% IRR = 12% Project L (low risk): Cost of capital - 8% TRR = 7% Note that the projects' costs of capital vary because the projects have different levels...
Walsh Company is considering three independent projects, each of which requires a $4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented below: Project H (High risk) Cost of capital = 15% IRR = 19% Project M (Medium risk) IRR 13% Cost of capital = 12% IRR 11% Cost of capital = 7% Project L (Low risk): Note that the projects' costs of capital vary because the projects have different levels...
Problem Walk-Through RESIDUAL DIVIDEND MODEL Walsh Company is considering three independent projects, each of which requires a $6 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Project M (medium risk): Project L (low risk): Cost of capital-17% Cost of capital-15% Cost of capital = 8% IRR 22% IRR-11% Note that the projects' costs of capital vary because the projects have different levels of risk. The...
RESIDUAL DIVIDEND MODEL Walsh Company is considering three independent projects, each of which requires a $6 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 15% IRR = 19% Project M (medium risk): Cost of capital = 13% IRR = 10% Project L (low risk): Cost of capital = 7% IRR = 9% Note that the projects' costs of capital vary because...
eBook Problem Walk-Through Walsh Company is considering three independent projects, each of which requires a $3 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 17% IRR = 22% Project M (medium risk): Cost of capital = 13% IRR = 11% Project L (low risk): Cost of capital = 8% IRR = 10% Note that the projects' costs of capital vary because...
Lane Industries is considering three independent projects, each of which requires a $3.4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 13% IRR = 15% Project M (medium risk): Cost of capital = 11% IRR = 9% Project L (low risk): Cost of capital = 10% IRR = 11% Note that the projects' costs of capital vary because the projects have...
Sandwich Company is considering five independent projects, each of the project will require a $10 million investment. The estimated IRR and cost of capital for these projects are presented as follows: Project A Cost of capital = 12% RR = 14% Project B Cost of capital = 14% IRR = 12% Project C Cost of capital = 8% IRR = 10% Project D Cost of capital = 9% IRR = 10% Project E Cost of capital = 16,5% IRR =...
16.3-16.6 16-3 16-4 Intermediate Problems 4-6 16-5 STOCK REPURCHASES Beta Industries has net income of $2,000,000, and it has 1,000,000 shares of common stock outstanding. The company's stock currently trades at $32 a share. Beta is considering a plan in which it will use available cash to repurchase 20% of its shares in the open market. The repurchase is expected to have no effect on net income or its stock price. What will be Beta's EPS following the stock repurchase?...
Harris Company must set its investment and dividend policies for the coming year. It has three independent projects from which to choose, each of which requires a $5 million investment. These projects have different levels of risk, and therefore different costs of capital. Their projected IRRs and costs of capital are as follows: Project A: Cost of capital = 15%; IRR = 18% Project B: Cost of capital = 14%; IRR = 9% Project C: Cost of capital = 7%;...