Expected Dividend Pay-out Ratio using residual dividend model
Step-1, Determination of total Investment cost by comparing the Project’s IRR with their cost of capital
We know that the project should be accepted only if the IRR is greater than the cost of capital. Here, the IRR for the Project-A, Project-C and Project-D are greater than their cost of capital and therefore, the Project-A, Project-C, Project-D should be accepted.
Hence, the total Investment cost will be $30,000,000 [$10,000,000 x 2]
Step-2, Calculation of Total Dividend paid
Total Dividend paid using the residual dividend policy is calculated as follows
Total Dividend = Net Income – [Total Capital Budget x Equi ty Ratio]
= $25,000,000 – [$30,000,000 x 50%]
= $25,000,000 - $15,000,000
= $10,000,000
Step-3, The Expected Dividend Pay-out Ratio for this year
Therefore, the Expected Dividend Pay-out Ratio = [Total Dividend Paid / Net Income] x 100
= [$10,000,000 / $25,000,000] x 100
= 40.00%
“Hence, the Expected Dividend Pay-out Ratio will be 40.00%”
Sandwich Company is considering five independent projects, each of the project will require a $10 million...
Walsh Company is considering three independent projects, each of which requires a $4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 16% IRR = 18% Project M (medium risk): Cost of capital = 13% IRR = 12% Project L (low risk): Cost of capital = 7% IRR = 10% Note that the projects' costs of capital vary because the projects have...
Walsh Company is considering three independent projects, each of which requires a $4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital -15% TRR - 22% Project M (medium risk): Cost of capital -11% IRR = 12% Project L (low risk): Cost of capital - 8% TRR = 7% Note that the projects' costs of capital vary because the projects have different levels...
Walsh Company is considering three independent projects, each of which requires a $4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented below: Project H (High risk) Cost of capital = 15% IRR = 19% Project M (Medium risk) IRR 13% Cost of capital = 12% IRR 11% Cost of capital = 7% Project L (Low risk): Note that the projects' costs of capital vary because the projects have different levels...
Walsh Company is considering three independent projects, each of which requires a $4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 15% IRR = 22% Project M (medium risk): Cost of capital = 11% IRR = 13% Project L (low risk): Cost of capital = 7% IRR = 8% Note that the projects' costs of capital vary because the projects have...
Lane Industries is considering three independent projects, each of which requires a $3.4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 13% IRR = 15% Project M (medium risk): Cost of capital = 11% IRR = 9% Project L (low risk): Cost of capital = 10% IRR = 11% Note that the projects' costs of capital vary because the projects have...
RESIDUAL DIVIDEND MODEL Walsh Company is considering three independent projects, each of which requires a $6 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 15% IRR = 19% Project M (medium risk): Cost of capital = 13% IRR = 10% Project L (low risk): Cost of capital = 7% IRR = 9% Note that the projects' costs of capital vary because...
Problem Walk-Through RESIDUAL DIVIDEND MODEL Walsh Company is considering three independent projects, each of which requires a $6 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Project M (medium risk): Project L (low risk): Cost of capital-17% Cost of capital-15% Cost of capital = 8% IRR 22% IRR-11% Note that the projects' costs of capital vary because the projects have different levels of risk. The...
eBook Problem Walk-Through Walsh Company is considering three independent projects, each of which requires a $3 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 17% IRR = 22% Project M (medium risk): Cost of capital = 13% IRR = 11% Project L (low risk): Cost of capital = 8% IRR = 10% Note that the projects' costs of capital vary because...
16.3-16.6 16-3 16-4 Intermediate Problems 4-6 16-5 STOCK REPURCHASES Beta Industries has net income of $2,000,000, and it has 1,000,000 shares of common stock outstanding. The company's stock currently trades at $32 a share. Beta is considering a plan in which it will use available cash to repurchase 20% of its shares in the open market. The repurchase is expected to have no effect on net income or its stock price. What will be Beta's EPS following the stock repurchase?...
Harris Company must set its investment and dividend policies for the coming year. It has three independent projects from which to choose, each of which requires a $5 million investment. These projects have different levels of risk, and therefore different costs of capital. Their projected IRRs and costs of capital are as follows: Project A: Cost of capital = 15%; IRR = 18% Project B: Cost of capital = 14%; IRR = 9% Project C: Cost of capital = 7%;...