Answer :- Dividend Payout Ratio = 20.85%
Calculation :-
We select Project that have IRR > Cost of capital. In our Case Project A & C satifies this. so we take these 2 projects.
Total capital required = 5,000,000 * 2 ==> 10,000,000
Investment = $10,000,000
debt weight = 25%
equity weight = 75%
Net income = $9,476,000
Dividend = Net income - (Investment * equity weight)
Dividend = 9,476,000 - (10,000,000 * 75%)
Dividend = 9,476,000 - 7,500,000
Dividend = $1,976,000
Dividend payout ratio = Dividend / Net income
= 1,976,000 / 9,476,000
= 0.2085 or 20.85%
Harris Company must set its investment and dividend policies for the coming year. It has three...
Problem Walk-Through RESIDUAL DIVIDEND MODEL Walsh Company is considering three independent projects, each of which requires a $6 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Project M (medium risk): Project L (low risk): Cost of capital-17% Cost of capital-15% Cost of capital = 8% IRR 22% IRR-11% Note that the projects' costs of capital vary because the projects have different levels of risk. The...
RESIDUAL DIVIDEND MODEL Walsh Company is considering three independent projects, each of which requires a $6 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 15% IRR = 19% Project M (medium risk): Cost of capital = 13% IRR = 10% Project L (low risk): Cost of capital = 7% IRR = 9% Note that the projects' costs of capital vary because...
Walsh Company is considering three independent projects, each of which requires a $4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 16% IRR = 18% Project M (medium risk): Cost of capital = 13% IRR = 12% Project L (low risk): Cost of capital = 7% IRR = 10% Note that the projects' costs of capital vary because the projects have...
Walsh Company is considering three independent projects, each of which requires a $4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 15% IRR = 22% Project M (medium risk): Cost of capital = 11% IRR = 13% Project L (low risk): Cost of capital = 7% IRR = 8% Note that the projects' costs of capital vary because the projects have...
Walsh Company is considering three independent projects, each of which requires a $4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital -15% TRR - 22% Project M (medium risk): Cost of capital -11% IRR = 12% Project L (low risk): Cost of capital - 8% TRR = 7% Note that the projects' costs of capital vary because the projects have different levels...
Lane Industries is considering three independent projects, each of which requires a $3.4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 13% IRR = 15% Project M (medium risk): Cost of capital = 11% IRR = 9% Project L (low risk): Cost of capital = 10% IRR = 11% Note that the projects' costs of capital vary because the projects have...
Walsh Company is considering three independent projects, each of which requires a $4 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented below: Project H (High risk) Cost of capital = 15% IRR = 19% Project M (Medium risk) IRR 13% Cost of capital = 12% IRR 11% Cost of capital = 7% Project L (Low risk): Note that the projects' costs of capital vary because the projects have different levels...
eBook Problem Walk-Through Walsh Company is considering three independent projects, each of which requires a $3 million investment. The estimated internal rate of return (IRR) and cost of capital for these projects are presented here: Project H (high risk): Cost of capital = 17% IRR = 22% Project M (medium risk): Cost of capital = 13% IRR = 11% Project L (low risk): Cost of capital = 8% IRR = 10% Note that the projects' costs of capital vary because...
Your company has decided that its capital budget during the coming year will be RM15 million. Its optimal capital structure is 60% equity and 40% debt. Its earnings before interest and taxes (EBIT) are projected to be RM26 million for the year. The company has RM150 million of assets; its average interest rate on outstanding debt is 10%; there are 6 million common stocks issued and its tax rate is 40%. a) If the company follows the residual dividend model...
(Dividend Payout): AT&T may be forced to cut its dividend so it is carefully bidding on projects which are profitable. It is currently evaluating 3 projects and AT&T can spend S6 million on each project (for a total of $18 million) if it is profitable. Its 3 projects are: Project WACC IRR 1590 10% 8% 13% 11% 9% Project Fiber Optics Project Data Streaming Project AI If the optimal capital structure is 60% equity financing and net income is projected...