5. Frosty Corporation manufactures and sells custom snowmobiles. From the time an order is placed until...
Navern Corporation manufactures and sells custom home elevators. From the time an order is placed until the time the elevator is installed in the customer’s home averages 90 days. This 90 days is spent as follows: Wait time 40 days Inspection time 2 days Process time 18 days Move time 20 days Queue time 10 days What is Navern's manufacturing cycle efficiency (MCE) for its elevators?
Navern Corporation manufactures and sells custom home elevators. From the time an order is placed until the time the elevator is installed in the customer’s home averages 49 days. This 49 days is spent as follows: Wait time 11 days Inspection time 8 days Process time 10 days Move time 10 days Queue time 10 days What is Navern's manufacturing cycle efficiency (MCE) for its elevators? Multiple Choice 36.7% 26.3% 63.3% 57.1%
Santoyo Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below. Wait time Process time Inspection time Move time Queue time Hours 12.9 2.0 0.4 4.6 6.3 The delivery cycle time was: Multiple Choice 0 10.9 hours O 23 8 hours Schapp Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below. Move time Wait time Queue time Process time Inspection time...
to fill orders. Data concerning 5) Santoyo Corporation keeps careful track of the time required to a particular order appear below: Hours 28.0 1.0 Inspection time 0.4 Move time 3.2 Queue time Wait time Process time 5.1 The delivery cycle time was: A) 8.3 hours B) 3.2 hours C) 37.7 hours D) 36.3 hours 35) Simkin Corporation keeps careful track of the time required to fill orders. Data concem a particular order appear below: Hours 20.6 1.9 0.1 Wait time...
2. Schurz Corporation's management reports that its average delivery cycle time is 36 days, its average throughput time is 14.0 days, its manufacturing cycle efficiency (MCE) is 0.50, its average move time is 0.6 day, and its average queue time is 2.2 days. Required: a. What is the wait time? (Round your answer to 1 decimal place.) b. What is the process time? (Round your answer to 1 decimal place.) c. What is the inspection time? (Round your intermediate calculations...
Simkin Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below. Hours 21.9 5.8 Wait time Process time Inspection time Move time Queue time 4.0 The manufacturing cycle efficiency (MCE) was closest to:
Schapp Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below: Hours 4.6 12.4 Move time Wait time Queue time Process time Inspection time 8.8 3.5 2.4 The throughput time was: Multiple Choice 19.3 hours 31.7 hours 0 212 hours 10.5 hours
Santoyo Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: Hours Wait time 13.7 Process time 2.8 Inspection time 0.4 Move time 3.4 Queue time 7.1 The delivery cycle time was: Multiple Choice 10.5 hours 3.4 hours 27.4 hours 24.2 hours
Vandenheuvel Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below: Hours Move time 3.3 Wait time 19.7 Queue time 9.9 Process time 1.7 Inspection time 0.9 The manufacturing cycle efficiency (MCE) was closest to: 0.11 0.31 0.19 0.05
4. During the most recent month at Hybarger Corporation, queue time was 3.0 days, inspection time was 0.8 day, process time was 2.8 days, wait time was 11.8 days, and move time was 0.6 day. Required: (15%) a. Compute the throughput time. b. Compute the manufacturing cycle efficiency (MCE). c. What percentage of the production time is spent in non-value-added activities? d. Compute the delivery cycle time.