2. How much
manufacturing overhead was applied to Job P and how much was
applied to Job Q?
Solution 2:
Total estimated Overhead = (2500*1.40) + (1500*2.20) + $25000 = $31,800
Predetermined Overhead rate = $31800/ 4000 = $7.95 per Machine hour
Overhead assigned to Job P = 2300* $7.95 = $18,285
Overhead assigned to Job Q = 1700* $7.95 = $13,515
2. How much manufacturing overhead was applied to Job P and how much was applied to Job...
1. What was the company’s plantwide predetermined overhead
rate?
1a. How much manufacturing overhead was applied to Job P and how
much was applied to Job Q? (Do not round intermediate
calculations.)
b. What was the total manufacturing cost assigned to Job P?
(Do not round intermediate calculations.)
2a. If Job P included 20 units, what was its unit product cost?
(Do not round intermediate calculations. Round your final
answer to nearest whole dollar.)
2b. What was the total manufacturing...
10. How much manufacturing overhead was applied from the Molding
Department to Job P and how much was applied to Job Q? (Do
not round intermediate calculations.)
11. How much manufacturing overhead was applied from the
Fabrication Department to Job P and how much was applied to Job Q?
(Do not round intermediate calculations.)
12. If Job P included 20 units, what was its unit product cost?
(Do not round intermediate calculations.)
13. If Job Q included 30 units, what...
10. How much manufacturing overhead was applied from the Molding
Department to Job P and how much was applied to Job Q? (Do
not round intermediate calculations.)
11. How much manufacturing overhead was applied from the
Fabrication Department to Job P and how much was applied to Job Q?
(Do not round intermediate calculations.)
12. If Job P included 20 units, what was its unit product cost?
(Do not round intermediate calculations.)
13. If Job Q included 30 units, what...
1. what was the companys plantwide predetermined overhead
rate?
2.How much manufacturing overhead was applied to Job P and how
much was applied to Job Q?
3.What was the total manufacturing cost assigned to Job
P?
4.If Job P included 20 units, what was its unit product
cost?
5.What was the total manufacturing cost assigned to Job
Q?
6. If Job Q included 30 units, what was its unit product
cost?
7.
8. what was Sweeten Companys cost of goods...
3. What was the total
manufacturing cost assigned to Job P
Required information (The following information applies to the questions displayed below.] Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments --Molding and Fabrication. It started, completed, and sold only two jobs during March-Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all...
4. If Job P included 20 units,
what was its unit product cost?
Required information (The following information applies to the questions displayed below.] Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments --Molding and Fabrication. It started, completed, and sold only two jobs during March-Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and...
The Foundational 15 (LO2-1, LO2-2, LO2-3, LO2-4) [The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the...
3. what was the total of manufacturing cost assigned to job
P?
4. if job P included 20units, what was its unit produced
cost?
5. what was the total manufacturing cost assigned to job
Q?
6. if job Q included 30 units, what was its unit product
cost?
------------------ The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments...
help me please
Required information The Foundational 15 (LO2-1, LO2-2, LO2-3, LO2-4) (The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March, Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total machine-hours used Estimated total fixed manufacturing overhead Estimated variable manufacturing overhead...