Question

E14.12 (LO 3) Cepeda Corporation has the following cost records for June 2020. Prepare a cost of goods manufactured schedule

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer - (a)

CEPEDA CORPORATION

Cost of Goods Manufactured Schedule

For the Month Ended June 30, 2020

Calculation Amount ($) Amount ($) Amount ($)
Work in Process, 6/1/20 Given in question - - 3000
Direct Materials used Given in question - 20000 -
Direct Labor Given in question - 40000 -
Manufacturing Overhead: - - - -
Indirect Factory Labor Given in question 4500 - -
Factory Utilities Given in question 400 - -
Depreciation, Factory Equipment Given in question 1400 - -
Maintenance, Factory Equipment Given in question 1800 - -
Indirect Materials Given in question 2200 - -
Factory manager's salary Given in question 3000 - -
Total Manufacturing Overhead $4500+$400+$1400+$1800+$2200+$3000 - 13300 -
Total Manufacturing Cost $20000 + $40000 + $13300 - - 73300
Total Cost of WIP $3000 + $73300 - - 76300
Less: Work in Process, 6/30/20 Given in question - - 3800
Cost of Goods Manufactured $76300 - $3800 72500
Add a comment
Know the answer?
Add Answer to:
E14.12 (LO 3) Cepeda Corporation has the following cost records for June 2020. Prepare a cost...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • E14.12 (LO 3) Cepeda Corporation has the following cost records for June 2020. Prepare a cost...

    E14.12 (LO 3) Cepeda Corporation has the following cost records for June 2020. Prepare a cost of goods manufactured schedule and a partial income statement. > Excel Indirect factory labor Direct materials used Work in process, 6/1/20 Work in process, 6/30/20 Finished goods, 6/1/20 Finished goods, 6/30/20 $ 4,500 20,000 3,000 3,800 5,000 7,500 Factory utilities Depreciation, factory equipment Direct labor Maintenance, factory equipment Indirect materials Factory manager's salary $ 400 1,400 40,000 1,800 2,200 3,000 Instructions b. Prepare an...

  • *Exercise 10-12 (Part Level Submission) Cepeda Corporation has the following cost records for June 2017 Indirect...

    *Exercise 10-12 (Part Level Submission) Cepeda Corporation has the following cost records for June 2017 Indirect factory labor Direct materials used Work in process, 6/1/17 Work in process, 6/30/17 Finished goods, 6/1/17 Finished goods, 6/30/17 $4,500 20,000 3,000 3,800 5,000 7,500 Factory utilities Depreciation, factory equipment Direct labor Maintenance, factory equipment Indirect materials Factory manager's salary $400 1,400 40,000 1,800 2,200 3,000 *(a) Prepare a cost of goods manufactured schedule for June 2017. CEPEDA CORPORATION Cost of Goods Manufactured Schedule...

  • Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $4,600 Factory utilities...

    Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $4,600 Factory utilities $410 1.500 Direct materials used 21,000 Depreciation, factory equipment 41,000 Work in process. 6/1/20 Work in process, 6/30/20 3,100 Direct labor 3.900 Maintenance, factory equipment 1.810 Finished goods, 6/1/20 Finished goods, 6/30/20 5.100 7,600 Indirect materials Factory manager's salary 2,100 3,100 Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost of Goods Manufactured Schedule

  • Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $5.330 Factory utilities...

    Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $5.330 Factory utilities $440 Direct materials used Work in process, 6/1/20 22,580 3,910 Depreciation, factory equipment Direct labor 1,640 42,770 Work in process, 6/30/20 Finished goods, 6/1/20 Finished goods, 6/30/20 4,680 5,510 ,270 Maintenance, factory equipment Indirect materials Factory manager's salary 1,940 2.430 3.210 8 Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost of Goods Manufactured Schedule

  • Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $4,760 Factory utilities...

    Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $4,760 Factory utilities $470 Direct materials used 22,680 Depreciation, factory equipment 1,540 Work in process, 6/1/20 3,540 Direct labor 42,930 Work in process, 6/30/204,880 Maintenance, factory equipment 1,850 Finished goods, 6/1/20 5,940 Indirect materials 2,820 Finished goods, 6/30/20 7,940 Factory manager's salary 3,120 (a) Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost of Goods Manufactured Schedule Save for Later

  • Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $5,150 Factory utilities...

    Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $5,150 Factory utilities $500 Direct materials used 22,360 Depreciation, factory equipment 1,620 Work in process, 6/1/20 3,480 Direct labor 42,170 Work in process, 6/30/20 4,620 Maintenance, factory equipment 2,000 5,660 Indirect materials 2,600 Finished goods, 6/1/20 Finished goods, 6/30/20 7,680 Factory manager's salary 3,340 Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost of Goods Manufactured Schedule $ We were unable to transcribe...

  • Cepeda Corporation has the following cost records for June 2020. Indirect factory labor Direct materials used...

    Cepeda Corporation has the following cost records for June 2020. Indirect factory labor Direct materials used Work in process, 6/1/20 Work in process, 6/30/20 Finished goods, 6/1/20 Finished goods, 6/30/20 $4,750 21,330 3,400 4,540 6,090 8,470 Factory utilities Depreciation, factory equipment Direct labor Maintenance, factory equipment Indirect materials Factory manager's salary $440 1,590 42,300 1,900 2,140 3,360 Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost of Goods Manufactured Schedule For the Year Ended June 30,...

  • Exercise 14-12 Cepeda Corporation has the following cost records for June 2020. Indirect factory labor Direct...

    Exercise 14-12 Cepeda Corporation has the following cost records for June 2020. Indirect factory labor Direct materials used Work in process, 6/1/20 Work in process, 6/30/20 Finished goods, 6/1/20 Finished goods, 6/30/20 $5,000 Factory utilities 22,910 Depreciation, factory equipment 3,690 Direct labor 4,170 Maintenance, factory equipment 5,350 Indirect materials 8,480 Factory manager's salary $430 1,790 41,860 1,960 2,540 3,330 Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost of Goods Manufactured Schedule << ব য য...

  • part B) Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $4,690...

    part B) Cepeda Corporation has the following cost records for June 2020. Indirect factory labor $4,690 Factory utilities $430 Direct materials used 22,410 Depreciation factory equipment 1,770 Work in process, 6/1/20 3,970 Direct labor 42,100 Work in process, 6/30/20 4,410 Maintenance, factory equipment 1,910 2,810 Finished goods, 6/1/20 Finished goods, 6/30/20 5,650 Indirect materials 8,030 Factory manager's salary 3,930 Your Answer Correct Answer Your answer is correct. Prepare a cost of goods manufactured schedule for June 2020. CEPEDA CORPORATION Cost...

  • Ex. 2 Cepeda Corporation has the following cost records for June 2018 Indirect factory labor $...

    Ex. 2 Cepeda Corporation has the following cost records for June 2018 Indirect factory labor $ 4,500 Factory utilities $ 400 Direct materials used 20,000 Depreciation, factory equipment 1,400 Work in process, 6/1/18 3,000 Direct labor 40,000 Work in process, 6/30/18 3,800 Maintenance, factory equipment 1,800 Finished goods, 6/1/18 5,000 Indirect materials 2,200 Finished goods, 6/30/18 7,500 Factory manager’s salary 3,000 . Instructions a. Prepare a cost of goods manufactured schedule for June 2018. b. Prepare an income statement through...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT