1). OCF = (Sales*(Price per unit - Variable cost per unit) - Fixed cost)*(1-Tax rate) + (Depreciation*Tax rate)
Depreciation = initial cost/life = 837,790/8 = 104,723.75
OCF = (62,239*(36-19) - 424,751)*(1-35%) + (104,723.75*35%) = 448,306.11 (This is the OCF with VC = 19)
Now, assume that VC = 20.
New OCF = (62,239*(36-20) - 424,751)*(1-35%) + (104,723.75*35%) = 407,850.76
Change in OCF = new OCF - old OCF = 407,850.76 -448,306.11 = 40,455.35 (Ignore negative sign as we are measuring sensitivity)
Change in VC = 20-19 = 1
Sensitivity of OCF to VC = (Change in OCF/change in VC)% = 4,045,535.00%
6). Best-case NPV = 1,145,743.95
Formula | Base case | Formula | Best case | |
Initial Outlay (IO) | 680,403 | 680,403 | ||
Life (n) | 5 | 5 | ||
IO/n | Depreciation (D) | 136,080.60 | 136,080.60 | |
Sales (S) | 45,496 | Sbase-case*(1+10%) | 50,045.60 | |
Price per unit (P) | 45 | Pbase-case*(1+10%) | 49.50 | |
Variable cost per unit (VC) | 26 | VCbase-case*(1-10%) | 23.40 | |
Fixed cost (FC) | 525,466 | FCbase-case*(1-10%) | 472,919.40 | |
Tax rate (T) | 30% | 30% | ||
(S*(P-VC)-FC)*(1-T)+(D*T) | OCF | 278,094.78 | 624,113.71 | |
Return | 21% | 21% | ||
Using PV function with OCF | Present Value of OCF (PV) | 813,700.97 | 1,826,146.95 | |
PV - IO | NPV | 133,297.97 | 1,145,743.95 |
Need help solving these questions We are evaluating a project that costs $837,790, has an eight-year...
Need help solving these questions
We are evaluating a project that costs $836,117, has an eight-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 63,362 units per year. Price per unit is $38, variable cost per unit is $16, and fixed costs are $424,469 per year. The tax rate is 35 %, and we require a return of 18% on this project. Calculate the Financial...
We are evaluating a project that costs $842,060, has an eight-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 60,726 units per year. Price per unit is $38, variable cost per unit is $17, and fixed costs are $415,433 per year. The tax rate is 35%, and we require a return of 20% on this project. Calculate the Accounting Break-Even Point. (Round answer to 0...
We are evaluating a project that costs $837,434, has an eight-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 56,652 units per year. Price per unit is $39, variable cost per unit is $19, and fixed costs are $421,397 per year. The tax rate is 35%, and we require a return of 21% on this project. Calculate the Accounting Break-Even Point. We are evaluating a...
We are evaluating a project that costs $841,297, has an eight-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 62,152 units per year. Price per unit is $40, variable cost per unit is $21, and fixed costs are $422,878 per year. The tax rate is 35%, and we require a return of 19% on this project. In dollar terms, what is the sensitivity of NPV...
We are evaluating a project that costs $838917, has an eight-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 61793 units per year. Price per unit is $36, variable cost per unit is $16, and fixed costs are $417398 per year. The tax rate is 35%, and we require a return of 19% on this project. In percentage terms, what is the sensitivity of NPV...
We are evaluating a project that costs $788,400, has a nine-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 75,000 units per year. Price per unit is $52, variable cost per unit is $36, and fixed costs are $750,000 per year. The tax rate is 21 percent, and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...
We are evaluating a project that costs $898,000, has an eight-year life, and has no salvage value. Assume that depreciation is straight- line to zero over the life of the project. Sales are projected at 88,000 units per year. Price per unit is $66, variable cost per unit is $48, and fixed costs are $782,000 per year. The tax rate is 35%, and we require a 10% return on this project. Suppose the projections given for price, quantity, variable costs,...
We are evaluating a project that costs $1,710,000, has a life of 6 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 86,400 units per year. Price per unit is $38.01, variable cost per unit is $23.25, and fixed costs are $818,000 per year. The tax rate is 21 percent, and we require a return of 9 percent on this project. Suppose the projections given for...
We are evaluating a project that costs $500,000, has an eight-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 50,000 units per year. Price per unit is $50, variable cost per unit is $25, and fixed costs are $600,000 per year. The tax rate is 35 percent, and we require a return of 12 percent on this project. b-2 What is the sensitivity of NPV...
We are evaluating a project that costs $924,000, has an eight-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 75,000 units per year. Price per unit is $46, variable cost per unit is $31, and fixed costs are $825,000 per year. The tax rate is 35 percent, and we require a 15 percent return on this project. Suppose the projections given for price, quantity, variable...