Question

Current Attempt in Progress Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented be
0 0
Add a comment Improve this question Transcribed image text
Answer #1

297 answers

Case A Case B
Direct materials used                         $ 69,150 (a) $93,600
Direct labor 54,000 146,500
Manufacturing overhead applied 32,400 87,900 (d)
Total manufacturing costs 155,550 328,000 (e)
Work in process 1/1/20 49,750 (b) 23,900
Total cost of work in process 205,300 351,900 (f)
Work in process 12/31/20 7,300 (c) 16,600
Cost of goods manufactured    198,000 $335,300 (g)

(a) Direct materials used    = Total manufacturing costs - Direct labor - Manufacturing overhead applied
                                               = 155550- 54000-32400 = $69150
b)

Total cost of work in process = Total manufacturing costs + Work in process 1/1/20                        

Work in process 1/1/20      = Total cost of work in process - Total manufacturing costs
                                                 = $ 205,300 - 155,550 = 49,750

(c)

Cost of goods manufactured = Total cost of work in process - Work in process 12/31/20
Work in process 12/31/20 = Total cost of work in process - Cost of goods manufactured
                                                = 205,300 -198,000 = 7,300

(d) Predetermined Overhead Rate in case 1 = Manufacturing Overhead Applied/ Direct Labor
                                                               = $ 32,400/54,000 = 60%

as in all cases Manufacturing overhead is applied on basis of direct labor hour

Manufacturing overhead applied in case 2 = Predetermined Overhead Rate x direct Labor Hour
                                                                             = 60% x 146,500 = $87,900

(e) Total manufacturing costs in case 2 = Direct materials used + Direct labor + Manufacturing overhead applied
                                                                          = $93600 + 146,500 + 87900 = $328,000

(f) Total cost of work in process (case 2)= Total manufacturing costs + Work in process 1/1/20    
                                                                           = 328,000 + 23,900 = $ 351,900

(g) Cost of goods manufactured (case 2) = Total cost of work in process - Work in process 12/31/20
                                                                       = $ 351,900 - 16,600 = $335300                                                                                                                                                                                                                                                    
                                                                       
                                                            


                                                                                                                                                                                                                                                                         
                                                 
                                                              

Add a comment
Know the answer?
Add Answer to:
Current Attempt in Progress Manufacturing cost data for Orlando Company, which uses a job order cost...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below....

    Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below. Indicate the missing amount for each letter. Assume that in all cases manufacturing overhead is applied on the basis of direct labor cost and the rate is the same. (Round overhead rate to 2 decimal places, e.g. 15.25 and final answers to O decimal places, e.g. 5,275.) Case A Case B Direct materials used $93,600 Direct labor 54,000 146,500 Manufacturing overhead applied 32,400 Total...

  • Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below....

    Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below. Indicate the missing amount for each letter. Assume that in all cases manufacturing overhead is applied on the basis of direct labor cost and the rate is the same. (Round overhead rate to 2 decimal places, e.g. 15.25 and final answers to O decimal places, e.g. 5,275.) Case A Case B Direct materials used $ (a) $93,600 Direct labor 54,000 146,500 Manufacturing overhead applied...

  • Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below....

    Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below. Indicate the missing amount for each letter. Assume that in all cases manufacturing overhead is applied on the basis of direct labor cost and the rate is the same. (Round overhead rate to 2 decimal places, e.g. 15.25 and final answers to 0 decimal places, e.g. 5,275.) Case A Case B $92,500 (a) Direct materials used 58150 54,000 Direct labor 143,200 | (d) Manufacturing...

  • Manufacturing cost data for Vaughn Company, which uses a job order cost system, are presented below....

    Manufacturing cost data for Vaughn Company, which uses a job order cost system, are presented below. Indicate the missing amount for each letter. Assume that in all cases manufacturing overhead is applied on the basis of direct labor cost and the rate is the same. (Round overhead rate to 2 decimal places, e.g. 15.25 and final answers to O decimal places, e.g. 5,275.) Case A Case B Case C Direct materials used $92,100 $63,150 Direct labor 54,000 149,000 3 Manufacturing...

  • Manufacturing cost data for Vaughn Company, which uses a job order cost system, are presented below....

    Manufacturing cost data for Vaughn Company, which uses a job order cost system, are presented below. Indicate the missing amount for each letter. Assume that in all cases manufacturing overhead is applied on the basis of direct labor cost and the rate is the same. (Round overhead rate to 2 decimal places, e.g. 15.25 and final answers to 0 decimal places, e.g. 5,275.) Case A Case B Case C Direct materials used % $92,100 $63.150 Direct labor 54,000 149,000 Manufacturing...

  • Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below....

    Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below. Indicate the missing amount for each letter. Assume that in all cases manufacturing overhead is applied on the basis of direct labor cost and the rate is the same. (Round overhead rate to 2 decimal places, e.g. 15.25 and final answers to O decimal places, e.g. 5,275.) Case A Case B Direct materials used $ 69150 (a) $84,200 Direct labor 50,000 145,200 Manufacturing overhead...

  • Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below....

    Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below. Indicate the missing amount for each letter. Assume that in all cases manufacturing overhead is applied on the basis of direct labor cost and the rate is the same. (Round overhead rate to 2 decimal places, eg. 15.25 and final answers to 0 decimal places, e.g. 5,275.) Case A Case B Direct materials used $92,500 Direct labor 54.000 143,200 Manufacturing overhead applied 40,500 Total...

  • Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below....

    Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below. Indicate the missing amount for each letter. Assume that in all cases manufacturing overhead is applied on the basis of direct labor cost and the rate is the same. (Round overhead rate to 2 decimal places, e.g. 15.25 and final answers to 0 decimal places, e.g. 5,275.) Case A Case B Direct materials used $84,200 Direct labor 50,000 145,200 Manufacturing overhead applied 30,000 Total...

  • Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below...

    Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below Indicate fie missing amount for each letter. Assume that in all cases manufacturing overhead is applied on the basis of direct labor cost and the rate is the same. overhead rate to 2 decimal places, e.g. 15.25 and final answers to 0 decimal places, e.g. 5,275.) Case A Case C Direct materials used Direct labor Manufacturing overhead applied $88,000 $66,650 8,000 46,400 147,950 150,700...

  • Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below....

    Manufacturing cost data for Orlando Company, which uses a job order cost system, are presented below. Indicate the missing amount for each letter. Assume that in all cases manufacturing overhead is applied on the basis of direct labor cost and the rate is the same. (Round overhead rate to 2 decimal places, e.g. 15.25 and final answers to 0 decimal places, e.g. 5,275.) Case A Case B Direct materials used $ (a) $88,000 Direct labor 58,000 150,700 Manufacturing overhead applied...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT