Canal Authority is evaluating a new project and has estimated the following cash flows:
Year 0 = -$2,478,000 Year 1 = $1,389,000 Year 2 = $1,076,000 Year 3 = $876,000 Canal Authority’s cost of capital is 12%.
Calculate the following:
1. NPV
2. IRR
3. MIRR
4. Indicate whether the Canal Authority should accept or reject this project.
Canal Authority is evaluating a new project and has estimated the following cash flows: Year 0...
IBM is evaluating a project in Eutopia. The project will create the following cash flows: Year $ 0 -1,330,000 1 250,000 2 470,000 3 450,000 4 215,000 5 95,000 All cash flows will occur in Eutopia and are expressed in dollars. In an attempt to improve its economy, the Eutopia’s government has declared that all cash flows created by a foreign company are “blocked” and must be reinvested with the government for one year. The reinvestment rate for these funds...
Jumbo Enterprises is evaluating an investment project with project cash flows (millions) as indicated below. The firm's cost of capital is 7.5%. What is the NPV and IRR of this project? WACC: Year Cash flows (Smillions) 7.5% 0 $350 1 $50 2 75 3 $120 4 $160 5 $190 a. NPV=$100, IRR= 16.45% b. NPV=110.16, IRR=7.5% C. NPV=110.16, IRR=16.45% d. NPV=120.5, IRR=16.45% e. NPV=5245, IRR=21.50%
Consider Project Theta, its time line of cash flows, and one of the project IRRs: Year....................0.............1............2............IRR Cash Flow......($200).....$850....($700)......15% What is the best decision for Project Theta (accept or reject) if the project’s required rate of return is 15% and why? a. Accept the project because the payback is short b. Accept the project because the NPV is greater than zero c. Reject the project because the IRR is less than the required rate of return d. Reject the project because...
Mittuch Corp. is evaluating a project with the following cash flows: Year Cash Flow 0 –$ 16,200 1 7,300 2 8,500 3 8,100 4 6,900 5 –4,300 The company uses an interest rate of 12 percent on all of its projects. Calculate the MIRR of the project using all three methods. (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) MIRR Discounting approach % Reinvestment approach % Combination approach %
Chronic Pain Clinic has estimated the following cash flows associated with a new project. The project cost of capital is 10 percent. Year Expected Net Cash Flow 0.............. ($800,000) 1.............. 400,000 2............... 400,000 3................. 400,000 What it the project’s NPV?
Management of TSC, Inc. is evaluating a new $75,000 investment
with the following estimated cash flows:
Year
Cash Flow
1
$
13,000
2
35,000
3
40,000
4
56,000
The firm’s cost of capital is 8 percent and the project will
require that the firm spend $18,000 to terminate the project. Use
Appendix B to answer the question. Use a minus sign to enter a
negative value, if any. Round your answer to the nearest
dollar.
The NPV of the investment...
Management of TSC, Inc. is evaluating a new $89,000 investment with the following estimated cash flows: Year Cash Flow 1 $ 16,000 2 22,000 3 43,000 4 63,000 The firm’s cost of capital is 14 percent and the project will require that the firm spend $30,000 to terminate the project. Use Appendix B to answer the question. Use a minus sign to enter a negative value, if any. Round your answer to the nearest dollar. The NPV of the investment...
Vital Silence, Inc., has a project with the following cash flows: Year Cash Flow 0 –$ 27,400 1 11,400 2 14,400 3 10,400 The required return is 16 percent. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) IRR % Should the firm accept the project? Accept Reject
Assume a new project requires an initial investment of $6 million dollars, with ensuing cash flows of $1, $3 and $5 million in years 1, 2 and 3. Assuming the company's WACC is 10%, which of the following statements is true? The firm should accept the project, as the IRR is lower than the WACC. The firm should reject the project, as the IRR is higher than the WACC. The firm should accept the project, as the NPV is positive....
Comparing all methods. Risky Business is looking at a project
with the following estimated cash flow:. Risky Business wants to know
the payback period, NPV, IRR, MIRR, and PI of this project. The
appropriate discount rate for the project is 12%.
If the cutoff period is 66 years for major projects, determine
whether the management at Risky Business will accept or reject the
project under the five different decision models.
What is the payback period for the new project at...