1 | Cost of Land | |||||||||
$ | ||||||||||
Acquisition cost | 620000 | |||||||||
Broker's commission | 44640 | |||||||||
Legal fees | 7440 | |||||||||
Title insurance | 22320 | |||||||||
Building razing cost | 66960 | |||||||||
Total | 761360 | |||||||||
2 | Cost of Building | |||||||||
$ | ||||||||||
Fixed-price contract | 3720000 | |||||||||
Plans, specifications, and blueprints | 26040 | |||||||||
Architects’ fees | 101680 | |||||||||
Interst capitalized in 2018 | (Note:1) | 134333 | ||||||||
Interst capitalized in 2019 | (Note:1) | 176700 | ||||||||
Total | 4158753 | |||||||||
Note:1 | ||||||||||
Interest to be capitalized=Accumulated building construction contract*Interest rate of loan taken for construction | ||||||||||
2018 | Interest to be capitalized=1612000*10%*10/12=$134333 | (For 10 months-Mar to Dec) | ||||||||
2019 | Interest to be capitalized=2356000*10%*9/12=$ 176700 | (For 9 months-Jan to Sep) | ||||||||
Question 9 --/1 View Policies Current Attempt in Progress On January 1, 2020, Blue Corporation purchased...
On January 1, 2020, Marin Corporation purchased for $720,000 a tract of land (site number 101) with a building. Marin paid a real estate broker's commission of $51,840, legal fees of $8,640, and title guarantee insurance of $25,920. The closing statement indicated that the land value was $720,000 and the building value was $144,000. Shortly after acquisition, the building was razed at a cost of $77,760. Marin entered into a $4,320,000 fixed-price contract with Slatkin Builders, Inc. on March 1,...
On January 1, 2020, Marigold Corporation purchased for $680.000 a tract of land (site number 101) with a building Marigold paid a real estate broker's commission of $48,960, legal fees of $8,160, and title guarantee insurance of $24.480. The dosing statement indicated that the land value was $680,000 and the building value was $136,000. Shortly after acquisition, the building was razed at a cost of $73,440. Marigold entered into a $4,080,000 fixed-price contract with Slatkin Builders, Inc. on March 1,...
Problem 10-5 On January 1, 2020, Sheridan Corporation purchased for $680,000 a tract of land (site number 101) with a building. Sheridan paid a real estate broker’s commission of $48,960, legal fees of $8,160, and title guarantee insurance of $24,480. The closing statement indicated that the land value was $680,000 and the building value was $136,000. Shortly after acquisition, the building was razed at a cost of $73,440. Sheridan entered into a $4,080,000 fixed-price contract with Slatkin Builders, Inc. on...
On January 1, 2021, the Blackstone Corporation purchased a tract of land (site number 11) with a building for $740,000. Additionally, Blackstone paid a real estate broker's commission of $50,000, legal fees of $8,000, and title insurance of $25,000. The closing statement indicated that the land value was $570,000 and the building value was $170,000. Shortly after acquisition, the building was razed at a cost of $89,000. Blackstone entered into a $4,400,000 fixed-price contract with Barnett Builders, Inc., on March...
On January 1, 2021, the Blackstone Corporation purchased a tract of land (site number 11) with a building for $630,000. Additionally, Blackstone paid a real estate broker's commission of $39,000, legal fees of $7,500, and title insurance of $19,500. The closing statement indicated that the land value was $515,000 and the building value was $115,000. Shortly after acquisition, the building was razed at a cost of $78,000. Blackstone entered into a $3,300,000 fixed-price contract with Barnett Builders, Inc., on March...
On January 1, 2018, the Blackstone Corporation purchased a tract of land (site number 11) with a building for $620,000. Additionally, Blackstone paid a real estate broker's commission of $38,000, legal fees of $7,000, and title insurance of $19,000. The closing statement indicated that the land value was $510,000 and the building value was $110,000. Shortly after acquisition, the building was razed at a cost of $77,000. Blackstone entered into a $3,200,000 fixed-price contract with Barnett Builders, Inc., on March...
On January 1, 2021, the Blackstone Corporation purchased a tract of land (site number 11) with a building for $740,000. Additionally, Blackstone paid a real estate broker's commission of $50,000, legal fees of $8,000, and title insurance of $25,000. The closing statement indicated that the land value was $570,000 and the building value was $170,000. Shortly after acquisition, the building was razed at a cost of $89,000. Blackstone entered into a $4,400,000 fixed-price contract with Barnett Builders, Inc., on March...
On January 1, 2021, the Blackstone Corporation purchased a tract of land (site number 11) with a building for $740,000. Additionally, Blackstone paid a real estate broker's commission of $50,000, legal fees of $8,000, and title insurance of $25,000. The closing statement indicated that the land value was $570,000 and the building value was $170,000. Shortly after acquisition, the building was razed at a cost of $89,000. Blackstone entered into a $4,400,000 fixed-price contract with Barnett Builders, Inc., on March...
Chapter 11 wepreciation Depreciation m oglimento poinment, and Disposol and ding for sive on Bröding's valce insuradditional 2019. Brock Corporation purchased a tracto of 536,0Value was,000,019, for the conock enterede was Sicc of $18, Boock paid a real estate broker's comd that the lat a cost March occupied orporation purchased a tract Comprehensive On January 2, 2019, Brock building for S600,000. Additionally, Brock paida and title guarantee insurance of Buarantee insurance of si8.000. The closing ilding's value was $100,000. Shortly...
On March 1, 2021, Beldon Corporation purchased land as a factory site for $71,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2021. Costs incurred during this period are listed below: Demolition of old building $ 9,500 Architect’s fees (for new building) 10,000 Legal fees for title investigation of land 7,500 Property taxes on land (for period beginning March 1, 2021) 4,100 Construction costs 610,000 Interest on...