Send to Gradebook Question 2 View Policies Current Attempt in Progress Labor data for making one gallon of finished product i
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution a:

Standard direct labor rate per hour = $15 + $0.60 + 1.70 = $17.30 per hour

Solution b:

Standard direct labor hour per gallon = 1.60 + 0.30 + 0.20 = 2.10 hour

Solution c:

Standard labor cost per gallon = Standard hour per gallon * Standard rate per hour = 2.10 * $17.30 = $36.33 per unit

Add a comment
Know the answer?
Add Answer to:
Send to Gradebook Question 2 View Policies Current Attempt in Progress Labor data for making one...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • CH 24 HW 7th e(**) Send to Gradebook Question 8 View Policies Current Attempt in Progress...

    CH 24 HW 7th e(**) Send to Gradebook Question 8 View Policies Current Attempt in Progress Labor data for making one gallon of finished product in Bing Company are as follows. (1) Price-hourly wage rate $16.70, payroll taxes $0.60, and fringe benefits $1.40. (2) Quantity-actual production time 1.60 hours, rest periods and cleanup 0.30 hours, and setup and downtime 0.20 hours. Compute the following (Round answers to 2 decimal places, eg. 1.25) (a) Standard direct labor rate per hour. (b)...

  • Send to Gradebook < Prev Nons --/1 Question 7 View Policies Current Attempt in Progress Stefani...

    Send to Gradebook < Prev Nons --/1 Question 7 View Policies Current Attempt in Progress Stefani Company has gathered the following information about its product. Direct materials. Each unit of product contains 5.00 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 1.00 pounds. Materials cost $1 per pound, but Stefani always takes the 5.00% cash discount all of its suppliers offer. Freight costs average 50.25 per pound. Direct labor. Each unit requires 1.70...

  • Question 1 View Policies Current Attempt in Progress Tang Company accumulates the following data concerning raw...

    Question 1 View Policies Current Attempt in Progress Tang Company accumulates the following data concerning raw materials in making its finished product: (1) Price per pound of raw materials-net purchase price $2.50, freight- in $0.30, and receiving and handling $0.20. (2) Quantity per gallon of finished product-required materials 3.60 pounds, allowance for waste and spoilage 0.90 pounds. Compute the following. (Round answers to 2 decimal places, e.g. 1.25.) (a) Standard direct materials price per pound of raw materials. $ (b)...

  • Send to Gradebook < Prev I Next > --/18 Question 2 View Policies Current Attempt in...

    Send to Gradebook < Prev I Next > --/18 Question 2 View Policies Current Attempt in Progress Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.10 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.70 pounds. Materials cost $5 per pound, but Stefani always takes the 5.00% cash discount all of its suppliers offer. Freight costs average $0.45 per pound. Direct labor. Each unit...

  • Labor data for making one gallon of finished product in Bing Company are as follows. (1)...

    Labor data for making one gallon of finished product in Bing Company are as follows. (1) Price-hourly wage rate $17.22, payroll taxes $0.84, and fringe benefits $1.76. (2) Quantity -actual production time 1.72 hours, rest periods and deanup 0.26 hours, and setup and downtime 0.18 hours Compute the following (Round answers to 2 decimal place . 1.25.) (a) Standard direct labor rate per hour. (b) Standard direct labor hours per gallon. (c) Standard labor cost per gallon

  • Labor data for making one gallon of finished product in B ng Company are as follows...

    Labor data for making one gallon of finished product in B ng Company are as follows 1 Price hourly wage rate $17.74, payroll taxes $0.52, and fringe benefits $1.50 2 uantity actual production time 1.26 hours, rest periods and cleanup 0.26 hours, and setup and downtime 0.26 hours. Compute the following. (Round answers to 2 decimal places, e.g. 1.25.,) (a) Standard direct labor rate per hour (b) Standard direct labor hours per gallon. (c) Standard labor cost per gallon. hours

  • Labor data for making one gallon of finished product in Bing Company are as follows. (1) Price-hourly wage rate $17...

    Labor data for making one gallon of finished product in Bing Company are as follows. (1) Price-hourly wage rate $17.22, payroll taxes $0.84, and fringe benefits $1.76. (2) Quantity -actual production time 1.72 hours, rest periods and deanup 0.26 hours, and setup and downtime 0.18 hours Compute the following (Round answers to 2 decimal place . 1.25.) (a) Standard direct labor rate per hour. (b) Standard direct labor hours per gallon. (c) Standard labor cost per gallon

  • Question 1 View Policies Current Attempt in Progress Stefani Company has gathered the following information about...

    Question 1 View Policies Current Attempt in Progress Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.40 pounds of materials. The average waste and spollage per unit produced under normal conditions is 0.60 pounds. Materials cost $2 per pound, but Stefani always takes the 2.00% cash discount all of its suppliers offer. Freight costs average $0.25 per pound. Direct labor. Each unit requires 1.00 hours of labor. Setup, cleanup, and downtime...

  • Question 2 --/18 View Policies Current Attempt in Progress Stefani Company has gathered the following information...

    Question 2 --/18 View Policies Current Attempt in Progress Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.40 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.60 pounds. Materials cost $5 per pound, but Stefani always takes the 4.00% cash discount all of its suppliers offer. Freight costs average $0.40 per pound. Direct labor. Each unit requires 1.00 hours of labor. Setup, cleanup, and...

  • Question 2 View Policies Show Attempt History Current Attempt In Progress Metlock Services, Inc. is trying...

    Question 2 View Policies Show Attempt History Current Attempt In Progress Metlock Services, Inc. is trying to establish the standard labor cost of a typical brake repair. The following data have been collected from time and motion studies conducted over the past month Actualtime spent on the brake repairs 3 hours Hourly wage rate $13 Payroll taxes 10% of wage rate Setup and downtime 12% of actualibor time Cleanup and rest periods 28% of actual labor time Fringe benefits 20%...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT