Question

During year​ 1, Fox Co. started a construction job with a contract price of​ $1,500,000. The...

During year​ 1, Fox Co. started a construction job with a contract price of​ $1,500,000. The job was completed in year 2 and the company uses the percentage of completion method. The following information is available for year 1 and year​ 2:
Year 1 Year 2
Cost incurred to date $350,000 $1,100,000
Estimated cost to complete 650,000 0
Billings to date 300,000 1,100,000
Collections to date 100,000 1,000,000


What amount of gross profit should Fox recognize for this job for year 2?
Group of answer choices
$400,000
$225,000
$325,000
$260,000
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

The  gross profit should Fox recognize for this job for year 2 is $225,000

Working

Year 1 end

Year 2 End

A

Contract Price

$       1,500,000

$       1,500,000

B

Cost Incurred to Date

$           350,000

$       1,100,000

C

Estimated cost yet to be incurred to complete the contract

$       650,000

$                            -  

D = B+C

Total Cost

$       1,000,000

$       1,100,000

E = (B/D) x 100

% of Completion

35.00%

100.00%

F = A x E

Revenue to date

$           525,000

$       1,500,000

G

Revenue of Previous year

$                            -  

$          525,000

H = F - G

Net Revenue this year

$           525,000

$       975,000

I (=B)

Cost to date

$           350,000

$       1,100,000

J

Cost to date of previous year

$                            -  

$          350,000

K = I - J

Net Cost for the year

$           350,000

$       750,000

L = H - K

Gross Profits

$           175,000

$          225,000  Answer

Add a comment
Know the answer?
Add Answer to:
During year​ 1, Fox Co. started a construction job with a contract price of​ $1,500,000. The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job...

    During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $400,000 $825,000 $1,070,000 Estimated costs to complete 600,000 275,000 –0– Billings to date 300,000 900,000 1,600,000 Collections to date 270,000 810,000 1,425,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized...

  • During 2020, Riverbed Company started a construction job with a contract price of $1,600,000. The job was complete...

    During 2020, Riverbed Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2022 2020 2021 Costs incurred to date $404,000 $830,680 $1,069,000 Estimated costs to complete -0 606,000 262,320 Billings to date 300,000 906,000 1,600,000 Collections to date 272,000 810,000 1,416,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 Gross profit recognized in...

  • During 2020, Sunland Company started a construction job with a contract price of $1,590,000. The job...

    During 2020, Sunland Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete 2020 2021 2022 $410,000 $901,180 $1,067,000 590,000 197,820 -0- 297,000 903,000 .590,000 271,000 805,000 1,434,000 Billings to date Collections to date ✓ Your answer is correct Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in...

  • During 2017, Crane Company started a construction job with a contract price of $ 1,610,000. The...

    During 2017, Crane Company started a construction job with a contract price of $ 1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $ 366,300 $ 772,100 $ 1,063,000 Estimated costs to complete 623,700 330,900 –0– Billings to date 300,000 909,000 1,610,000 Collections to date 271,000 807,000 1,424,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017...

  • During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job...

    During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 –0– Billings to date 301,000 897,000 1,610,000 Collections to date 271,000 817,000 1,428,000 A) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ 258,000 Gross...

  • During 2020, Oriole Company started a construction job with a contract price of $1,590,000. The job...

    During 2020, Oriole Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete Billings to date Collections to date 2020 $366,300 623,700 297,000 270,000 2021 $831,440 262,560 894,000 816,000 2022 $1,067,000 -0- 1,590,000 1,417,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...

  • During 2020, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job...

    During 2020, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $396,000 $806,600 $1,080,000 Estimated costs to complete 594,000 283,400 -0- Billings to date 301,000 268,000 892,000 816,000 1,590,000 1,427,000 Collections to date Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...

  • During 2017, Cullumber Company started a construction job with a contract price of $1,610,000. The job...

    During 2017, Cullumber Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 -0- 1,610,000 Billings to date 301.000 897,000 271,000 1428,000 Collections to date 817,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used $ Gross profit recognized in 2017 $ Gross profit...

  • During 2020, Stellar Company started a construction job with a contract price of $1,620,000. The job...

    During 2020, Stellar Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $373,700 $749,360 $1,070,000 Estimated costs to complete 636,300 352,640 –0– Billings to date 302,000 907,000 1,620,000 Collections to date 268,000 815,000 1,425,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...

  • During 2020, Pearl Company started a construction job with a contract price of $1,590,000. The job...

    During 2020, Pearl Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $396,000 $806,600 $1,080,000 Estimated costs to complete 594,000 283,400 –0– Billings to date 301,000 892,000 1,590,000 Collections to date 268,000 816,000 1,427,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT