  • Working

Actual result

Flexible Budget

Planning Budget

Machine hours

                        18,000

                      18,000

                    20,000

Utilities

$      16,500.00

+ (

$      0.18

   18,000

)

$               21,900.00

$             19,740.00

$          20,100.00

Maintenance

$      38,800.00

+

$      1.40

   18,000

)

$               60,600.00

$             64,000.00

$          66,800.00

Supplies

$                      -  

+

$      0.60

   18,000

)

$               11,800.00

$             10,800.00

$          12,000.00

Indirect Labor

$      94,400.00

+

$     1.80

   18,000

)

$            131,300.00

$           126,800.00

$        130,400.00

Depreciation

$      67,600.00

)

$           -  

   18,000

$               69,300.00

$             67,600.00

$          67,600.00

Total Expenses

$            294,900.00

$           288,940.00

$        296,900.00

  • [1] Activity Variance = Difference between ‘Flexible’ and ‘planning’ budget

Activity Variance

Machine hours

Utilities

$                360.00

Favourable

Maintenance

$            2,800.00

Favourable

Supplies

$            1,200.00

Favourable

Indirect Labor

$            3,600.00

Favourable

Depreciation

$                         -  

None

Total Expenses

$            7,960.00

Favourable

  • [2] Spending Variance = Difference between ‘Actual’ and ‘Flexible’

Spending Variance

Machine hours

Utilities

$         2,160.00

Unfavourable

Maintenance

$         3,400.00

Favourable

Supplies

$         1,000.00

Unfavourable

Indirect Labor

$         4,500.00

Unfavourable

Depreciation

$         1,700.00

Unfavourable

Total Expenses

$         5,960.00

Unfavourable

Add a comment
Know the answer?
Add Answer to:
Looking for variances for March! Please help! You have just been hired by FAB Corporation, the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door...

    You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis,...

  • You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door...

    You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis,...

  • You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door...

    You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis,...

  • You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door...

    You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis,...

  • You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door...

    You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. points After much effort and...

  • You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door...

    You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company’s costing system and “do what you can to help us get better control of our manufacturing overhead costs.” You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis,...

  • You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door...

    You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis,...

  • You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door...

    You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company’s costing system and “do what you can to help us get better control of our manufacturing overhead costs.” You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis,...

  • You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door...

    You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control After much effort and analysis,...

  • You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door...

    You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company’s costing system and “do what you can to help us get better control of our manufacturing overhead costs.” You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT