Journal Entry:
Account Titles and Explanations | Debit | Credit |
Land | $156,000 | |
Demolition and Removal Costs | $21,700 | |
Clearing, Grading and Filing Costs | $15,400 | |
Recovery of Salvaged Building Materials | $10,200 | |
Cash ($156,000 + $21,700 + $15,400 - $10,200) | $182,900 | |
(To record purchase of land by cash and payment of other costs to demolish the building) |
Stellar Pharmaceuticals purchased land for $156,000 to build its new headquarters. The land has an old...
Flounder Pharmaceuticals purchased land for $160,400 to build its new headquarters. The land has an old building on it. The demolition and removal costs of the old building paid were $20,300 and the recovery of salvaged building materials was $9,700. The cost of clearing, grading and filling is $15,600 and the closing costs are $9,600. Prepare the appropriate journal entry for the land, demolition and other costs assuming the company pays cash. (Credit account titles are automatically indented when the...
Cheyenne Pharmaceuticals purchased land for $150,200 to build its new headquarters. The land has an old building on it. The demolition and removal costs of the old building paid were $20,100 and the recovery of salvaged building materials was $9,100. The cost of clearing, grading and filling is $16,100 and the closing costs are $10,100. Prepare the appropriate journal entry for the land, demolition and other costs assuming the company pays cash.
On March 1, 2021, Beldon Corporation purchased land as a factory site for $71,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2021. Costs incurred during this period are listed below: Demolition of old building $ 9,500 Architect’s fees (for new building) 10,000 Legal fees for title investigation of land 7,500 Property taxes on land (for period beginning March 1, 2021) 4,100 Construction costs 610,000 Interest on...
On March 1, 2021, Beldon Corporation purchased land as a factory site for $75,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2021. Costs incurred during this period are listed below: Demolition of old building$6,500Architect’s fees (for new building)14,000Legal fees for title investigation of land3,000Property taxes on land (for period beginning March 1, 2021)4,500Construction costs650,000Interest on construction loan7,500 Salvaged materials resulting from the demolition of the old building were...
Terrabyte Corporation purchased land as a factory site and contracted with Mordor Construction to construct a factory. Terrabyte made the following expenditures related to the acquisition of the land, building, and equipment to equip the factory: Purchase price of the land Demolition and removal of old building Clearing and grading the land before construction Various closing costs in connection with acquiring the land Architect's fee for the plans for the new building Payments to Mordor for building construction Equipment purchased...
Question 1) A company purchased land adjacent to its existing property to build a warehouse. The company's maintenance crew and additional temporary employees built the warehouse. In addition, the company took out a $40,000 construction loan, which was repaid with a new loan after construction was completed. Which of the following statements is true? All costs associated with building the warehouse should be expensed as incurred. Materials costs should be capitalized to the building account, but all labor and interest...
Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a factory. Teradene made the following expenditures related to the acquisition of the land, building, and equipment for the factory: (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided.): Purchase price of the land $ 1,330,000 Demolition and removal of old building 93,000 Clearing and grading the land...
Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a factory. Teradene made the following expenditures related to the acquisition of the land, building, and equipment for the factory: (FV of $1, P of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided.): Purchase price of the land Demolition and removal of old building Clearing and grading the land before construction Various...
Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a factory. Teradene made the following expenditures related to the acquisition of the land, building, and equipment for the factory. (EV of $1. PV of $1. EVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided. Purchase price of the land Demolition and removal of old building Clearing and grading the land before construction Various...
Cala Manufacturing purchases land for $359,000 as part of its plans to build a new plant. The company pays $25,100 to tear down an old building on the lot and $37,104 to fill and level the lot. It also pays construction costs $1,714,700 for the new building and $108,237 for lighting and paving a parking area. Prepare a single journal entry to record these costs incurred by Cala, all of which are paid in cash. View transaction list Journal entry...