The following account appears in the ledger after only part of the postings have been completed for March Work in Progress Ba

0 0
Add a comment Improve this question Transcribed image text
Answer #1
General Journal Debit Credit
Work in process inventory $417,000
Raw material inventory $417,000
Work in process inventory $210,000
Wages payable $210,000
Work in process inventory $84,000
Factory overhead (210,000*40%) $84,000
Factory overhead $79,500
Cash $79,500
Finished goods inventory $692,000
Work in process inventory $692,000
Add a comment
Know the answer?
Add Answer to:
The following account appears in the ledger after only part of the postings have been completed...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. The following account appears in the ledger after only nart of the after only part...

    1. The following account appears in the ledger after only nart of the after only part of the postings have been completed for March, the first month of the current fiscal year: Balance, March 1 Direct materials Direct labor Work in Process 182,000 417,000 210,000 Factory overhead is applied to jobs at the rate of 40% of direct labor cost. The actual factory overhead incurred for March was $79,500. Jobs completed during the month totaled $692,100. (a) Prepare the journal...

  • 2. The following account appears in the ledger after only part of the postings have been...

    2. The following account appears in the ledger after only part of the postings have been completed for July the first month of the current fiscal year: Work in Process July | Balance 28.200 Direct materials2 74. CCO Direct labor 152,000 Factory overhead is applied to jobs at the rate of 40% of direct labor cost. The actual factory overhead incurred for July was $58,000. Jobs completed during the month totaled $298,200. (a) What is the balance of the factory...

  • The following account appears in the ledger after only part of the postings have been completed...

    The following account appears in the ledger after only part of the postings have been completed for July, the first month of the current fiscal year: Work in Process Duly1 Balance Direct materials Direct labor 60,200 147,000 120,000 Factory overhead is applied to jobs at the rate of 60% of direct labor cost. The actual factory overhead incurred for July was $75,000. Jobs completed during the month totaled $301,200. a. Prepare the journal entries to record (1) the application of...

  • Recording jobs completed The following account appears in the ledger after only part of the postings...

    Recording jobs completed The following account appears in the ledger after only part of the postings have been completed for October: Work in Process Balance, October 1 $12,520 Direct materials 85,140 Direct labor 101,410 Factory overhead 56,340 Jobs finished during October are summarized as follows: Job 1004 $45,970 Job 1030 28,100 Job 1037 53,640 Job 1041 89,390 a. Determine the cost of jobs completed. b. Determine the cost of the unfinished jobs at October 31.

  • The following account appears in the ledger prior to recognizing the jobs completed in August: Work...

    The following account appears in the ledger prior to recognizing the jobs completed in August: Work in Process Balance, August 1 $ 60,000 Direct materials 325,000 Direct labor 462,000 Factory overhead 210,000 Jobs finished during August are summarized as follows: Job 210 $197,800 Job 216 240,000 Job 224 160,000 Job 230 364,000 Required: A. Journalize the entry on Aug. 31 to record the jobs completed. Refer to the Chart of Accounts for exact wording of account titles. B. Determine the...

  • Entry for Jobs Completed; Cost of Unfinished Jobs The following account appears in the ledger prior...

    Entry for Jobs Completed; Cost of Unfinished Jobs The following account appears in the ledger prior to recognizing the jobs completed in January: Work in Process Balance, January 1 Direct materials $9,240 75,120 81,030 Direct labor Factory overhead 42,600 Jobs finished during January are summarized as follows: $37,440 22,880 Job 210 Job 216 Job 224 Job 230 43,680 76,960 a. Journalize the entry to record the jobs completed. b. Determine the cost of the unfinished jobs at January 31.

  • The following account appears in the ledger prior to recognizing the jobs completed in January: Work...

    The following account appears in the ledger prior to recognizing the jobs completed in January: Work in Process Balance, January 1 $10,510 Direct materials 85,450 Direct labor 92,170 Factory overhead 48,450 Jobs finished during January are summarized as follows: Job 210 $42,580    Job 224 $49,680 Job 216 26,020    Job 230 89,900 a. Journalize the entry to record the jobs completed. If an amount box does not require an entry, leave it blank. b. Determine the cost of the...

  • Entry for Jobs Completed; Cost of Unfinished Jobs The following account appears in the ledger prior...

    Entry for Jobs Completed; Cost of Unfinished Jobs The following account appears in the ledger prior to recognizing the jobs completed in January: Work in Process $85,800 Balance, January 1 Direct materials Direct labor 115,000 140,000 296,200 Factory overhead Jobs finished during January are summarized as follows: Job 210 $182,500 Job 216 78,300 Job 224 Job 230 $232,190 67,250 ) a. Journalize the entry to record the jobs completed. If an amount box does not require an entry, leave it...

  • Entry for Jobs Completed; Cost of Unfinished Jobs The following account appears in the ledger prior...

    Entry for Jobs Completed; Cost of Unfinished Jobs The following account appears in the ledger prior to recognizing the jobs completed in January: Work in Process Balance, January 1 $9,420 Direct materials 76,580 Direct labor 82,610 Factory overhead 43,430 Jobs finished during January are summarized as follows: Job 210 $38,170 Job 224 $44,530 Job 216 23,320 Job 230 86,940 a. Journalize the entry to record the jobs completed. If an amount box does not require an entry, leave it blank....

  • The following account appears in the ledger prior to recognizing the jobs completed in August: Work...

    The following account appears in the ledger prior to recognizing the jobs completed in August: Work in Process Balance, August 1 $ 63,300 Direct materials 349,700 Direct labor 457,400 Factory overhead 226,700 Jobs finished during August are summarized as follows: Job 210 $182,500 Job 216 238,250 Job 224 157,300 Job 230 349,550 Required: a. Journalize the entry on Aug. 31 to record the jobs completed. Refer to the Chart of Accounts for exact wording of account titles. b. Determine the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT