Question

eBook Calculator Unit Cost and Cost Assignment, Nonuniform Inputs Loran-Inc. had the following equivalent units schedule and
61.00 51.195.000 3. Dalh of its reserved and Colofono in proces (Previous Next > Seda seesmert for Grading BN
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution 1:

Loran Inc.
Computation of Cost per equivalent unit -Fabrication department
Particulars Material Conversion Total
Opening WIP $147,000 $7,875 $154,875
Cost Added during Period $1,195,000 $446,425 $1,641,425
Total cost to be accounted for $1,342,000 $454,300 $1,796,300
Equivalent units of production 241000 215380
Cost per Equivalent unit $5.57 $2.11

solution 2:

Loran Inc.
Computation of Cost of ending WIP and units completed & transferred out - Fabrication Department
Particulars Material Conversion Total
Equivalent unit of Ending WIP 61000 35380
Cost per equivalent unit $5.57 $2.11
Cost of Ending WIP (Equivalent unit * Cost per equivalent unit) $339,770 $74,652 $414,422
Units completed and transferred 180000 180000
Cost of units completed & Transferred (Unit completed * cost per equivalent unit) $1,002,600 $379,800 $1,382,400
Add a comment
Know the answer?
Add Answer to:
eBook Calculator Unit Cost and Cost Assignment, Nonuniform Inputs Loran-Inc. had the following equivalent units schedule...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Hello! Will someone please help me solve this problem? I cannot figure it out and could use some assistance. Unit Cost...

    Hello! Will someone please help me solve this problem? I cannot figure it out and could use some assistance. Unit Cost and Cost Assignment, Nonuniform Inputs Loran Inc. had the following equivalent units schedule and cost for its fabrication department during September: Materials Conversion Units completed 180,000 180,000 Add: Units in ending WIP x Fraction complete 72,000 41,040 (72,000 x 57%) Equivalent units of output 252,000 221,040 Costs: Work in process, September 1: Materials $147,000 Conversion costs 7,875 Total $154,875...

  • QUESTION 4 Nonuniform Inputs, Weighted Average Carter Inc. had the following production and cost information for...

    QUESTION 4 Nonuniform Inputs, Weighted Average Carter Inc. had the following production and cost information for its fabrication department during April (with materials added at the beginning of the fabrication process): Production: Units in process, April 1, 50% complete with respect to conversion 10,000 Units completed 65,200 Units in process, April 30, 60% complete 12,000 Costs: Work in process, April 1: Materials $40,980 Conversion costs 14,600    Total $55,580 Current costs: Materials $125,000 Conversion costs 210,000    Total $335,000 Carter uses the...

  • part 3 Nonuniform Inputs, Weighted Average Carter Inc. had the following production and cost information for...

    part 3 Nonuniform Inputs, Weighted Average Carter Inc. had the following production and cost information for its fabrication department during April (with materials added at the beginning of the fabrication process): Production: Units in process, April 1, 50% complete with respect to conversion 10,000 Units completed 65,200 Units in process, April 30, 60% complete 12,000 Costs: Work in process, April 1: Materials $40,980 Conversion costs 14,600    Total $55,580 Current costs: Materials $125,000 Conversion costs 210,000    Total $335,000 Carter uses the...

  • Nonuniform Inputs, Equivalent Units Terry Unens Inc, manufactures bed and bath linens. The bath linens department...

    Nonuniform Inputs, Equivalent Units Terry Unens Inc, manufactures bed and bath linens. The bath linens department sews terry cloth into towels of various sizes. Terry uses the weighted average method. All materials are added at the beginning of the process. The following data are for the bath linens department for August: Production: 17,500 61,000 Units in process, August 1, 25% complete Units completed and transferred out Units in process, August 31, 66% complete - With respect to conversion costs. 27,250...

  • NEED HELP WITH ALL PARTS 1-3 ebook Calculator Nonuniform Inputs Apeto Company produces premium chocolate candy...

    NEED HELP WITH ALL PARTS 1-3 ebook Calculator Nonuniform Inputs Apeto Company produces premium chocolate candy bars. Conversion costs are added uniformly. For February, EWIP is 40 percent complete with respect to conversion costs. Materials are added at the beginning of the process. The following information is provided for February Physical flow schedule Units to account for: Units in WWTP Units started 70,000 Tetal units to account for 70,000 Units accounted for Units completed From BWP 0 Started and completed...

  • Weighted Average Method, Physical Flow, Equivalent Units, Unit Costs, Cost Assignment, ABC Swasey Fabrication, Inc., manufactures...

    Weighted Average Method, Physical Flow, Equivalent Units, Unit Costs, Cost Assignment, ABC Swasey Fabrication, Inc., manufactures frames for bicycles. Each frame passes through three processes: Cutting, Welding, and Painting. In September, the Cutting Department of the Tulsa, Oklahoma, plant reported the following data: In Cutting, all direct materials are added at the beginning of the process. Beginning work in process consisted of 41,500 units, 20 percent complete with respect to direct labor and overhead. Costs in beginning inventory included direct...

  • Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for...

    Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for its Sewing Department for the month of December: Direct Materials         Conversion Costs   Units started and completed 49,000 49,000   Add: Units in beginning work in process ×          Percentage complete:          6,000 × 0% direct materials —          6,000 × 50% conversion Costs 3,000   Add: Units in ending work in process ×          Percentage complete:          10,000 × 100% direct materials 10,000 —          10,000 × 35% conversion Costs —...

  • Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for...

    Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for its Sewing Department for the month of December: Direct Materials         Conversion Costs   Units started and completed 49,000 49,000   Add: Units in beginning work in process ×          Percentage complete:          6,000 × 0% direct materials —          6,000 × 50% conversion Costs 3,000   Add: Units in ending work in process ×          Percentage complete:          10,000 × 100% direct materials 10,000 —          10,000 × 35% conversion Costs —...

  • Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for...

    Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for its Sewing Department for the month of December: Direct Materials Conversion Costs Units started and completed 40,000 40,000 Add: Units in beginning work in process × Percentage complete: 5,000 × 0% direct materials — 5,000 × 50% conversion Costs 2,500 Add: Units in ending work in process × Percentage complete: 12,000 × 100% direct materials 12,000 — 12,000 × 35% conversion Costs — 4,200...

  • FIFO Method, Physical Flow, Equivalent Units, Unit Costs, Cost Assignment Swasey Fabrication, Inc., manufactures frames for...

    FIFO Method, Physical Flow, Equivalent Units, Unit Costs, Cost Assignment Swasey Fabrication, Inc., manufactures frames for bicycles. Each frame passes through three processes: Cutting, Welding, and Painting. In September, the Cutting Department of the Tulsa, Oklahoma, plant reported the following data: In Cutting, all direct materials are added at the beginning of the process. Beginning work in process consisted of 41,000 units, 20 percent complete with respect to direct labor and overhead. Costs in beginning inventory included direct materials, $1,215,000;...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT