Question

Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for...

Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for its Sewing Department for the month of December: Direct Materials Conversion Costs Units started and completed 40,000 40,000 Add: Units in beginning work in process × Percentage complete: 5,000 × 0% direct materials — 5,000 × 50% conversion Costs 2,500 Add: Units in ending work in process × Percentage complete: 12,000 × 100% direct materials 12,000 — 12,000 × 35% conversion Costs — 4,200 Equivalent units of output 52,000 46,700 Costs: Work in process, December 1: Direct Material $65,000 Conversion Costs 10,000 Total work in process $75,000 Current costs: Direct Material $728,000 Conversion Costs 140,100 Total current costs $868,100 Required: 1. Calculate the unit cost for December, using the FIFO method. $ per equivalent unit 2. Calculate the cost of goods transferred out, calculate the cost of EWIP, and reconcile the costs assigned with the costs to account for. Cost of goods transferred out $ Cost of EWIP $ Cost to account for: BWIP $ Current (December) Total $ 3. What if you were asked for the unit cost from the month of November? Calculate November's unit cost. $ per equivalent unit

0 0
Add a comment Improve this question Transcribed image text
Answer #1

solution Materials = 728000 / 52000 = 14 Conversion = 140100 / 46700 = 3 Cost per equivalent unit = 17 Cost of goods transfer

Add a comment
Know the answer?
Add Answer to:
Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for...

    Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for its Sewing Department for the month of December: Direct Materials Conversion Costs Units started and completed 40,000 40,000 Add: Units in beginning work in process × Percentage complete: 5,000 × 0% direct materials — 5,000 × 50% conversion Costs 2,500 Add: Units in ending work in process × Percentage complete: 12,000 × 100% direct materials 12,000 — 12,000 × 35% conversion Costs — 4,200...

  • Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for...

    Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for its Sewing Department for the month of December: Direct Materials         Conversion Costs   Units started and completed 49,000 49,000   Add: Units in beginning work in process ×          Percentage complete:          6,000 × 0% direct materials —          6,000 × 50% conversion Costs 3,000   Add: Units in ending work in process ×          Percentage complete:          10,000 × 100% direct materials 10,000 —          10,000 × 35% conversion Costs —...

  • Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for...

    Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for its Sewing Department for the month of December: Direct Materials         Conversion Costs   Units started and completed 49,000 49,000   Add: Units in beginning work in process ×          Percentage complete:          6,000 × 0% direct materials —          6,000 × 50% conversion Costs 3,000   Add: Units in ending work in process ×          Percentage complete:          10,000 × 100% direct materials 10,000 —          10,000 × 35% conversion Costs —...

  • Gunnison Company had the following equivalent units schedule and cost information for its Sewing Department for...

    Gunnison Company had the following equivalent units schedule and cost information for its Sewing Department for the month of December: Direct Materials         Conversion Costs   Units started and completed 49,000 49,000   Add: Units in beginning work in process ×          Percentage complete:          6,000 × 0% direct materials —          6,000 × 50% conversion Costs 3,000   Add: Units in ending work in process ×          Percentage complete:          10,000 × 100% direct materials 10,000 —          10,000 × 35% conversion Costs — 3,500   Equivalent units of...

  • Cost Information and the Weighted Average Method Morrison Company had the equivalent units schedule and cost...

    Cost Information and the Weighted Average Method Morrison Company had the equivalent units schedule and cost information for its Sewing Department for the month of December, as shown below. Direct Materials Conversion Costs Units completed 40,000 40,000 Add: Units in ending work in process × Percentage complete: 10,000 × 100% direct materials 10,000 — 10,000 × 40% conversion materials — 4,000 Eqivalent units of output 50,000 44,000 Costs: Work in process, December 1: Direct materials $62,000 Conversion costs 12,000 Total...

  • Morrison Company had the equivalent units schedule and cost information for its Sewing Department for the...

    Morrison Company had the equivalent units schedule and cost information for its Sewing Department for the month of December, as shown below. Direct Materials Conversion Costs Units completed 46,000 46,000 Add: Units in ending work in process ×      Percentage complete:         10,000 × 100% direct materials 10,000 —         10,000 × 40% conversion materials — 4,000 Eqivalent units of output 56,000 50,000 Costs:         Work in process, December 1:           Direct materials $66,000           Conversion costs 11,000           Total...

  • Cost Information and the Weighted Average Method Morrison Company had the equivalent units schedule and cost...

    Cost Information and the Weighted Average Method Morrison Company had the equivalent units schedule and cost information for its Sewing Department for the month of December, as shown below. Direct Materials Conversion Costs Units completed 46,000 46,000 Add: Units in ending work in process ×      Percentage complete:         10,000 × 100% direct materials 10,000 —         10,000 × 40% conversion materials — 4,000 Eqivalent units of output 56,000 50,000 Costs:         Work in process, December 1:           Direct materials...

  • Cost Information and the Weighted Average Method Morrison Company had the equivalent units schedule and cost...

    Cost Information and the Weighted Average Method Morrison Company had the equivalent units schedule and cost information for its Sewing Department for the month of December, as shown below. Direct Materials Conversion Costs Units completed 45,000 45,000 Add: Units in ending work in process x Percentage complete: 10,000 ~ 100% direct materials 10,000 10,000 x 45% conversion materials 4,500 Eqivalent units of output 55,000 49,500 Costs: Work in process, December 1: Direct materials $66,000 Conversion costs 14,000 Total work in...

  • Cost Information and the Weighted Average Method Morrison Company had the equivalent units schedule and cost...

    Cost Information and the Weighted Average Method Morrison Company had the equivalent units schedule and cost information for its Sewing Department for the month of December, as shown below. Direct Materials Conversion Costs Units completed 46,000 46,000 Add: Units in ending work in process ×      Percentage complete:         10,000 × 100% direct materials 10,000 —         10,000 × 40% conversion materials — 4,000 Eqivalent units of output 56,000 50,000 Costs:         Work in process, December 1:           Direct materials...

  • FIFO Method, Equivalent Units, Unit Cost, Multiple Departments Fordman Company has a product that passes through...

    FIFO Method, Equivalent Units, Unit Cost, Multiple Departments Fordman Company has a product that passes through two processes: Grinding and Polishing. During December, the Grinding Department transferred 20,000 units to the Polishing Department. The cost of the units transferred into the second department was $40,000. Direct materials are added uniformly in the second process. Units are measured the same way in both departments. The second department (Polishing) had the following physical flow schedule for December: Units to account for:   Units,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT