Liters completed and transferred | 74000 |
Less: Liters in beginning Work in process | 3000 |
Liters started and completed | 71000 |
Option D 71,000 is correct |
QUESTION 19 The Blue Lake Water Company has two departments, Purifying and Bottling. The Bottling Department...
The Mountain Springs Water Company has two departments, Purifying and Bottling. The Bottling Department had 8,000 liters in beginning work in process inventory (60% complete). During the period 70,000 liters were completed. The ending work in process was 3,000 liters (60% completed). What are the total equivalent units for direct materials under the FIFO method if materials were added throughout the process? Whole Units Equivalent Units Inventory in process, beginning of period Started and completed during the period Transferred out...
The Mountain Springs Water Company has two departments, Purifying and Bottling. The Bottling Department had 2,610 liters in beginning work in process inventory (30% complete). During the period 57,020 liters were completed. The ending work in process was 5,410 liters (70% completed). All inventories are costed by the first-in, first-out method. What is the total equivalent units for direct materials (using the FIFO method) if materials were added at the beginning of the process? equivalent units
The Mountain Springs Water Company has two departments, Purifying and Bottling. The Bottling Department had 2,680 liters in beginning work in process inventory (30% complete). During the period 58,970 liters were completed. The ending work in process was 6,610 liters (70% completed). All inventories are costed by the first-in, first-out method. What is the total equivalent units for direct materials (using the FIFO method) if materials were added at the beginning of the process? Please Help Me!! I do not...
The Bottling Department of Mountain Springs Water Company had 5,400 liters in beginning work in process inventory (30% complete). During the period, 55,200 liters were completed. The ending work in process inventory was 3,000 liters (65% complete). All inventories are costed by the first in, first-out method. What are the equivalent units for conversion costs under the FIFO method? equivalent units
The Bottling Department of Mountain Springs Water Company had 4,500 liters in beginning work in process inventory (25% complete). During the period, 56,300 liters were completed. The ending work in process inventory was 2,800 liters (55% complete). All inventories are costed by the first-in, first-out method. What are the equivalent units for conversion costs under the FIFO method? _equivalent units
Kraus Steel Company has two departments, Casting and Rolling. In the Rolling Department, ingots from the Casting Department are rolled into steel sheet. The Rolling Department received 60,800 tons from the Casting Department in October. During October, the Rolling Department completed 73,900 tons, including 16,700 tons of work in process on October 1. The ending work in process inventory on October 31 was 3,600 tons. How many tons were started and completed during October? tons
Units to be Assigned Costs Kraus Steel Company has two departments, Casting and Rolling. In the Rolling Department, ingots from the Casting Department are rolled into steel sheet. The Rolling Department received 65,800 tons from the Casting Department in October. During October, the Rolling Department completed 74,100 tons, including 14,200 tons of work in process on October 1. The ending work in process inventory on October 31 was 5,900 tons. How many tons were started and completed during October? tons
Units to be Assigned Costs Kraus Steel Company has two departments, Casting and Rolling. In the Rolling Department, ingots from the Casting Department are rolled into steel sheet. The Rolling Department received 46,000 tons from the Casting Department in October. During October, the Rolling Department completed 59,700 tons, including 17,400 tons of work in process on October 1. The ending work in process inventory on October 31 was 3,700 tons. How many tons were started and completed during October? tons
Units to be Assigned Costs Kraus Steel Company has two departments, Casting and Rolling. In the Rolling Department, ingots from the Casting Department are rolled into steel sheet. The Rolling Department received 55,200 tons from the Casting Department in October. During October, the Rolling Department completed 70,000 tons, including 18,700 tons of work in process on October 1. The ending work in process inventory on October 31 was 3,900 tons. How many tons were started and completed during October? tons
Units to be Assigned Costs Oak Ridge Steel Company has two departments, Casting and Rolling. In the Rolling Department, ingots from the Casting Department are rolled into steel sheet. The Rolling Department received 38,100 tons from the Casting Department. During July, the Rolling Department completed 48,000 tons, including 11,400 tons of work in process on July 1. The ending work in process inventory on July 31 was 1,500 tons. How many tons were started and completed during July? tons