Alrodyne Wind, Inc., has wind tunnels that can operate vertically or horizontally for evaluating the effects...
Alrodyne Wind, Inc., has wind tunnels that can operate vertically or horizontally for evaluating the effects of air flow on a component's PCB response and reliability. The company expects to build a new tunnel that will be outfitted with multiple sensor ports. For the estimates below. calculate the equivalent annual cost of the project. First Cost Replacement Cost Year 2 AOC per Year Salvage Value $360000 $-340.000 $920000 $265.000 Life, Years Interest Rate 1296 The equivalent annual cost of the project is $0