P3-49A Determine and record job costs (PP.166) Veon Homes manufactures prefabricated chalets in Colorado. The company uses a
c. Requisitioned direct materials in manufacturing as follows: Direct Materials Chalet 13 $41,400 Chalet 14 $56,700 Chalet 15
Equipment rentals paid in cash $10,600 Prepaid plant insurance expired $ 8,000 f. Allocated overhead to jobs at the predeterm
0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

CR DR $4,90,000.00 1 Particulars Raw material inventory Accounts payable To record purchase of material on account $4,90,000.

Add a comment
Know the answer?
Add Answer to:
P3-49A Determine and record job costs (PP.166) Veon Homes manufactures prefabricated chalets in Colorado. The company...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • P3-49A Determine and record job costs (Learning Objectives 2, 3, 4, & 6) Veon Homes manufactures...

    P3-49A Determine and record job costs (Learning Objectives 2, 3, 4, & 6) Veon Homes manufactures prefabricated chalets in Colorado. The company uses a perpetual inventory system and a job cost system in which each chalet is a job. The following events occurred during May: a. Purchased materials on account, $490,000. b. Incurred total manufacturing wages of $115,000, which included both direct labor and indirect labor. Used direct labor in manufacturing as follows: Direct Labor Chalet 13 $14,200 Chalet 14...

  • Divine Homes manufactures prefabricated chalets in Colorado. The company uses a perpetual inventory system and a...

    Divine Homes manufactures prefabricated chalets in Colorado. The company uses a perpetual inventory system and a job cost system in which each chalet is a job. The following events occurred during May: (Click the icon to view the events.) Read the requirements Requirement 1. Record the events in the general journal. (Record debits first, then credits. Exclude explanations from any journal entries.) Start with the entry from event (a). Purchased materials on account, $420,000. x - Journal Entry Requirements Date...

  • * More Info a. Purchased materials on account, $460,000 Incurred total manufacturing wages of $112.000, which...

    * More Info a. Purchased materials on account, $460,000 Incurred total manufacturing wages of $112.000, which included both direct labor and indirect labor. Used direct labor in manufacturing as follows: Direct Labor Requirements Chalet 13 .........$ 14,100 Chalet 14...........$ 28,100 Chalet 15........... $ 19,300 1. Record the preceding events in the general journal. Chalet 16. 2. Post the appropriate entries to the T-accounts, identifying each entry by letter. Determine the ending ..........$ 21,500 account balances, assuming that the beginning balances...

  • Date Materials Requisition Description Amount No. 11/30 437 60 pounds rubber at $14 $ 840 12/2...

    Date Materials Requisition Description Amount No. 11/30 437 60 pounds rubber at $14 $ 840 12/2 439 $ 480 40 meters polyester fabric at $12 12/3 501 100 meters steel cord at $8 S 800 Durable Tire allocates manufacturing overhead to jobs on the basis of the relationship between expected overhead costs ($529,000) and expected direct labor hours (23,000). Job 298 was completed on December 3 and shipped to ATV on December 5. Requirements 1. Prepare a job cost record...

  • Please answer the following question. JOB ORDER COSTING The company "Homes for Us" manufactures houses. The...

    Please answer the following question. JOB ORDER COSTING The company "Homes for Us" manufactures houses. The company is labor intensive and allocates overhead based on labor hours. "Homes for Us" expects to incur S400,000 of manufacturing overhead costs and to use 8.000 labor hours during 2018. "Homes for Us" had no beginning inventory. It recorded the following transactions during January Purchased direct materials (on account) for $85,000 Purchased indirect materials (on account) for $12,000 Incurred other manufacturing overhead cost on...

  • Problem 02-3A Source documents, journal entries, and accounts in job order costing LO P1, P2, P3...

    Problem 02-3A Source documents, journal entries, and accounts in job order costing LO P1, P2, P3 [The following information applies to the questions displayed below.] Widmer Watercraft’s predetermined overhead rate is 200% of direct labor. Information on the company’s production activities during May follows. Purchased raw materials on credit, $220,000. Materials requisitions record use of the following materials for the month. Job 136 $ 49,000 Job 137 32,000 Job 138 19,800 Job 139 22,600 Job 140 6,600 Total direct materials...

  • Please answer the following question. JOB ORDER COSTING The company "Homes for Us" manufactures houses. The...

    Please answer the following question. JOB ORDER COSTING The company "Homes for Us" manufactures houses. The company is labor intensive and allocates overhead based on labor hours. “Homes for Us" expects to incur $400,000 of manufacturing overhead costs and to use 8,000 labor hours during 2018. "Homes for Us" had no beginning inventory. It recorded the following transactions during January, 1. Purchased direct materials (on account) for $85,000 2. Purchased indirect materials (on account) for $12,000 3. Incurred other manufacturing...

  • Bonita Company uses a job order cost system and applies overhead to production on the basis...

    Bonita Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $ 21,200 direct labor $ 12,720, and manufacturing overhead $ 16,960. As of January 1, Job 49 had been completed at a cost of $ 95,400 and was part of finished goods inventory....

  • Problem for Job Order Costing Tiny Homes uses a job costing system to account for the...

    Problem for Job Order Costing Tiny Homes uses a job costing system to account for the individual prefabricated homes of January 1, its accounting records showed inventories as follows the individual prefabricated homes it builds. As Materials and supplies Work in process (Jobs 422 and 423) Finished goods (Job 421) $120,000 180,000 175,000 The work in process in ventory consisted of two jobs: Job# 422 423 Direct Materials $36,000 Direct Labor Manufacturing Overh $40,000 $20,000 $96,000 $36,000 $180,000 $76,000 $68,000...

  • P19-30A ​Construction, Inc. is a home builder in Arizona. MemoryMemory uses a job order costing system in which each hou...

    P19-30A ​Construction, Inc. is a home builder in Arizona. MemoryMemory uses a job order costing system in which each house is a job. Because it constructs​ houses, the company uses an account titled Construction Overhead. The company applies overhead based on estimated direct labor costs. For the​ year, it estimated construction overhead of $1,050,000 and total direct labor cost of $2,100,000.The following events occurred during August​: a. Purchased materials on​ account, $ 420 comma 000$420,000 b. Requisitioned direct materials and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT