Question
1)
A favorable cost variance occurs when Oa. actual costs are the same as standard costs Ob. actual costs are more than standard costs Oc. standard costs are more than actual costs Od. standard costs are less than actual costs
2)
The Flapjack Corporation had 8,042 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but only 999 units were actually produced. Labor standards were 7.9 hours per completed unit at a standard rate of $13.14 per hour. The labor rate variance is O$9,167.88 unfavorable O$9,167.88 favorable $2,153.46 unfavorable O$2,153.46 favorable
3)
If the actual direct labor hours spent producing a commodity differs from the standard hours, the variance is a Oa. time variance Ob. quantity variance Oc. rate variance Od. price varianc
4)
The following data relate to direct labor costs for the current period: Standard costs 36,000 hours at $22.00 35,000 hours at $23.00 Actual costs What is the direct labor time variance? Oa. $23,000 favorable Ob. $35,000 unfavorable c.$36,000 unfavorable Od. $22,000 favorable
5)
The following data is given for the Stringer Company: Budgeted production Actual production Materials: Standard price per ounce Standard ounces per completed unit Actual ounces purchased and used in production Actual price paid for materials Labor: Standard hourly labor rate Standard hours allowed per completed unit Actual labor hours worked Actual total labor costs Overhead Actual and budgeted fixed overhead Standard variable overhead rate Actual variable overhead costs 26,000 units 27,500 units $6.50 8 228,000 $1,504,800 $22 per hour 6.6 183,000 $4,020,000 $1,029,600 $24.50 per standard labor hour $4,520,000 Overhead is applied on standard labor hours The direct materials price variance is Oa. $22,800 unfavorable Ob. Oc. $52,000 favorable $52,000 unfavorable d. $22,800 favorable
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1)Answer :C

Explanation : When standard cost is more than actual cost then the variance is said to be favorable.

2)Labor rate variance =( Standard rate- Actual rate ) x Actual hours worked

=(13.14-12)*8042

=9,167.88 favorable

3)Answer :A

Explanation :The direct labor time variance is the difference between the actual direct labor hours and the standard direct labor hours

4)Labor time variance = (Standard hours-Actual hours )* Standard rate

= (36000-35000)*22 per hour = -$22000 favorable

5)Material price variance =( Standard price-Actual price ) x Actual quantity used

=(6. 5-(1504800/228000)) *228000

=22,800 Unfavorable

IN CASE OF ANY DOUBTS OR CORRECTIONS FEEL FREE TO COMMENT BELOW

PLEASE RATE MY ANSWER BY HITTING ??

THANK YOU

Add a comment
Know the answer?
Add Answer to:
1) 2) 3) 4) 5) A favorable cost variance occurs when Oa. actual costs are the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following information is for the standard and actual costs for the Happy Corporation: Enter favorable...

    The following information is for the standard and actual costs for the Happy Corporation: Enter favorable variances as negative numbers. Standard Costs: Budgeted units of production - 16,000 [80% (or normal) capacity] Standard labor hours per unit - 4 Standard labor rate - $26 per hour Standard material per unit - 8 lbs. Standard material cost - $12 per pound Standard variable overhead rate - $15 per labor hour Budgeted fixed overhead - $640,000 Fixed overhead rate is based on...

  • Use this information for Stringer Company to answer the question that follow. The following data are...

    Use this information for Stringer Company to answer the question that follow. The following data are given for Stringer Company: 941 units Budgeted production 1,061 units Actual production Materials: $1.77 Standard price per ounce 10 Standard ounces per completed unit 10,928 Actual ounces purchased and used in production $22,402 Actual price paid for materials Labor: $14.86 per hour Standard hourly labor rate Standard hours allowed per completed unit 4.1 Actual labor hours worked 5,464.15 Actual total labor costs $83,328 Overhead:...

  • A. The standard costs and actual costs for direct materials for the manufacture of 2,240 actual...

    A. The standard costs and actual costs for direct materials for the manufacture of 2,240 actual units of product are as follows: Standard Costs Direct materials 2,240 kilograms @$8.60 Actual Costs Direct materials 2,300 kilograms The direct materials quantity variance is? Choose the correct answer below $413 favorable $516 unfavorable $516 favorable $413 unfavorable B. The following data relate to direct labor costs for the current period: Standard costs 7,200 hours at $11.30 Actual costs 6,400 hours at $10.80 What...

  • The following data are given for Harry Company: Budgeted production 1,054 units Actual production   937 units...

    The following data are given for Harry Company: Budgeted production 1,054 units Actual production   937 units Materials:     Standard price per ounce $1.919     Standard ounces per completed unit 11     Actual ounces purchased and used in production 10,616     Actual price paid for materials $21,763 Labor:     Standard hourly labor rate $14.76 per hour     Standard hours allowed per completed unit 4.3     Actual labor hours worked 4,826     Actual total labor costs $78,423 Overhead:     Actual and budgeted fixed overhead $1,025,000     Standard variable overhead rate $24.00 per...

  • The following data are given for Stringer Company: Budgeted production 909 units Actual production   1,036 units...

    The following data are given for Stringer Company: Budgeted production 909 units Actual production   1,036 units Materials:     Standard price per ounce $1.82     Standard ounces per completed unit 12     Actual ounces purchased and used in production 12,805     Actual price paid for materials $26,250 Labor:     Standard hourly labor rate $14.95 per hour     Standard hours allowed per completed unit 4.4     Actual labor hours worked 5,335.4     Actual total labor costs $81,365 Overhead:     Actual and budgeted fixed overhead $1,110,000     Standard variable overhead rate $28.00 per...

  • The following data relate to direct labor costs for August: Actual costs: 5,500 hours at $24.00...

    The following data relate to direct labor costs for August: Actual costs: 5,500 hours at $24.00 per hour. Standard costs: 5,000 hours at $23.70 per hour. What is the direct labor rate variance? Oa. $1,500 favorable ob. $1,650 favorable OC. $1,500 unfavorable od. $1,650 unfavorable

  • Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come...

    Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come from material costs that are higher or lower than expected, material usage that is not what was expected, higher or lower labor costs than expected, or more or less time spent to produce an item than expected. Overhead cost and volume variances are another cause for costs to be higher or lower than what was expected. The total manufacturing variance can be broken down...

  • Use this information to answer the question that follow. The standard costs and actual costs for...

    Use this information to answer the question that follow. The standard costs and actual costs for factory overhead for the manufacture of 2,600 units of actual production are as follows Fixed overhead (based on 10,000 hours) Variable overhead 3 hours per unit$0.75 per hour 3 hours per unit $1.95 per hour Total variable cost, $18,200 Total fixed cost, $8,200 The fixed factory overhead volume variance is Oa. $1,320 unfavorable Ob. $0 Oc.$1,650 unfavorable Od. $1,320 favorable

  • The standard costs and actual costs for direct materials for the manufacture of 2,900 actual units...

    The standard costs and actual costs for direct materials for the manufacture of 2,900 actual units of product are Standard Costs Direct materials (per completed unit) 1,040 kilograms @$8.82 Actual Costs Direct materials Round your final answer to the nearest dollar. 2,900 kilograms @ $8.00 The amount of direct materials price variance is oa. $853 favorable ob. $2,378 favorable OC. $853 unfavorable od. $2,378 unfavorable

  • What is the direct labor rate variance? 50 unfavorable 125 unfavorable 125 favorable The following information...

    What is the direct labor rate variance? 50 unfavorable 125 unfavorable 125 favorable The following information for Q 7-8 The St. Augustine Corporation originally budgeted for $360,000 of fixed overhead at 100% normal production capacity. Production was budgeted to be 12,000 units. The standard hours for production were 5 hours per unit. The variable overhead rate was S3 per hour. Actual fixed overhead was $360,000 and actual variable overhead was $170,000. Actual production was 11,800 units. 7. The variable factory...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT