Activity Rate = Total Activity Cost/Total Activity
= 600,000/(400+600) = $600 per setup
Cost assigned under activity based costing = Activity rate*Activity level
Hence, cost assigned to sparklers = 600*400 = $240,000
Hence, the answer is $240000
Multiple Choice Question 80 One of Stine Company's activity cost pools is machine setups, with estimated...
28. One of Stine Company's activity cost pools is machine setups, with estimated overhead of $360,000. Stine produces sparklers (400 setups) and lighters (600 setups). How much of the machine setup cost pool should be assigned to sparklers? A) $360,000 B) $144,000 C) $180,000 D) $216,000
Machine Setups Machining hours Do It Review 4-2 0-0 Plynn Industries has three activity cost pools and two products. It estimated production 2,000 units of Product BC113 and 1,000 of Product ADS08. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers Estimated Use of Annual Overhead Data Cost Drivers per Product Estimated Estimated COM Product Product Activity Overhead Drivers 8C113 ADSOB Cost...
Question 2 Randel Manufacturing has five activity cost pools and two products (a budget tape vacuum and a deluxe tape vacuum). Information is presented below: Activity Cost Pool Ordering and Receiving Machine Setup Cost Driver Orders Setups Machine hours Parts Inspections Estimated Overhead $130,000 297,000 1,000,000 1,600,000 300,000 Cost Drivers by Product Budget Deluxe 600 400 500 400 150,000 100,000 1,200,000 800,000 550 450 Machining Assembly Inspection Compute the overhead cost per unit for each product. Production is 700,000 units...
Do It! Review 4-2 a-c Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Estimated Use of Cost Drivers per Product Annual Overhead Data Estimated Overhead $15,600 86,190 30,250 Estimated Use of Cost Drivers per Activity Activity Cost Pools...
Flynn Industries has three activity cost pools and two
products. It estimates production 2,000 units of Product BC113 and
1,000 of Product AD908. Having identified its activity cost pools
and the cost drivers for each pool, Flynn accumulated the following
data relative to those activity cost pools and cost drivers.
Annual Overhead Data
Estimated Use of
Cost Drivers per Product
Activity Cost Pools
Cost Drivers
Estimated
Overhead
Estimated Use of Cost
Drivers per Activity
Product
BC113
Product
AD908
Machine setup...
Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Use of Cost Drivers per Product Product AD908 Activity Cost Pools Machine setup Machining Packing Estimated Overhead $18,500 106,920 35,640 Cost Drivers Setups Machine hours...
Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Use of Cost Drivers per Product Estimated Use of Cost Product Product Drivers BC113 AD908 per Activity Estimated Overhead Activity Cost Pools Cost Drivers Machine setup...
Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each . pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Product AD908 Annual Overhead Data Estimated Activity Cost Pools Cost Drivers Overhead Machine setup Setups $22,000 Machining Machine hours 97,200 Packing Orders 30,080 Estimated Use of Cost Drivers per...
Do It! Review 4-2 a-c Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Estimated Use of Cost Drivers per Product Annual Overhead Data Estimated t Estimated Use of Cost Product Product Activity BC113 AD908 12 4,840 1,050 3,790...
Do It! Review 17-02 ac Flynn Industries has three activity cost pools and two products. It estimates production 2.000 units of Product BC113 and 1,000 of Product ADSOB. Having identified its activity cost pools and the cost drivers for each pool Flynn accumulated the following data relative to those activity cost pools and cost drivers Annual Overhead Data Activity Cost Pools Machine setup Machining Packing Cost Drivers Setups Machine hours Orders Estimated Overhead $15,600 86,190 30,250 Estimated Use of Cost...