Alternative A M P, $ 23,000 8,000 S, $ 4,000 0 Life, years 10 5 M&O, $/year 3,500 1,500 Labor rate $/hr 24 12 People 1 3 Output, tons/hr 8 6
Select the best alternative if the expected production tonnage is 2500 tons
S = Salvage value
M&O = money spent per year
From the given alternatives, it can be understood that one of the alternative products is a high-end product with quality and the other product is an average product. The choice therefore would be been a very good product and a good product. Here, we need to understand our requirement from the product.
Given is that, we need to produce 2500 tons of output every year, therefore, it can be seen that Product B (Alterative B is more suitable for us ) as it can produce 6 tons of the product per hour and our demand would be met in a total of about 615 hours. Alternative A would have been more suitable if our need for production would have been much higher. But since our production requirement is only 2500 tons, Alternative B should be more preferable choice.
Alternative A M P, $ 23,000 8,000 S, $ 4,000 0 Life, years 10 5 M&O,...
Alternative P, $ S, $ Life, years M&O, S/year 3,500 1,500 Labor rate $/hr 24 People Output, tons/hr 8 4,000 0 10 5 12 Select the best alternative if the expected production tonnage is 2500 ton
d. What quantity would be required for a profit of $2,000? 20 Alternative P, $ S, $ Life, years M&O, $/year Labor rate $/hr People Output, tons/hr 23,000 8,000 4,000 0 10 3,500 1,500 24 12 Select the best alternative if the expected production tonnage is 2500 ton
For the following table, assume a MARR of 9% per year and a useful life for each alternative of six years that equals the study period. The rank-order of alternatives from least capital investment to greatest capital investment is Do Nothing A CB. Complete the IRR analysis by selecting the preferred alternative. Do Nothing A A C CB - $15,000 A Capital investment A Annual revenues A Annual costs - $3,250 - $2,000 4,000 900 460 -1,000 6,000 - 150...
A five-year-old defender has a current market value of $4,000 and expected O&M costs of $3,400 this year, increasing by $1,200 per year. Future market values are expected to decline by $1,100 per year. The machine can be used for another three years. The challenger costs $6,500 and has O&M costs of $2,200 per year, increasing by $600 per year. The machine will be needed for only three years, and the salvage value at the end of that time is...
Normal No Spacing Heading 1 Heading Problem 3.) P&S Enterprises, Operating Budgets Bilal Mehran P&S Enterprises (PSE) Manufacture and sell two products, G29 and H02. Each product requires Labor hours, Machine hours and (raw) Material Y. Price Std cost Labor hrs. Mach burs M atlY Per unit G29 $ 40/unit $21.50 4 tbs HO2 $ 60/unit $29.50 6 lbs The standard cost/unit of Matly is $3/lb. The Standard Labor rate is $15/ab hour. Overhead is applied using Machine hours as...
Homework 5 wing is Information On Two Alternative invest Chape.com *5 i Help S a. A new operating system for an existing machine is expected to cost $770,000 and have a useful life of six years. The system yields an incremental after-tax income of $220,000 each year after deducting its straight-line depreciation. The predicted salvage value of the system is $23,200. b. A machine costs $430,000, has a $31,700 salvage value, is expected to last eight years, and will generate...
1.) Projects A and B both have 5 years of life. The initial investments and cash flows from these two projects are shown below. Year 0 1 2 3 4 5 Project A -12,300 4,500 4,000 3,500 3,000 2,500 Project B -15,000 6,000 5,000 4,000 3,200 2,400 A.) Use Data Table tool to find the NPVs of both projects when the discount rate is 10%. B.) Use Data Table tool to find the IRRs of both projects C.) Plot the...
1.) Projects A and B both have 5 years of life. The initial investments and cash flows from these two projects are shown below. Year 0 1 2 3 4 5 Project A -12,300 4,500 4,000 3,500 3,000 2,500 Project B -15,000 6,000 5,000 4,000 3,200 2,400 A.) Use Data Table tool to find the NPVs of both projects when the discount rate is 10%. B.) Use Data Table tool to find the IRRs of both projects C.) Plot the...
Apologies for the long question! L M N O P Q R S at 10 at A1 ✓ fx Part 2 C D E F G H I J K 7 The budget director for Bird House Unlimited, Inc., has gathered the following data for use in developing the budgeted income statement for January 2020. Estimated sales for January Bird House 34,000 units $42 per unit Bird Feeder 25,000 units $70 per unit Direct materials Estimated inventories at January 1(beginning)...
10:15 GX 1.51%. e s o s IL Multiple choice (60 p cholesben 1. The shape of the Men deviation 2. The standard Standard deviat i le devii d curve la tribal the value i n 15 3. Ir the were mad e is 2.5 or distribution is 45 and standard deviation of normal distributors is that the value of x for a distribution is 97.5 47.5 e 373 4 675 See other value. 4. Considering the normal distribution, pal...