Solution:
Department G | |||
Computation of Equivalent unit (FIFO) | |||
Particulars | Physical units | Material | Conversion |
Units to be accounted for: | |||
Beginning WIP Inventory | 2040 | ||
Units started this period | 11960 | ||
Total unit to be accounted for | 14000 | ||
Units Accounted for: | |||
Units completed and transferred out | |||
From
beginning inventory Material - 0% Conversion - 75% |
2040 | 0 | 1530 |
Started and completed currently | 10260 | 10260 | 10260 |
Transferred to finished goods | 12300 | 10260 | 11790 |
Units in
ending WIP Material - 100% Conversion - 20% |
1700 | 1700 | 340 |
Total units accounted for | 14000 | 11960 | 12130 |
Department G | |||
Computation of Cost per Equivalent unit | |||
Particulars | Total cost | Material | Conversion |
Current period cost | $208,480.00 | $95,680.00 | $112,800.00 |
Equivalent units | 11960 | 12130 | |
Cost per equivalent unit | $8.0000 | $9.2993 |
Total cost of beginning WIP completed this period = $30,300 + (1530*$9.2993) = $44,528
Hence option b is correct.
Department G had 2,040 units 25% completed at the beginning of the period, 12,300 units were...
Department G had 2,040 units 25% completed at the beginning of the period, 12,300 units were completed during the period, 1,700 units were 20% completed at the end of the period, and the following manufacturing costs debited to the departmental work in process account during the period: Work in process, beginning of period $30,700 Costs added during period: Direct materials (11,960 units at $8) 95,680 Direct labor 78,000 Factory overhead 26,000 All direct materials are placed in process at the...
Department G had 2,040 units 25% completed at the beginning of the period, 13,900 units were completed during the period, 1,700 units were 20% completed at the end of the period, and the following manufacturing costs debited to the departmental work in process account during the period: Work in process, beginning of period $25,700 Costs added during period: Direct materials (13,560 units at $8) 108,480 Direct labor 79,200 Factory overhead 26,400 All direct materials are placed in process at the...
1. Department G had 2,040 units 25% completed at the beginning of the period, 13,200 units were completed during the period, 1,700 units were 20% completed at the end of the period, and the following manufacturing costs debited to the departmental work in process account during the period: Work in process, beginning of period $28,300 Costs added during period: Direct materials (12,860 units at $8) 102,880 Direct labor 88,200 Factory overhead 29,400 All direct materials are placed in process at...
Department G had 3,600 units, 25% completed at the beginning of the period, 11,000 units were completed during the period, 3,000 units were one-fifth completed at the end of the period, and the following manufacturing costs were debited to the departmental work in process account during the period: Work in process, beginning of period $40,000 Costs added during period: Direct materials (10,400 at $8) 83,200 Direct labor 63,000 Factory overhead 25,000 Assuming that all direct materials are placed in process...
Department G had 2,280 units 25% completed at the beginning of the period, 14,000 units were completed during the period, 1,900 units were 20% completed at the end of the period, and the following manufacturing costs were debited to the departmental work in process account during the period: Work in process, beginning of period $33,500 Costs added during period: Direct materials (13,620 units at $9) 122,580 Direct labor 165,720 Factory overhead 55,240 All direct materials are placed in process at...
Department G had 2,160 units 25% completed at the beginning of the period, 13,100 units were completed during the period, 1,800 units were 20% completed at the end of the period, and the following manufacturing costs debited to the departmental work in process account during the period: Work in process, beginning of period $25,400 Costs added during period: Direct materials (12,740 units at $9) 114,660 Direct labor 73,800 Factory overhead 24,600 All direct materials are placed in process at the...
Department G had 1,920 units 25% completed at the beginning of the period, 13,900 units were completed during the period, 1,600 units were 20% completed at the end of the period, and the following manufacturing costs debited to the departmental work in process account during the period: Work in process, beginning of period $25,300 Costs added during period: Direct materials (13,580 units at $9) 122,220 Direct labor 75,000 Factory overhead 25,000 All direct materials are placed in process at the...
Department G had 3,600 units 25% completed at the beginning of the period, 11,000 units were completed during the period; 3,000 units were 20% completed at the end of the period, and the following manufacturing costs debited to the departmental work in process account during the period: Work in process, beginning of period $40,000 Costs added during period: Direct materials (10,400 units at $8) 83,200 Direct labor 63,000 Factory overhead 25,000 All direct materials are placed in process at the...
Department G had 1,800 units 25% completed at the beginning of the period, 13,900 units were completed during the period; 1,500 units were 20% completed at the end of the period, and the following manufacturing costs debited to the departmental work in process account during the period: Work in process, beginning of period $33,400 Costs added during period: Direct materials (13,600 units at $8) 108,800 Direct labor 88,200 Factory overhead 29,400 All direct materials are placed in process at the...
Department G had 2,280 units 25% completed at the beginning of the period, 12,200 units were completed during the period, 1,900 units were 20% completed at the end of the period, and the following manufacturing costs debited to the departmental work in process account during the period: Work in process, beginning of period $25,800 Costs added during period: Direct materials (11,820 units at $9) 106,380 Direct labor 88,800 Factory overhead 29,600 All direct materials are placed in process at the...