1. Computation of product margins for Xactive and Pathbreaker products using company's traditional costing system:- | |||||||
a. Computation of Predetemined Manufacturing overhead rate :- | |||||||
Estimated Total manufacturing Overheads | $1,634,000 | ||||||
Estimated total Direct labor hours | 86,000 | DLHs | |||||
Predetemined Manufacturing overhead rate | = | Estimated Total manufacturing Overheads | |||||
Estimated total Direct labor hours | |||||||
= | $1,634,000 | ||||||
86000 | |||||||
= | $19.00 | per DLH | |||||
B. Computation of Overhead Cost Per unit:- | |||||||
Product | Activity Driver | Plantwide OH Rate | Overhead Cost per Unit | ||||
a | b | c | d = b×c | ||||
Xactive | 1.4 | DLHs | $19.00 | per DLH | $26.60 | ||
Pathbreaker | 1.0 | DLHs | $19.00 | per DLH | $19.00 | ||
b. Computation of Unit Product Cost :- | |||||||
Product | |||||||
Xactive | Pathbreaker | ||||||
No. of units produced | 15000 | 65000 | |||||
Per Unit | Total | Per Unit | Total | ||||
Direct Material Cost | $ 63.80 | $ 957,000 | $ 50.00 | $ 3,250,000 | |||
Direct labor Cost | $ 17.20 | $ 258,000 | $ 12.00 | $ 780,000 | |||
Overhead Cost | $ 26.60 | $ 399,000 | $19.00 | $ 1,235,000 | |||
Product Cost | $ 107.60 | $ 1,614,000 | $ 81.00 | $ 5,265,000 | |||
2. Computation of Activity rates:- | |||||||
Activity Cost Pools | Activity measures (Cost Drivers) | Estimated Overhead Cost | Expected Activity | Activity Rate | |||
Xactive | Pathbreaker | Total | |||||
a | b | c | d | e | f | g = c/f | |
Supporting Direct labor | Direct labor hours (DLHs) | $ 580,500 | 21,000 | 65,000 | 86,000 | $ 6.75 | per DLH |
Batch setups | Setups | $ 360,000 | 200 | 100 | 300 | $ 1,200 | per setup |
Product sustaining | No. of products | $ 639,500 | 1 | 1 | 2 | $ 319,750 | per product |
General Factory | Machine hours | $ 54,000 | 1,500 | 6,500 | 8,000 | $ 6.75 | per MHR |
Total Manufacturing Overhead Cost | $ 1,634,000 | ||||||
Computation of Overhead Cost Per unit:- | |||||||
Overhead Assigned | Activity Driver | Activity Rate | Total Overhead Cost | ||||
a | b | c | d = b×c | ||||
Xactive | |||||||
Supporting Direct labor | 21,000 | Direct labor hours (DLHs) | $ 6.75 | $ 141,750 | |||
Batch setups | 200 | Setups | $ 1,200.00 | $ 240,000 | |||
Product sustaining | 1 | No. of products | $ 319,750.00 | $ 319,750 | |||
General Factory | 1,500 | Machine hours | $ 6.75 | $ 10,125 | |||
Total | $ 711,625 | ||||||
Units Produced | 15,000 | ||||||
Overhead Cost per Unit | $ 47.44 | ||||||
Pathbreaker | |||||||
Supporting Direct labor | 65,000 | Direct labor hours (DLHs) | $ 6.75 | $ 438,750 | |||
Batch setups | 100 | Setups | $ 1,200.00 | $ 120,000 | |||
Product sustaining | 1 | No. of products | $ 319,750.00 | $ 319,750 | |||
General Factory | 6,500 | Machine hours | $ 6.75 | $ 43,875 | |||
Total | $ 922,375 | ||||||
Units Produced | 65,000 | ||||||
Overhead Cost per Unit | $ 14.19 | ||||||
3. Computation of Unit Produt Cost :- | |||||||
Product | |||||||
Xactive | Pathbreaker | ||||||
No. of units produced | 15000 | 65000 | |||||
Per Unit | Total | Per Unit | Total | ||||
Direct Material Cost | $ 63.80 | $ 957,000 | $ 50.00 | $ 3,250,000 | |||
Direct labor Cost | $ 17.20 | $ 258,000 | $ 12.00 | $ 780,000 | |||
Overhead Cost | $ 47.44 | $ 711,625 | $ 14.19 | $ 922,375 | |||
Product Cost | $ 128.44 | $ 1,926,625 | $ 76.19 | $ 4,952,375 |
Feel free to ask any clarification, if required. Kindly
provide feedback by thumbs up, if satisfied. It will be highly
appreciated.
Thank you.
Rocky Mountain Corporation makes two types of hiking boots-Xactive and Pathbreaker. Data concerning these two product...
Rocky Mountain Corporation makes two types of hiking boots-Xactive and Pathbreaker. Data concerning these two product lines appear below: $ $ Direct materials per unit Direct labor cost per unit Direct labor-hours per unit Estimated annual production and sales Xactive 64.20 17.60 1.4 DLHS 19,000 units Pathbreaker 50.40 12.40 1 DLHS 69,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours. Data concerning manufacturing overhead and direct labor-hours for...
Rocky Mountain Corporation makes two types of hiking boots-Xactive and Pathbreaker. Data concerning these two product lines appear below: $ $ Xactive 65.10 18.50 1.4 DLHS 28,000 units Direct materials per unit Direct labor cost per unit Direct labor-hours per unit Estimated annual production and sales $ $ Pathbreaker 51.30 13.30 1 DLHS 78,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours. Data concerning manufacturing overhead and direct...
Rocky Mountain Corporation makes two types of hiking boots-Xactive and Pathbreaker. Data concerning these two product lines appear below: Direct materials per unit Direct labor cost per unit Direct labor-hours per unit Estimated annual production and sales Xactive $64.90 S 18.30 1.4 DLHS 26,000 units Pathbreaker $ 51.10 $ 13.10 1 DLHS 76,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours. Data concerning manufacturing overhead and direct labor-hours...
Rocky Mountain Corporation makes two types of hiking boots-Xactive and Pathbreaker. Data concerning these two product lines appear below: $ $ Xactive 65.80 19.20 1.4 DLHS 35,000 units Direct materials per unit Direct labor cost per unit Direct labor-hours per unit Estimated annual production and sales $ $ Pathbreaker 52.00 14.00 1 DLHS 85,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours. Data concerning manufacturing overhead and direct...
Check my work Rocky Mountain Corporation makes two types of hiking boots-Xactive and Pathbreaker. Data concerning these two product lines appear below: Direct materials per unit Direct labor cost per unit Direct labor-hours per unit Estimated annual production and sales Xactive $ 64.10 $17.50 1.4 DLHS 18,000 units Pathbreaker $ 50.30 $ 12.30 1 DLHS 68,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours. Data concerning manufacturing overhead...
Rocky Mountain Corporation makes two types of hiking boots—Xactive and Pathbreaker. Data concerning these two product lines appear below: Xactive Pathbreaker Direct materials per unit $ 64.90 $ 51.10 Direct labor cost per unit $ 18.30 $ 13.10 Direct labor-hours per unit 1.4 DLHS 1 DLHS Estimated annual production and sales 26,000 units 76,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours. Data concerning manufacturing overhead and direct...
Rocky Mountain Corporation makes two types of hiking boots-Xactive and Pathbreaker. Data concerning these two product lines appear below: Direct materials per unit Direct labor cost per unit Direct labor-hours per unit Estimated annual production and sales Xactive $ 64.80 $ 18.20 1.4 DLHS 25, eee units Pathbreaker $ 51.ee $ 13.00 1.2 DLHS 75, eee units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours. Data concerning manufacturing overhead...
ter 4 Rocky Mountain Corporation makes two types of hiking boots-Xactive and Pathbreaker. Data concerning these two product lines appear below: $ $ Xactive 63.80 17.20 1.4 DLHS 15,000 units Direct materials per unit Direct labor cost per unit Direct labor-hours per unit Estimated annual production and sales $ $ Pathbreaker 50.00 12.00 1 DLHS 65,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours. Data concerning manufacturing overhead...
Rocky Mountain corporation Rocky Mountain Corporation makes two types of hiking boots-Xactive and Pathbreaker. Data concerning these two product line appear below: Direct materials per unit Direct labor cost per unit Direct labor-hours per unit Estimated annual production and sales Xactive $65.20 $ 18.60 1.4 DLHS 29,000 units Pathbreaker $ 51.40 $ 13.40 1 DLHS 79,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours Data concerning manufacturing overhead...
Rocky Mountain Corporation makes two types of hiking boots-Xactive and Pathbreaker. Data concerning these two product lines appear below: $ $ Direct materials per unit Direct labor cost per unit Direct labor-hours per unit Estimated annual production and sales Xactive Pathbreaker 65.20 $ $1.40 18.60 $ 13.40 1.4 DLHS 1 DLA 29,000 units79,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor hours. Data concerning manufacturing overhead and direct...