Question
Please show work for this problem.

4. (7 points) During 2014, Barden Building Company constructed various assets at a total cost of $12,600,000. The weighted av
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer Page No ① Given that Tobal cost - $ 12600,000 Coreighted average acumulated expenditure on assets = 48400, pot from thPage No @ 420.000 + 370,000 6000,000 +3000,000 weighted average interest rate = X100 999000___ 9000000 :: Avoidable interest

Add a comment
Know the answer?
Add Answer to:
Please show work for this problem. 4. (7 points) During 2014, Barden Building Company constructed various...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • During 2017, Barden Building Company constructed various assets at a total cost of $12,600,000. The weighted...

    During 2017, Barden Building Company constructed various assets at a total cost of $12,600,000. The weighted average accumulated expenditures on assets qualifying for capitalization of interest during 2017 were $8,742,000. The company had the following debt outstanding at December 31, 2017: 1096, 5-year note to finance construction of various assets, dated January 1, 2017, with interest payable annually on January 1 1. $5,262,000 6,123,000 3,061,500 12%, ten-year bonds issued at par on December 31, 2011, with interest payable annually on...

  • During 2017, Barden Building Company constructed various assets at a total cost of $12,600,000. The weighted...

    During 2017, Barden Building Company constructed various assets at a total cost of $12,600,000. The weighted average accumulated expenditures on assets qualifying for capitalization of interest during 2017 were $8,742,000. The company had the following debt outstanding at December 31, 2017: 1096, 5-year note to finance construction of various assets, dated January 1, 2017, with interest $5,262,000 6,123,000 3,061,500 payable annually on January 1 12%, ten-year bonds issued at par on December 31, 2011, with interest payable annually on December...

  • Testbank Problem 139 During 2020, Debra Building Company constructed various assets at a total cost of...

    Testbank Problem 139 During 2020, Debra Building Company constructed various assets at a total cost of $12,600,000. The weighted average accumulated expenditures on assets qualifying for capitalization of interest during 2020 were $8,729,000. The company had the following debt outstanding at December 31, 2020: 1. 10%, 5-year note to finance construction of various assets, dated January 1, 2020, with interest payable annually on January 1 $5,313,000 2. 12%, ten-year bonds issued at par on December 31, 2014, with interest payable...

  • Teslüdrik Problemi 139 x Your answer is incorrect. Try again. During 2020, Maria Building Company constructed...

    Teslüdrik Problemi 139 x Your answer is incorrect. Try again. During 2020, Maria Building Company constructed various assets at a total cost of $12,600,000. The weighted average accumulated expenditures on assets qualifying for capitalization of interest during 2020 were $8,347,000. The company had the following debt outstanding at December 31, 2020: 1. 10%, 5-year note to finance construction of various assets, dated January 1, 2020, with interest payable annually on January 1 2. 12%, ten-year bonds issued at par on...

  • 4. total interest to be capitalize during 2010 Early in 2010, Dobbs Corporation engaged Kiner, Inc....

    4. total interest to be capitalize during 2010 Early in 2010, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2010 and was completed on December 31, 2010. Dobbs made the following payments to Kiner, Inc. during 2010: Date Payment June 1, 2010 $3,600,000 August 31, 2010 5,400,000 December 31, 2010 4,500,000 In order to help finance the construction, Dobbs issued the following during 2010: 1. $3,000,000...

  • Riverbed Company is constructing a building. Construction began on February 1 and was completed on December...

    Riverbed Company is constructing a building. Construction began on February 1 and was completed on December 31. Expenditures were $5,400,000 on March 1, $3,600,000 on June 1, and $9,000,000 on December 31. Riverbed Company borrowed $3,000,000 on March 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 5-year, $6,000,000 note payable and an 11%, 4-year, $10,500,000 note payable. Compute avoidable interest for Riverbed Company. Use the...

  • Early in 2015, Logan Corporation engaged Reese, Inc. to design and construct a complete modernization of...

    Early in 2015, Logan Corporation engaged Reese, Inc. to design and construct a complete modernization of Logan's manufacturing facility. Construction was begun on January 1, 2015 and was completed on December 31, 2015. Logan made the following payments to Reese, Inc. during 2015: Date Payment June 1, 2015 $2,400,000 August 31, 2015 3,600,000 December 31, 2015 3,000,000 In order to help finance the construction, Logan issued $2,000,000 of 10-year, 9% bonds payable, issued at par on January 2, 2015, with...

  • Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...

    Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2017 and was completed on December 31, 2017. Dobbs made the following payments to Kiner, Inc. during 2017: Date Payment June 1, 2017 $2,000,000 August 31, 2017 3,000,000 December 31,2017 2,500,000 In order to help finance the construction, Dobbs issued the following during 2017: 1. $1,700,000 of 10-year, 9% bonds payable, issued at par on...

  • Testbank Problem 140 Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a...

    Testbank Problem 140 Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2020 and was completed on December 31, 2020. Dobbs made the following payments to Kiner, Inc. during 2020: Date Payment June 1, 2020 $2,200,000 August 31, 2020 3,300,000 December 31, 2020 2,750,000 In order to help finance the construction, Dobbs issued the following during 2020: 1. $1,870,000 of 10-year, 9% bonds payable,...

  • Testbank Problem 140 Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a...

    Testbank Problem 140 Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2020 and was completed on December 31, 2020. Dobbs made the following payments to Kiner, Inc. during 2020: Payment Date $1,600,000 June 1, 2020 2,400,000 August 31, 2020 December 31, 2020 2,000,000 In order to help finance the construction, Dobbs issued the following during 2020 1. $1,360,000 of 10-year, 9% bonds payable,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT