Question

Early in 2010, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbss manufacturin

4. total interest to be capitalize during 2010
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Part 1

Date

Capitalization expenditures

period

Weighted-Average accumulated expenditures

June 1

3600000

7/12

2100000

August 31

5400000

4/12

1800000

December 31

4500000

0

0

3900000

Part 2

Weighted-Average accumulated expenditures

Appropriate interest rate

Avoidable interest

3000000

9%

270000

900000

12%

108000

$3900000

$378000

Part 3

Actual interest incurred during 2010:

9% bonds payable, $3,000,000 × .09 × 7/12

157500

12% note payable, $750,000 × .12

90000

Actual interest

$247500

The interest cost to be capitalized is $247500 (the lesser of the $378,000 avoidable interest and the $247500 actual interest cost)

Add a comment
Know the answer?
Add Answer to:
4. total interest to be capitalize during 2010 Early in 2010, Dobbs Corporation engaged Kiner, Inc....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...

    Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2020 and was completed on December 31, 2020. Dobbs made the following payments to Kiner, Inc. during 2020: Date Payment June 1, 2020 $1,680,000 August 31, 2020 2,520,000 December 31, 2020 2,100,000 In order to help finance the construction, Dobbs issued the following during 2020: 1. $1,428,000 of 10-year, 9% bonds payable, issued at par...

  • Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...

    Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2020 and was completed on December 31, 2020. Dobbs made the following payments to Kiner, Inc. during 2020: Date June 1, 2020 August 31, 2020 December 31, 2020 Payment $2,280,000 3,420,000 2,850,000 In order to help finance the construction, Dobbs issued the following during 2020: 1. $1,938,000 of 10-year, 9% bonds payable, issued at par...

  • Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...

    Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2017 and was completed on December 31, 2017. Dobbs made the following payments to Kiner, Inc. during 2017: Date Payment June 1, 2017 $2,000,000 August 31, 2017 3,000,000 December 31,2017 2,500,000 In order to help finance the construction, Dobbs issued the following during 2017: 1. $1,700,000 of 10-year, 9% bonds payable, issued at par on...

  • Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...

    Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2017 and was completed on December 31, 2017. Dobbs made the following payments to Kiner, Inc. during 2017: Date June 1, 2017 August 31, 2017 December 31, 2017 Payment $6,156,000 9,168,000 7,404,000 In order to help finance the construction, Dobbs issued the following during 2017: 1. $5,190,000 of 10-year, 9% bonds payable, issued at par...

  • Testbank Problem 140 Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a...

    Testbank Problem 140 Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2020 and was completed on December 31, 2020. Dobbs made the following payments to Kiner, Inc. during 2020: Date Payment June 1, 2020 $2,200,000 August 31, 2020 3,300,000 December 31, 2020 2,750,000 In order to help finance the construction, Dobbs issued the following during 2020: 1. $1,870,000 of 10-year, 9% bonds payable,...

  • Testbank Problem 140 Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a...

    Testbank Problem 140 Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2020 and was completed on December 31, 2020. Dobbs made the following payments to Kiner, Inc. during 2020: Payment Date $1,600,000 June 1, 2020 2,400,000 August 31, 2020 December 31, 2020 2,000,000 In order to help finance the construction, Dobbs issued the following during 2020 1. $1,360,000 of 10-year, 9% bonds payable,...

  • . 2017 and was Question Early in 2017. Dobbs Corporation engaged Kiner, Inc. to design and...

    . 2017 and was Question Early in 2017. Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobb's manufacturing facility. Construction was begun completed on December 31, 2017. Dobbs made the following payments to the during 2017: Payment June 1, 2017 $5,772,000 August 31, 2017 9,000,000 December 31, 2017 7,572,000 Date In order to help finance the construction, Dobbs issued the following during 2017: 1. $5.000.000 of 10-year bonds payable, issued at pron May 31, 2017,...

  • Early in 2015, Logan Corporation engaged Reese, Inc. to design and construct a complete modernization of...

    Early in 2015, Logan Corporation engaged Reese, Inc. to design and construct a complete modernization of Logan's manufacturing facility. Construction was begun on January 1, 2015 and was completed on December 31, 2015. Logan made the following payments to Reese, Inc. during 2015: Date Payment June 1, 2015 $2,400,000 August 31, 2015 3,600,000 December 31, 2015 3,000,000 In order to help finance the construction, Logan issued $2,000,000 of 10-year, 9% bonds payable, issued at par on January 2, 2015, with...

  • Finman company designated Jill Holland as pretty cash custodian and established a pretty cash fund of...

    Finman company designated Jill Holland as pretty cash custodian and established a pretty cash fund of 200$. Problem 1 (25 points): The following transactions occurred in Mars Co. in 2019 1. Accounts receivable in the amount of $1,000,000 were assigned to Utley Finance Co. by Mars as security for a loan of $850,000. Utley charged a 3% commission on the accounts; the interest rate on the note is 12%. 2. During the first month, Mars collected $400,000 on assigned accounts...

  • Early in 2020, Qatar Corporation engaged Emirate Ltd. to design and construct a complete modernization of...

    Early in 2020, Qatar Corporation engaged Emirate Ltd. to design and construct a complete modernization of Qatar’s manufacturing facility. Construction began on June 1, 2020, and was completed on December 31, 2020. Qatar made the following payments to Emirate Ltd. during 2020: Date Payment June 1, 2020$ 3,300,000 August 31, 20204,800,000 December 31, 20204,000,000 In order to help finance the construction, Qatar issued the following during 2020: 1.$ 2,000,000, ten-year, 9% bonds payable, issued at par on May 31, 2020,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT