Question

Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbss manufacturin

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Solution 1:
Weighted-Average accumulated expenditure
Date Amount Capitalization period Weighted Average Accumulated Expenditures
01 June 2017 $61,56,000 7/12 $35,91,000
31 August 2017 $91,68,000 4/12 $30,56,000
31 December 2017 $74,04,000 0/7 $0
Total $2,27,28,000 $66,47,000

Solution 2:

Computation of Avoidable Interest
Debt Weighted Average Accumulated Expenditures Interest rate Avoidable Interest amount
From 9% Bond $51,90,000 9% $4,67,100
From 12% Note $12,60,000 12% $1,51,200
Totals $64,50,000 $6,18,300

Solution 3:

Computation of Actual Interest cost incurred
Debt Weighted Average Accumulated Expenditures Interest rate Actual Interest
From 9% Bond (for 7 months) $51,90,000 9% $2,72,475
From 12% Note $12,60,000 12% $1,51,200
Totals $64,50,000 $4,23,675
Total amount of Interest cost to be capitalized for 2017 (Lower of actual interest or Avoidable interest) $4,23,675
Add a comment
Know the answer?
Add Answer to:
Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...

    Early in 2017, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2017 and was completed on December 31, 2017. Dobbs made the following payments to Kiner, Inc. during 2017: Date Payment June 1, 2017 $2,000,000 August 31, 2017 3,000,000 December 31,2017 2,500,000 In order to help finance the construction, Dobbs issued the following during 2017: 1. $1,700,000 of 10-year, 9% bonds payable, issued at par on...

  • Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...

    Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2020 and was completed on December 31, 2020. Dobbs made the following payments to Kiner, Inc. during 2020: Date Payment June 1, 2020 $1,680,000 August 31, 2020 2,520,000 December 31, 2020 2,100,000 In order to help finance the construction, Dobbs issued the following during 2020: 1. $1,428,000 of 10-year, 9% bonds payable, issued at par...

  • Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of...

    Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2020 and was completed on December 31, 2020. Dobbs made the following payments to Kiner, Inc. during 2020: Date June 1, 2020 August 31, 2020 December 31, 2020 Payment $2,280,000 3,420,000 2,850,000 In order to help finance the construction, Dobbs issued the following during 2020: 1. $1,938,000 of 10-year, 9% bonds payable, issued at par...

  • Testbank Problem 140 Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a...

    Testbank Problem 140 Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2020 and was completed on December 31, 2020. Dobbs made the following payments to Kiner, Inc. during 2020: Date Payment June 1, 2020 $2,200,000 August 31, 2020 3,300,000 December 31, 2020 2,750,000 In order to help finance the construction, Dobbs issued the following during 2020: 1. $1,870,000 of 10-year, 9% bonds payable,...

  • Testbank Problem 140 Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a...

    Testbank Problem 140 Early in 2020, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2020 and was completed on December 31, 2020. Dobbs made the following payments to Kiner, Inc. during 2020: Payment Date $1,600,000 June 1, 2020 2,400,000 August 31, 2020 December 31, 2020 2,000,000 In order to help finance the construction, Dobbs issued the following during 2020 1. $1,360,000 of 10-year, 9% bonds payable,...

  • . 2017 and was Question Early in 2017. Dobbs Corporation engaged Kiner, Inc. to design and...

    . 2017 and was Question Early in 2017. Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobb's manufacturing facility. Construction was begun completed on December 31, 2017. Dobbs made the following payments to the during 2017: Payment June 1, 2017 $5,772,000 August 31, 2017 9,000,000 December 31, 2017 7,572,000 Date In order to help finance the construction, Dobbs issued the following during 2017: 1. $5.000.000 of 10-year bonds payable, issued at pron May 31, 2017,...

  • 4. total interest to be capitalize during 2010 Early in 2010, Dobbs Corporation engaged Kiner, Inc....

    4. total interest to be capitalize during 2010 Early in 2010, Dobbs Corporation engaged Kiner, Inc. to design and construct a complete modernization of Dobbs's manufacturing facility. Construction was begun on June 1, 2010 and was completed on December 31, 2010. Dobbs made the following payments to Kiner, Inc. during 2010: Date Payment June 1, 2010 $3,600,000 August 31, 2010 5,400,000 December 31, 2010 4,500,000 In order to help finance the construction, Dobbs issued the following during 2010: 1. $3,000,000...

  • Early in 2020, Qatar Corporation engaged Emirate Ltd. to design and construct a complete modernization of...

    Early in 2020, Qatar Corporation engaged Emirate Ltd. to design and construct a complete modernization of Qatar’s manufacturing facility. Construction began on June 1, 2020, and was completed on December 31, 2020. Qatar made the following payments to Emirate Ltd. during 2020: Date Payment June 1, 2020$ 3,300,000 August 31, 20204,800,000 December 31, 20204,000,000 In order to help finance the construction, Qatar issued the following during 2020: 1.$ 2,000,000, ten-year, 9% bonds payable, issued at par on May 31, 2020,...

  • Early in 2020, Qatar Corporation engaged Emirate Ltd. to design and construct a complete modernization of...

    Early in 2020, Qatar Corporation engaged Emirate Ltd. to design and construct a complete modernization of Qatar’s manufacturing facility. Construction began on June 1, 2020, and was completed on December 31, 2020. Qatar made the following payments to Emirate Ltd. during 2020: Date Payment June 1, 2020$ 3,300,000 August 31, 20204,800,000 December 31, 20204,000,000 In order to help finance the construction, Qatar issued the following during 2020: 1.$ 2,000,000, ten-year, 9% bonds payable, issued at par on May 31, 2020,...

  • Early in 2015, Logan Corporation engaged Reese, Inc. to design and construct a complete modernization of...

    Early in 2015, Logan Corporation engaged Reese, Inc. to design and construct a complete modernization of Logan's manufacturing facility. Construction was begun on January 1, 2015 and was completed on December 31, 2015. Logan made the following payments to Reese, Inc. during 2015: Date Payment June 1, 2015 $2,400,000 August 31, 2015 3,600,000 December 31, 2015 3,000,000 In order to help finance the construction, Logan issued $2,000,000 of 10-year, 9% bonds payable, issued at par on January 2, 2015, with...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT