a) Plantwide predetermine overhead rate = (20000*3+30000*1+910000)/50000 = 20 per machine hour

b) Total manufacturing cost

Job D-70 Job C-200
Direct material 700000 550000
Direct labor 360000 400000
Overhead Applied 400000 600000
Total manufacturing cost 1460000 1550000

c) Bid price

Job D-70 Job C-200
Bid price 1460000*1.5 = 2190000 1550000*1.5 = 2325000

d) Cost of goods sold = 1460000+1550000 = 3010000

Add a comment
Know the answer?
Add Answer to:
Delph Company uses a job-order costing system and has two manufacturing departments-Molding and Fabrication. The company...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company...

    Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company provided the following estimates at the beginning of the year:    Molding Fabrication Total Machine-hours 25,000 35,000 60,000 Fixed manufacturing overhead costs $ 770,000 $ 240,000 $ 1,010,000 Variable manufacturing overhead cost per machine-hour $ 5.70 $ 5.70    During the year, the company had no beginning or ending inventories and it started, completed, and sold only two jobs—Job D-70 and Job C-200. It...

  • Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company...

    Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company provided the following estimates at the beginning of the year:    Molding Fabrication Total Machine-hours 34,000 44,000 78,000 Fixed manufacturing overhead costs $ 760,000 $ 230,000 $ 990,000 Variable manufacturing overhead cost per machine-hour $ 6.10 $ 6.10    During the year, the company had no beginning or ending inventories and it started, completed, and sold only two jobs—Job D-70 and Job C-200. It...

  • Delph Company uses a job-order costing system and has two manufacturing departments-Molding and Fabrication. The company...

    Delph Company uses a job-order costing system and has two manufacturing departments-Molding and Fabrication. The company provided the following estimates at the beginning of the year. Machine-hours Fixed manufacturing overhead costs Variable manufacturing overhead cost per machine-hour Molding Fabrication 26,000 36,000 $ 780,000 $200,000 $ 5.40 $ 5.40 Total 62,000 $980,000 During the year, the company had no beginning or ending inventories and it started, completed, and sold only two jobs-Job D-70 and Job C-200. It provided the following information...

  • Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company...

    Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company provided the following estimates at the beginning of the year: Molding Fabrication Total Machine-hours 25,000 35,000 60,000 Fixed manufacturing overhead costs $ 730,000 $ 280,000 $ 1,010,000 Variable manufacturing overhead cost per machine-hour $ 5.80 $ 5.80 During the year, the company had no beginning or ending inventories and it started, completed, and sold only two jobs—Job D-70 and Job C-200. It provided the...

  • Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company...

    Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company provided the following estimates at the beginning of the year:    Molding Fabrication Total Machine-hours 29,000 39,000 68,000 Fixed manufacturing overhead costs $ 760,000 $ 240,000 $ 1,000,000 Variable manufacturing overhead cost per machine-hour $ 6.00 $ 6.00    During the year, the company had no beginning or ending inventories and it started, completed, and sold only two jobs—Job D-70 and Job C-200. It...

  • Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company...

    Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company provided the following estimates at the beginning of the year:    Molding Fabrication Total Machine-hours 20,000 30,000 50,000 Fixed manufacturing overhead costs $ 700,000 $ 210,000 $ 910,000 Variable manufacturing overhead cost per machine-hour $ 3.00 $ 1.00 During the year, the company had no beginning or ending inventories and it started, completed, and sold only two jobs—Job D-70 and Job C-200. It provided...

  • Delph Company uses a job-order costing system and has two manufacturing departments-Molding and Fabrication. The company...

    Delph Company uses a job-order costing system and has two manufacturing departments-Molding and Fabrication. The company provided the following estimates at the beginning of the year: Machine-hours Fixed manufacturing overhead costs Variable manufacturing overhead cost per machine-hour Molding Fabrication Total 23,000 32,000 55,000 $ 720,000 $ 220,000 $ 940,000 S 4.00 $ 1.00 During the year, the company had no beginning or ending inventories and it started, completed, and sold only two jobs- Job D-70 and Job C-200. It provided...

  • Delph Company uses a job-order costing system and has two manufacturing departments-Molding and Fabrication. The company...

    Delph Company uses a job-order costing system and has two manufacturing departments-Molding and Fabrication. The company provided the following estimates at the beginning of the year: Machine-hours Fixed manufacturing overhead costs Variable manufacturing overhead cost per machine-hour Molding Fabrication Total 23,000 32,000 55,000 $ 720,000 $ 220,000 $ 940,000 S 4.00 $ 1.00 During the year, the company had no beginning or ending inventories and it started, completed, and sold only two jobs- Job D-70 and Job C-200. It provided...

  • Delph Company uses a job-order costing system and has two manufacturing departments-Molding and Fabrication. The company...

    Delph Company uses a job-order costing system and has two manufacturing departments-Molding and Fabrication. The company provided the following estimates at the beginning of the year: Machine-hours Fixed manufacturing overhead costs Variable manufacturing overhead cost per machine-hour Molding Fabrication 23,000 33,000 $ 750,000 $ 250,000 $ 5.90 $ 5.90 Total 56,000 $1,000,000 During the year, the company had no beginning or ending inventories and it started, completed, and sold only two jobs-Job D-70 and Job C-200. It provided the following...

  • Delph Company uses a job-order costing system and has two manufacturing departments-Molding and Fabrication. The company...

    Delph Company uses a job-order costing system and has two manufacturing departments-Molding and Fabrication. The company provided the following estimates at the beginning of the year Machine-hours Fixed manufacturing overhead costs Variable manufacturing overhead cost per machine-hour Molding 24,000 $ 740,000 S 4.00 Fabrication 32,800 $ 280,000 $ 1.00 Total 56,888 $1,020,000 During the year, the company had no beginning or ending inventories and it started, completed, and sold only two jobs- Job D 70 and Job C 200. It...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT