Hula Enterprises is considering a new project to produce solar water heaters. The finance manager wishes to find an appropriate risk adjusted discount rate for the project. The (equity) beta of Hot Water, a firm currently producing solar water heaters, is 1.4. Hot Water has a debt to total value ratio of 0.6. The expected return on the market is 0.12, and the riskfree rate is 0.08. Suppose the corporate tax rate is 35 percent. Assume that debt is riskless throughout this problem. (Round your answers to 2 decimal places. (e.g., 0.16))

a. The expected return on the unlevered equity (return on asset, R0) for the solar water heater project is  %.
b. If Hula is an equity financed firm, the weighted average cost of capital for the project is  %.
c. If Hula has a debt to equity ratio of 2, the weighted average cost of capital for the project is  %.
d. The finance manager believes that the solar water heater project can support 45 cents of debt for every dollar of asset value, i.e., the debt capacity is 45 cents for every dollar of asset value. Hence she is not sure that the debt to equity ratio of 2 used in the weighted average cost of capital calculation is valid. Based on her belief, the appropriate debt ratio to use is  %. The weighted average cost of capital that you will arrive at with this capital structure is  %.
0 0
Add a comment Improve this question Transcribed image text
Answer #1
a
D/A =0.6
D/E=D/(A-D)=0.6/(1-0.6)=1.5
As per CAPM
expected return = risk-free rate + beta * (expected return on the market - risk-free rate)
Expected return% = 8 + 1.4 * (12 - 8)
Expected return% = 13.6
Levered cost of equity = Unlevered cost of equity+D/E*( Unlevered cost of equity-cost of debt)*(1-tax rate)
13.6 = Unlevered cost of equity+1.5*(Unlevered cost of equity-8)*(1-0.35)
Unlevered cost of equity = 10.84
b
For unlevered firm WACC = unlevered cost of equity=10.84%
c
Levered cost of equity = Unlevered cost of equity+D/E*( Unlevered cost of equity-cost of debt)*(1-tax rate)
Levered cost of equity = 10.84+2*(10.84-8)*(1-0.35)
Levered cost of equity = 14.53
After tax rate = Cost of debt * (1-Tax rate)
After tax rate = 8 * (1-0.35)
After tax rate = 5.2
D/A = D/(E+D)
D/A = 2/(1+2)
=0.66667
Weight of equity = 1-D/A
Weight of equity = 1-0.66667
W(E)=0.33333
WACC=after tax cost of debt*W(D)+cost of equity*W(E)
WACC=5.2*0.66667+14.53*0.33333
WACC=8.31%
d
D/A =0.45
D/E=D/(A-D)=0.45/(1-0.45)=0.8182
Levered cost of equity = Unlevered cost of equity+D/E*( Unlevered cost of equity-cost of debt)*(1-tax rate)
Levered cost of equity = 10.84+0.81818*(10.84-8)*(1-0.35)
Levered cost of equity = 12.35
After tax rate = Cost of debt * (1-Tax rate)
After tax rate = 8 * (1-0.35)
After tax rate = 5.2
Weight of equity = 1-0.45
W(E)=0.55
WACC=after tax cost of debt*W(D)+cost of equity*W(E)
WACC=5.2*0.45+12.35*0.55
WACC=9.13%
Add a comment
Know the answer?
Add Answer to:
Hula Enterprises is considering a new project to produce solar water heaters. The finance manager wishes...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Hula Enterprises is considering a new project to produce solar water heaters. The finance manager wishes...

    Hula Enterprises is considering a new project to produce solar water heaters. The finance manager wishes to find an appropriate risk adjusted discount rate for the project. The (equity) beta of Hot Water, a firm currently producing solar water heaters, is 1.6. Hot Water has a debt to total value ratio of 0.2. The expected return on the market is 0.08, and the riskfree rate is 0.06. Suppose the corporate tax rate is 40 percent. Assume that debt is riskless...

  • Hula Enterprises is considering a new project to produce solar water heaters. The finance manager wishes to find an appropriate risk adjusted discount rate for the project. The (equity) beta of Ho...

    Hula Enterprises is considering a new project to produce solar water heaters. The finance manager wishes to find an appropriate risk adjusted discount rate for the project. The (equity) beta of Hot Water, a firm currently producing solar water heaters, is 1.2. Hot Water has a debt to total value ratio of 0.6. The expected return on the market is 0.11, and the riskfree rate is 0.04. Suppose the corporate tax rate is 38 percent. Assume that debt is riskless...

  • finance

    A firm currently has a debt-equity ratio of 1/2. The debt, which is virtually riskless, pays an interest rate of 7 %. The expected rate of return on the equity is 14 %. What is the Weighted-Average Cost of Capital if the firm pays no taxes? Enter your answer as a percentage rounded to two decimal places. 

  • As a project manager of UMBRELLA CORPORATION you are evaluating a new project, the cash flow...

    As a project manager of UMBRELLA CORPORATION you are evaluating a new project, the cash flow of which appear as below, and that your company uses a require rate of return of 7% to evaluate on the project such as these: Year Cash Flows (RM20,000) RM5.000 RM4,000 RM6,000 RM7,000 RM8.000 FIN2102 (F) Page 3 of 4 i. What is the project's payback period? (4 marks) ii. What is the project's net present value? (5 marks) iii. Should your company accept...

  • A company wishes to finance a new project. It will raise 40 million dollars using four borrowing ...

    A company wishes to finance a new project. It will raise 40 million dollars using four borrowing sources. The sources will be 3 million bonds 11 million bank loan 10 million common stock and 16 million preferred stock. The bonds will be at a dividend rate of 6 percent issued quarterly. The bank loan will be at 12 percent paid monthly. Earning per share of common stock are taken to be 14 cents per share with a stock price of...

  • You have recently joined the finance department of Flames plc as a graduate trainee. The Finance...

    You have recently joined the finance department of Flames plc as a graduate trainee. The Finance Director would like to use the weighted average cost of capital as the discount rate to calculate whether to invest in a new overseas plant. She is comfortable calculating the cost of equity however she is unsure of how to calculate the cost of listed debt finance. You have been provided with the following information and asked to look into this. The company has...

  • Your are the financial manager of Banana company, and the company want invest f this project...

    Your are the financial manager of Banana company, and the company want invest f this project is about 100 millions RMB which include 90 million RMB (nvestment for fixed asset and 10 millions for working capital. The tax law permIt Banana depreciate all tired asset in 5 years in straight-line method, and the marginal rate is 40% . According to your experience, you forecast the sales of new project in future 5 years as described in table 1, and from...

  • Phone Home, Inc. is considering a new 4-year expansion project that requires an initial fixed asset...

    Phone Home, Inc. is considering a new 4-year expansion project that requires an initial fixed asset investment of $3 million. The fixed asset will be depreciated straight-line to zero over its 4-year tax life, after which time it will have a market value of $225,000. The project requires an initial investment in net working capital of $330,000, all of which will be recovered at the end of the project. The project is estimated to generate $2,640,000 in annual sales, with...

  • You are a financial manager for Lenzie Corporation. The firm needs to purchase equipment for its...

    You are a financial manager for Lenzie Corporation. The firm needs to purchase equipment for its new production plant. The total cost of the equipment is $1,500,000. It is estimated that the after-tax cash inflows from the project will be $710,000 annually for five years. Lenzie Corporation has a market value debt-to-assets ratio of 40%. The firm’s common stock has a beta of 1.85, the risk-free rate is 1.2%, and the expected return on the market portfolio is 7%. The...

  • Zeta Corporation is considering a project that costs $18,000,000 and will increase the after-tax cash flows...

    Zeta Corporation is considering a project that costs $18,000,000 and will increase the after-tax cash flows by $4,000,000 per year for five years. The company has total assets of $80,000,000 and total debt of $20,000,000. The borrowing rate is 10 percent, the corporate tax rate is 21%, the risk-free rate is 3%, the beta of the stock is 1.5, and the return on the market is 12 percent The percent of debt in the capital structure is The cost of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT