I'm only missing this REQUIREMENT 8. Please let me know how you get the number that you multiply with the PDOHR(120%) for Direct Material Cost. Show all calculations please and where you get the numbers.
Calculate following
Ending work in process | 42800 |
Direct material cost (42800-11250-13500) | 18050 |
Applied overhead cost (11250*1.20) | 13500 |
I'm only missing this REQUIREMENT 8. Please let me know how you get the number that...
Selected T-accounts of Moore Company are given below for the just completed year: Manufacturing Overhead 203,800 Credits Debits - Manufacturing o ? Debits Bal. 1/1 Debits Bal. 12/31 Raw Materials 28,000 Credits 146,000 38,000 Work in Process 33,000 Credits 103,000 189,000 226,800 Factory Wages 509,000 ,000 Debits Debits Bal. 1/1 Direct materials Direct labor Overhead Bal. 12/31 Factory Wages Payable 211,000 Bal. 1/1 Credits Bal. 12/31 15,500 206,000 10,500 Cost of Goods Sold Finished Goods 53,000 Credits ? Debits Bal....
All one problem, multiple parts. Thank you! Selected T-accounts of Moore Company are given below for the just completed year: Debits Bal. 1/1 Debits Bal. 12/31 Manufacturing Overhead 188,480 Credits Raw Materials 35,000 Credits 160,000 45,000 Work in Process 40,000 Credits 110,000 210,000 218,400 530,000 Debits Bal. 1/1 Direct materials Direct labor Overhead Bal. 12/31 Factory Wages Payable 225,000 Bal. 1/1 Credits Bal. 12/31 19,000 220,000 14,000 Cost of Goods Sold Debits Bal. 1/1 Debits Bal. 12/31 Finished Goods 60,000...
All one problem, thank you. Selected T-accounts of Moore Company are given below for the just completed year: Bal. 1/1 Debits Bal. 12/31 Debits Manufacturing Overhead 188, 480 Credits Raw Materials 35,000 Credits 160,000 45,000 Work in Process 40,000 Credits 110,000 210,000 218,400 530,000 Debits Bal. 1/1 Direct materials Direct labor Overhead Bal. 12/31 Factory Wages Payable 225,000 Bal. 1/1 Credits Bal. 12/31 19,000 220,000 14,000 Cost of Goods Sold Debits Bal. 1/1 Debits Bal. 12/31 Finished Goods 60,000 Credits...
Selected T-accounts of Moore Company are given below for the just completed year: Raw Materials Bal. 1/1 28,000 Credits ? Debits 146,000 Bal. 12/31 38,000 Manufacturing Overhead Debits 203,800 Credits ? Work in Process Bal. 1/1 33,000 Credits 509,000 Direct materials 103,000 Direct labor 189,000 Overhead 226,800 Bal. 12/31 ? Factory Wages Payable Debits 211,000 Bal. 1/1 15,500 Credits 206,000 Bal. 12/31 10,500 Finished Goods Bal. 1/1 53,000 Credits ? Debits ? Bal. 12/31 79,500 Cost of Goods Sold Debits...
Selected T-accounts of Moore Company are given below for the just completed year: Manufacturing Overhead 230,000 Credits Bal. 1/1 Debits al. 12/31 Raw Materials 15,000 Credits 120.000 25,000 Work in Process 20,000 Credits 90.000 150,000 240.000 470,000 Debits Bal. 1/1 Direct materials Direct labor Overhead Bal. 12731 Factory Wages Payable 185,000 Bal. 1/1 Credits Bal. 12/31 9,000 180,000 4,000 Cost of Goods Sold Finished Goods 40,000 Credits al. 171 Debits al. 12731 60,000 Required: 1. What was the cost of...
Selected T-accounts of Moore Company are given below for the just completed year: Manufacturing Overhead 203,200 Credits ? Debits ? Bal. 1/1 Debits Bal. 12/31 Raw Materials 25,000 Credits 140,000 35,000 Work in Process 30,000 Credits 100,000 180,000 223,200 500,000 Debits Bal. 1/1 Direct materials Direct labor Overhead Bal. 12/31 Factory Wages Payable 205,000 Bal. 1/1 Credits Bal. 12/31 14,000 200,000 9,000 Cost of Goods Sold Finished Goods 50,000 Credits ? Debits Bal. 1/1 Debits Bal. 12/31 75,000 Required: 1....
3 Homework o Help Save a Problem 3-11 T-Account Analysis of Cost Flows [LO3-2, LO3-3, LO3-4) Selected T-accounts of Moore Company are given below for the just completed year: Manufacturing Overhead 181.900 Credits Debits Bal. 1/1 Debits Bal. 12/31 Raw Materials 31,000 Credits 152, eee 41,000 Work in Process 36,800 Credits 106,000 198,000 207,900 518,000 Debits Bal. 1/1 Direct materials Direct labor Overhead Bal. 12/31 Factory Wages Payable 217,000 Bal. 1/1 Credits Bal. 12/31 17,000 212,000 12,000 Cost of Goods...
Chec Manufacturing Overhead 233,800 Credits ? 473,000 Debits Raw Materials Bal. 1/1 16,800 Credits Debits 122,000 Bal. 12/31 26,80 Work in Process Bal. 1/1 21,000 Credits Direct materials 91,000 Direct labor 153,000 Overhead 244,880 Bal. 12/31 Finished Goods Bal. 1/1 41,000 Credits Debits Bal. 12/31 61,500 Factory Wages Payable 187,000 Bal. 1/ 1 Credits Bal. 12/31 9 ,500 182,800 4,500 Cost of Goods Sold ? Required: 1. What was the cost of raw materials used in production during the year?...
Selected T-accounts of Moore Company are given below for the just completed year: Manufacturing Overhead 188,400 Credits Debits Bal. 1/1 Debits Bal. 12/31 530,000 Debits Bal. 1/1 Direct materials Direct labor Overhead Bal. 12/31 Raw Materials 35,000 Credits 160,000 45,000 Work in Process 40,000 Credits 110,000 210,000 218,400 ? Finished Goods 60,000 Credits ? 90,000 Factory Wages Payable 225,000 Bal. 1/1 Credits Bal. 12/31 19,000 220,000 14,000 Cost of Goods Sold ? Debits Bal. 1/1 Debits Bal. 12/31 Required: 1....
Req 1 to 5 Req 6 Req 7 Req 8 If overhead is applied to production on the basis of direct labor cost, what predetermined overhead rate was in effect during the year? The predetermined overhead rate was % of direct labor cost < Req 1 to 5 Req7 > Req 1 to 5 Req 6 Req 7 Req 8 --------- Was manufacturing overhead underapplied or overapplied? By how much? Manufacturing overhead was < Req 6 Req8 > Req 1...