Statement of Equivalent production | |||||||
Particulars | Direct Materials | %completion | Equivalent mat | Conversion | %completion | Equivalent Conv | Total |
Inventory in process, April 01 | |||||||
Started and completed in April | |||||||
Transferred to finished goods in April | 17,000.00 | 100% | 17,000.00 | 17,000.00 | 100% | 17,000.00 | |
Inventory in process, April 30 | 1,000.00 | 100% | 1,000.00 | 1,000.00 | 40% | 400.00 | |
a) Equivalent Units of production | 18,000.00 | 17,400.00 | |||||
Opening WIP Costs | 100,000.00 | 70,000.00 | 170,000.00 | ||||
Current Month Costs | 800,000.00 | 365,000.00 | 1,165,000.00 | ||||
Total costs | 900,000.00 | 435,000.00 | 1,335,000.00 | ||||
b) Cost per Equivalent units | 50.00 | 25.00 | |||||
Ending WIP Units | 1,000.00 | 400.00 | |||||
c)Cost of Ending WIP | 50,000.00 | 10,000.00 | 60,000.00 | ||||
Units completed and transferred out | 17,000.00 | 17,000.00 | |||||
c) Cost of Units completed and transferred out | 850,000.00 | 425,000.00 | 1,275,000.00 |
Manufacturing costs: Materials $33.000; labor $21,000; and overhead $36,000. b. De c. Sh E3.11 manu Instructions...
please typed no hand written thank you Prepare a production cost report. E3.8 (LO 3. 4), AP The Blending Department of Luongo Company has the following cost and production data for the month of April. Determine equivalent units, unit costs, and assignment of costs. Costs: Work in process, April 1 Direct materials: 100% complete $100,000 Conversion costs: 20% complete 70.000 Cost of work in process, April 1 $170,000 Costs incurred during production in April Direct materials $ 800,000 Conversion costs...
For the month of April. Costs: Work in process, April 1 Direct materials: 100% complete $100,000 Conversion costs: 20% complete 70,000 Cost of work in process, April 1 $170,000 Costs incurred during production in April Direct materials $ 800,000 Conversion costs 365,000 Costs incurred in April $1,165,000 Units transferred out totaled 17,000. Ending work in process was 1,000 units that are 100% complete as to materials and 40% complete as to conversion costs. Using the results of the equivalents units...
E16-6 The Cutting Department of Cassel Company has the following production and cost data for July Det cos Production 1. Transferred out 12,000 units. 2. Started 3,000 units that are 60% complete as to conversion costs and 100% complete as to materials at July 31. Costs Beginning work in process Materials Labor Manufacturing overhead $ -0- 45,000 16,200 18,300 Materials are entered at the beginning of the process. Conversion costs are incurred uni- formly during the process Instructions (a) Determine...
E16-6 The Cutting Department of Cassel data for July ing Department of Cassel Company has the following production and cost Determine cu costs, and assi (LO 3, 4), AP Production Costs 1. Transferred out 12,000 units $-0- Beginning work in process 2. Started 3,000 units that are 60% 45,000 Materials complete as to conversion 16,200 Labor costs and 100% complete as Manufacturing overhead 18,300 to materials at July 31. materials are entered at the beginning of the process. Conversion costs...
The Mixing Department of Bravo Company has the following cost and production data for the month of April. Costs: Work in process, April 1 Direct materials: 100% complete $100,000 Conversion costs: 20% complete 70,000 Cost of work in process, April 1 $170,000 Costs incurred during production in April Direct materials $ 800,000 Conversion costs 365,000 Costs incurred in April $1,165,000 Units transferred out totaled 17,000. Ending work in process was 1,000 units that are 100% complete as to materials and...
Exercise 3-8 (Video) The Blending Department of Luongo Company has the following cost and production data for the month of April. Costs: Work in process, April 1 Direct materials: 100% complete $101,000 Conversion costs: 20% complete 70,700 Cost of work in process, April 1 $171,700 Costs incurred during production in April Direct materials $808,000 Conversion costs 368,650 Costs incurred in April $1,176,650 Units transferred out totaled 17,170. Ending work in process was 1,010 units that are 100% complete as to...
The Blending Department of Luongo Company has the following cost and production data for the month of April. $111,000 77,700 Costs: Work in process, April 1 Direct materials: 100% complete Conversion costs: 20% complete Cost of work in process, April 1 Costs incurred during production in April Direct materials Conversion costs Costs incurred in April $188,700 $888,000 405,150 $1,293,150 Units transferred out totaled 18,870. Ending work in process was 1,110 units that are 100% complete as to materials and 40%...
Exercise 16-08 The Blending Department of Luongo Company has the following cost and production data for the month of April. Conta: Work in process, April 1 Direct materials: 100% complete Conversion costs: 20% complete Cost of work in process, April 1 Costs incurred during production in April Direct materials Conversion costs Costs incurred in April $106,000 74,200 $180,200 $848,000 386,900 $1,234,900 Units transferred out totaled 18,020. Ending work in process was 1,060 units that are 100% complete as to materials...
The Blending Department of Luongo Company has the following cost and production data for the month of April. $119,000 Costs: Work in process, April 1 Direct materials: 100% complete Conversion costs: 20% complete Cost of work in process, April 1 Costs incurred during production in April Direct materials Conversion costs Costs incurred in April 83,300 $202,300 $952,000 434,350 $1,386,350 Units transferred out totaled 20,230. Ending work in process was 1,190 units that are 100% complete as to materials and 40%...
Exercise 17-8 The Blending Department of Luongo Company has the following cost and production data for the month of April. Costs: Work in process, April 1 Direct materials: 100% complete Conversion costs: 20% complete Cost of work in process, April 1 Costs incurred during production in April Direct materials Conversion costs Costs incurred in April $109,000 76,300 $185,300 $872,000 397,850 $1,269,850 Units transferred out totaled 18,530. Ending work in process was 1,090 units that are 100% complete as to materials...