Question

12) A project has a probability of 0.3 to generate a payoff of $15m, and 0.7 with payoff of $5m. a. What is the expected payo

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1.
Expected payoff=0.3*15+0.7*5=8 million
Variance=0.3*(15-8)^2+0.7*(5-8)^2=21 million^2
Standard Deviation=sqrt(21)=4.582575695 million

2.
Expected returns=0.3*(15/6-1)+0.7*(5/6-1)=33.3333333 %
Variance=0.3*(15/6-1-1/3)^2+0.7*(5/6-1-1/3)^2=5833.33333%^2
Standard deviation=sqrt(5833.3333%%)=76.3762616%

Add a comment
Know the answer?
Add Answer to:
12) A project has a probability of 0.3 to generate a payoff of $15m, and 0.7...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A project has a probability of 0.3 to generate a payoff of $15m, and 0.7 with...

    A project has a probability of 0.3 to generate a payoff of $15m, and 0.7 with payoff of $5m. A) What is the expected payoff of the project, its variance and standard deviation? B) if it takes an initial investment of $6m, what is the expected return of the project, its variance, and standard deviation? Ignore time value of money 12) A project has a probability of 0.3 to generate a payoff of $15m, and 0.7 with payoff of $5m....

  • 12) A project has a probability of 0.3 to generate a payoff of $15m, and 0.7...

    12) A project has a probability of 0.3 to generate a payoff of $15m, and 0.7 with payoff of $5m. a. What is the expected payoff of the project, its variance and standard deviation? b. If it takes an initial investment of $6m, what is the expected return of the project, its variance and standard deviation? Ignore time value of money.

  • A project has a 0.7 chance of doubling your investment in a year and a 0.3...

    A project has a 0.7 chance of doubling your investment in a year and a 0.3 chance of halving your investment in year. What is the standard deviation of the rate of return on this investment? (Do not round intermediate calculations. Round your answer to 2 decimal places.) Standard deviation

  • 12 points) uonsanb Hayek Corporation has a 0.3 probability of a return of 0.66, a 0.3 probability of a rate of ret...

    12 points) uonsanb Hayek Corporation has a 0.3 probability of a return of 0.66, a 0.3 probability of a rate of return of 0.05, and the remaining probability of a 0.30 rate of return. What is the variance in the expected rate of return of Hayek Corporation? Your Answer:

  • A project with an initial outlay of Tshs 10 million has a 0.2 probability of producing...

    A project with an initial outlay of Tshs 10 million has a 0.2 probability of producing a return of Tshs 8 million in Year 1 and a 0.8 probability of delivering a return of Tshs 5 million in Year 1. If the Tshs 8 million result occurs then the second year could return either Tshs 7 million (probability of 0.5) or Tshs 3 million (probability of 0.5). If the Tshs 5 million result in Year 1 occurs then either Tshs...

  • Project A Project & CHINA initial investment £15m 25% less than uk Revenue £6m per annual...

    Project A Project & CHINA initial investment £15m 25% less than uk Revenue £6m per annual 10% less than uk operating cost £1. 2m per annual 50% less than ute Residual Value £um £um Project length bys Syrs 0 Calculate Payback and Average return for each project and make a recommendation to the board on which project to pick What impact would a 35% increase in the investment cast make in your decision ?

  • Problem 7-15 Suppose you have a project that has a 0.3 chance of tripling your investment...

    Problem 7-15 Suppose you have a project that has a 0.3 chance of tripling your investment in a year and a 0.7 chance of halving your investment in a year. What is the standard deviation of the rate of return on this investment? (Do not round intermediate calculations. Enter your answer as a decimal rounded to 4 places.) Standard deviation

  • 1. a. Two investors, A and B, are evaluating the same investment opportunity, which has an expected value of £100. The u...

    1. a. Two investors, A and B, are evaluating the same investment opportunity, which has an expected value of £100. The utility functions of A and B are ln(x) and ​​​​​x​2, respectively. Which investor has a certainty equivalent higher than 100? Which investor requires the higher risk premium? b. (i) Describe suitable measures of risk for ‘loss-aversion’ and ‘risk aversion’. (ii) Concisely define the term ‘risk neutral’ with respect to a utility function u (w), where w is the realisation...

  • you are considering investing in two securities. Security 1 has a expected return of 12% and...

    you are considering investing in two securities. Security 1 has a expected return of 12% and a standard deviation of return of 10%. Security 2 has an expected return of 9%and a standard deviation of returns of 8%. The correlation coefficient of returns for the two securities is 0.3. What would the weights be for each of the two securities in the minimum variance portfolio? W1= W2= Given the weights computed in (a), compute the expected return and standard deviation...

  • A stock DEF has the following payoffs probabilities: Probability 0.3 0.45 0.25 Payoff $50 $60 $90...

    A stock DEF has the following payoffs probabilities: Probability 0.3 0.45 0.25 Payoff $50 $60 $90 What is the Variance of payoffs of the stock? Note: The numbers for this question may have been changed from the previous question. Give your answer for Variance as a number and not a percentage. Your Answer:

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT