Salmont Corporation uses the FIFO method in its process costing system. The company reported 27,000 equivalent units of production for materials last month. The company's beginning work in process inventory consisted of 7,000 units, 35% complete with respect to materials. The ending work in process inventory consisted of 5,000 units, 65% complete with respect to materials. The number of units started during the month was:
Calculation of no of unit started during the month | |||||
Particulars | unit | % of completion | equivalent unit | ||
Equivalent | 27000 | 100% | 27000 | ||
less: Work in processs beginning | 7000 | 65% | 4550 | ||
less: work in process ending | 5000 | 65% | 3250 | ||
add: inventory at the end | 5000 | ||||
number of unit started during the month | 24200 |
Salmont Corporation uses the FIFO method in its process costing system. The company reported 27,000 equivalent...
13 Salmont Corporation uses the FIFO method in its process costing system. The company reported 27000 equivalent units of production for materials last month. The company's beginning work in process inventory consisted of 7,000 units, 35% complete with respect to materials. The ending work in process inventory consisted of 5,000 units, 65% complete with respect to materials. The number of units started during the month was 8 00:42 Multiple Choice 27450 units 25,500 units 24,200 units 26.200 units
Marston Corporation uses the FIFO method in its process costing system. The equivalent units of production for March for conversion costs totaled 37,500 units. The beginning work in process inventory in March consisted of 15,000 units, 60% complete with respect to conversion costs. The ending work in process inventory in March consisted of 10,000 units, 75% complete with respect to conversion costs. The number of units started during the month was: Multiple Choice 41,500 units 34,000 units 25,000 units 72,500...
Mullins Corporation uses the FIFO method in its process costing system. Data concerning the first processing department for the most recent month are listed below: Beginning work in process inventory: Units in beginning work in process inventory 1,300 Materials costs $ 12,700 Conversion costs $ 22,800 Percent complete with respect to materials 75 % Percent complete with respect to conversion 65 % Units started into production during the month 9,800 Units transferred to the next department during the month 9,000...
Mullins Corporation uses the FIFO method in its process costing system. Data concerning the first processing department for the most recent month are listed below: Beginning work in process inventory: Units in beginning work in process inventory 1,100 Materials costs $ 12,300 Conversion costs $ 22,600 Percent complete with respect to materials 75 % Percent complete with respect to conversion 65 % Units started into production during the month 9,400 Units transferred to the next department during the month 8,600...
Mullins Corporation uses the FIFO method in its process costing system. Data concerning the first processing department for the most recent month are listed below: Beginning work in process inventory: Units in beginning work in process inventory 900 Materials costs $ 11,900 Conversion costs $ 22,400 Percent complete with respect to materials 75 % Percent complete with respect to conversion 65 % Units started into production during the month 9,000 Units transferred to the next department during the month 8,200...
Ozdemir Corporation uses the FIFO method in its process costing system. Data concerning the first processing department for the most recent month are listed below: Beginning work in process inventory: Units in beginning work in process inventory Materials costs Conversion costs Percent complete with respect to materials Percent complete with respect to conversion Units started into production during the month Units transferred to the next department during the month Materials costs added during the month Conversion costs added during the...
Annenbaum Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory in the first processing department consisted of 1,500 units. The costs and percentage completion of these units in beginning inventory were: Cost Percent Complete Materials costs $ 6,800 65% Conversion costs $ 7,900 45% A total of 8,700 units were started and 7,000 units were transferred to the second processing department during the month. The following costs were incurred in the first processing department...
Annenbaum Corporation uses the
weighted-average method in its process costing system. This month,
the beginning inventory in the first processing department
consisted of 2,400 units. The costs and percentage completion of
these units in beginning inventory were: Cost Percent Complete
Materials costs $ 7,700 65% Conversion costs $ 8,800 45% A total of
10,500 units were started and 7,900 units were transferred to the
second processing department during the month. The following costs
were incurred in the first processing department...
Mullins Corporation uses the FIFO method in its process costing system. Data concerning the first processing department for the most recent month are isted below! 780 $ 11,500 $ 22,200 753 655 Beginning work in process inventory: Units in beginning work in process inventory. Materials costs Conversion costs Percent complete with respect to materials Percent complete with respect to conversion Units started into production during the month Units transferred to the next department during the month Materials costs added during...
1. Annenbaum Corporation uses the weighted-average method in its process costing system. This month, the beginning inventory in the first processing department consisted of 400 units. The costs and percentage completion of these units in beginning inventory were: Cost Percent Complete Materials costs $ 5,700 65% Conversion costs $ 6,800 45% A total of 6,500 units were started and 5,900 units were transferred to the second processing department during the month. The following costs were incurred in the first processing...