Question

Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data...

Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available: Quantity of direct labor used 640 hrs. Actual rate for direct labor $13.7 per hr. Bicycles completed in April 300 bicycles Standard direct labor per bicycle 2 hrs. Standard rate for direct labor $14 per hr. a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. Direct Labor Rate Variance $ -192 Favorable Direct Labor Time Variance $ Unfavorable Total Direct Labor Cost Variance $ Unfavorable b. How much direct labor should be debited to Work in Process? $

0 0
Add a comment Improve this question Transcribed image text
Answer #1
a
Direct Labor Rate Variance -192 Favorable =640*(13.7-14)
Direct Labor Time Variance 560 Unfavorable =14*(640-300*2)
Total Direct Labor Cost Variance 368 Unfavorable =(640*13.7)-(300*2*14)
b
Direct labor debited to Work in Process 8400 =300*2*14
Add a comment
Know the answer?
Add Answer to:
Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT