Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates:
Machine-hours required to support estimated production | 150,000 | |
Fixed manufacturing overhead cost | $ | 653,000 |
Variable manufacturing overhead cost per machine-hour | $ | 4.90 |
Required:
1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places.)
2. During the year Job 500 was started and completed. The following information was available with respect to this job:
Direct materials requisitioned | $ | 350 |
Direct labor cost | $ | 260 |
Machine-hours used | 36 | |
Compute the total manufacturing cost assigned to Job 500.
(Round your intermediate calculations and final answer to 2
decimal places.)
3-a. During the year the company worked a total of 145,200 machine-hours on all jobs and incurred actual manufacturing overhead costs of $1,346,600. What is the amount of underapplied or overapplied overhead for the year? (Round your intermediate calculations to 2 decimal places.)
3-b. If this amount were closed out entirely to Cost of Goods Sold, would net operating income increase or decrease?
Increase | |
Decrease |
1 | ||
Predetermined overhead rate | 9.25 | =4.9+(653000/150000) |
2 | ||
Direct materials requisitioned | 350 | |
Direct labor cost | 260 | |
Overhead applied | 333 | =36*9.25 |
Total manufacturing cost Job 500 | 943 | |
3a | ||
Actual manufacturing overhead | 1346600 | |
Less: Manufacturing overhead applied | 1343100 | =145200*9.25 |
Underapplied overhead | 3500 | |
3b | ||
Net operating income would decrease. |
Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At...
Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 157,000 Fixed manufacturing overhead cost $ 653,000 Variable manufacturing overhead cost per machine-hour $ 4.20 Required: 1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places.) 2. During the year Job 500 was started and completed. The...
Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour S $ 154,000 654,000 4.90 Required: 1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places.) Predetermined overhead rate per MH 2. During the year Job 500 was started...
Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 155,000 Fixed manufacturing overhead cost $ 656,000 Variable manufacturing overhead cost per machine-hour $ 4.80 Required: 1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places.) 2. During the year Job 500 was started and completed. The following...
Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 152,000 S 655,000 $ 4.70 Required: 1. Compute the predetermined overhead rate. (Round your answer to 2 decimal places.) Predetermined overhead rate per MH 2. During the year Job 500 was started and completed. The following information...
Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour $ 156,000 658,000 4.30 Required: 1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places.) Predetermined overhead rate Predetermined overhead per MH 2. During the year Job 500 was...
Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 153,000 Fixed manufacturing overhead cost $ 659,000 Variable manufacturing overhead cost per machine-hour $ 4.40 1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places.) 2. During the year Job 500 was started and completed. The following information was...
Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour $ $ 153,000 651,000 4.50 Required: 1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places.) Predetermined overhead rate per MH 2. During the year Job 500 was started...
Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine hours. At the beginning of the year, the company made the following estimates: Machine hours requred to support estimated production Fixed manufacturing overhead cost Vanabio manufacturing overhead cost per machine-hour 150.000 654,000 $ 420 Required: 1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places.) Predetermined overhead I per MH 2. During the year Job 500 was...
Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the tolowing estimates Machine-hours required to support estimated production Fxed 159,000 659,000 4.00 overhead oost Required 1 Compute the predelemined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places. per MH 2 During the year Job 500 was stared and completed. The following information was available with respect to this job...
Answer #1 and #3 please
Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the compary made the following estimates: Fixed Variable manufacturing overhead cost per machine-hour 159,000 3 650,000 4.90 overmead cost Required: 1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places) per MH 2 During the year Job 500 was started and completed. The following information was...