Question

Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of t

0 0
Add a comment Improve this question Transcribed image text
Answer #1
1
Predetermined overhead rate 8.75 per MH =4.50+(651000/153000)
2
Direct materials 310
Direct labor cost 290
Manufacturing overhead 280 =32*8.75
Total manufacturing cost 880
3
Actual Manufacturing overhead 1278625
Manufacturing overhead applied 1276625 =145900*8.75
Manufacturing overhead cost underapplied by 2000
Add a comment
Know the answer?
Add Answer to:
Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At...

    Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 153,000 Fixed manufacturing overhead cost $ 659,000 Variable manufacturing overhead cost per machine-hour $ 4.40 1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places.) 2. During the year Job 500 was started and completed. The following information was...

  • Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At...

    Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour S $ 154,000 654,000 4.90 Required: 1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places.) Predetermined overhead rate per MH 2. During the year Job 500 was started...

  • Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At...

    Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour $ 156,000 658,000 4.30 Required: 1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places.) Predetermined overhead rate Predetermined overhead per MH 2. During the year Job 500 was...

  • Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At...

    Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 150,000 Fixed manufacturing overhead cost $ 653,000 Variable manufacturing overhead cost per machine-hour $ 4.90 Required: 1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places.) 2. During the year Job 500 was started and completed. The following information...

  • Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At...

    Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 157,000 Fixed manufacturing overhead cost $ 653,000 Variable manufacturing overhead cost per machine-hour $ 4.20 Required: 1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places.)           2. During the year Job 500 was started and completed. The...

  • Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At...

    Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 155,000 Fixed manufacturing overhead cost $ 656,000 Variable manufacturing overhead cost per machine-hour $ 4.80 Required: 1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places.)           2. During the year Job 500 was started and completed. The following...

  • Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine hours....

    Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine hours. At the beginning of the year, the company made the following estimates: Machine hours requred to support estimated production Fixed manufacturing overhead cost Vanabio manufacturing overhead cost per machine-hour 150.000 654,000 $ 420 Required: 1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places.) Predetermined overhead I per MH 2. During the year Job 500 was...

  • Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At...

    Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 152,000 S 655,000 $ 4.70 Required: 1. Compute the predetermined overhead rate. (Round your answer to 2 decimal places.) Predetermined overhead rate per MH 2. During the year Job 500 was started and completed. The following information...

  • Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At...

    Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the tolowing estimates Machine-hours required to support estimated production Fxed 159,000 659,000 4.00 overhead oost Required 1 Compute the predelemined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places. per MH 2 During the year Job 500 was stared and completed. The following information was available with respect to this job...

  • Answer #1 and #3 please Kody Corporation uses a job-order costing system with a plantwide overhead...

    Answer #1 and #3 please Kody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the compary made the following estimates: Fixed Variable manufacturing overhead cost per machine-hour 159,000 3 650,000 4.90 overmead cost Required: 1. Compute the predetermined overhead rate. (Do not round intermediate calculations. Round your answer to 2 decimal places) per MH 2 During the year Job 500 was started and completed. The following information was...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT