Question

Learning Curve percentage 0.80 Exponent for an 80% learning curve -0.321900 Direct Material Cost, per unit...

Learning Curve percentage 0.80
Exponent for an 80% learning curve -0.321900
Direct Material Cost, per unit $74,400.00
DMLH, for first unit 2,790.00
DML$, per hour $23.25
VMOH, per DMLH $13.95
(6) Calculate the total variable cost of producing 2, 4, 8, and 16 units,
using the Cumulative average-time model.
(7) Calculate the total variable cost of producing 2, 3, 4, and 5 units,
using the Incremental unit-time model.
0 0
Add a comment Improve this question Transcribed image text
Answer #1
(6) Cumulative No. of Units Cumulative Avg. time per Unit Cumulative Total Time
(1) (2) (3) = (1) x (2)
1                      2,790            2,790
2 (2,790 x 0.80) 2,232            4,464
4 (2,232 x 0.80) 1,786            7,144
8 (1,786 x 0.80) 1,429          11,432
16 (1,429 x 0.80) 1,143          18,288
(7) 2 units 4 units 8 units 16 units
Direct Material                   148,800        297,600       595,200       1,190,400
($74,400 x 2; 4; 8; 16)
Direct Manufacturing Labor                   103,788        166,098       265,794         425,196
($23.25 x 4,464; 7,144; 11,432; 18,288)
Variable Manufacturing Overhead                    62,273          99,659       159,476         255,118
($13.95 x 4,464; 7,144; 11,432; 18,288)
Total Variable cost                   314,861        563,357    1,020,470       1,870,714
Add a comment
Know the answer?
Add Answer to:
Learning Curve percentage 0.80 Exponent for an 80% learning curve -0.321900 Direct Material Cost, per unit...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • World Defense manufactures radar systems. It has just completed the manufacture of its first newly designed...

    World Defense manufactures radar systems. It has just completed the manufacture of its first newly designed system, RS-32. Manufacturing data for the RS-32 follow: (Click icon to view data) Requirement Calculate the total variable costs of producing 2, 4, and 8 units. Begin by calculating the total cumulative time in labor-hours. (Round the cumulative average time per unit to the nearest whole number.) Cumulative average time Number of Cumulative total time: units per unit: Labor-hours Labor-hours 3,145 6,290 2 2,673...

  • LEARNING CURVE TABLE 1.0000 0.8000 1.0000 0.8500 0.7021 0.6400 0.7729 0.5957 0.5618 0.5345 0.5120 0.7225 0.6856...

    LEARNING CURVE TABLE 1.0000 0.8000 1.0000 0.8500 0.7021 0.6400 0.7729 0.5957 0.5618 0.5345 0.5120 0.7225 0.6856 0.6569 0.6336 0.6141 1.0000 0.9000 0.8462 0.8100 0.7830 0.7616 0.7440 0.7290 1.0000 0.9500 0.9219 0.9025 0.8877 0.8758 0.8659 0.8574 Question 1 (13 marks) ABC produces equipment. It has just completed the manufacture of its first newly designed AB-XY Data is as follows: Direct Materials $ 5,000 Direct labor-first unit 180 hrs Learning curve - Incremental 90% Direct labor cost $45/DM labour hour Variable Manufacuring...

  • The Pacific Boat Company, which is under contract to the U.S. Navy, assembles troop deployment boats....

    The Pacific Boat Company, which is under contract to the U.S. Navy, assembles troop deployment boats. As part of its research program, it completes the assem of the first of a new model (PT109) of deployment boats. The Navy is impressed with the PT109. It requests that Pacific Boat submit a proposal on the cost of producing another six PT 109s Pacific Boat reports the following cost information for the first PT 109 assembled. Pacific Boat uses a 90% incremental...

  • Part IV-Problems (55 points) A. Highestec, Inc is beginning the production of a new product. Management...

    Part IV-Problems (55 points) A. Highestec, Inc is beginning the production of a new product. Management believes that 500 labor hours will be required to complete the new unit. A 90 percent cumulative average-time learning curve model for direct labor hours is assumed to be valid. Data on costs are as follows: S50,000 per unit s20 per direct labor hour $30 per direct labor hour Direct materials Direct labor Variable manufacturing overhead Required: a. Set up a table with columns...

  • 1. Total costs may be computed as follows: a.(Fixed costs per unit × Unit volume) +...

    1. Total costs may be computed as follows: a.(Fixed costs per unit × Unit volume) + Variable costs per unit b.Fixed costs per unit + (Variable costs per unit × Unit volume) c.Fixed costs + (Variable costs per unit × Unit volume) 2. A coefficient of determination of 0.91 means a.that the independent variable explains 91 percent of the cost. b.the model is significant 91 percent of the time. c.the two variables move together in the same direction and have...

  • Peter company produces a product with the following unit cost : Direct Material Direct Labour Variable...

    Peter company produces a product with the following unit cost : Direct Material Direct Labour Variable overhead Fixed Overhead Unit cost S 2.75 1.25 4.00 2.50 10.50 Fixed selling costs are $600.000 per year and variable selling costsare $1.50 per unit sol Production capacity is 500.000 units per year. However, the company expects to produc only 300,000 units per year. The product normally sells for $15 each. A customer has offered to buy 150.000 units for $10. The units would...

  • Bemmitt’s direct material cost is $3 per unit. The direct labor rate is $16 per hour...

    Bemmitt’s direct material cost is $3 per unit. The direct labor rate is $16 per hour and each units takes 1/4 hour to produce. Variable manufacturing overhead is $3 per unit and total budgeted fixed overhead is $6,000. A sales commission of $4 is paid on each unit. If Bemmitt expects to produce 2,270 units and sell 1,380 units, what is the total budgeted cost of goods sold ? Round your answer to the nearest dollar.

  • Bemmitt’s direct material cost is $3 per unit. The direct labor rate is $16 per hour...

    Bemmitt’s direct material cost is $3 per unit. The direct labor rate is $16 per hour and each units takes 1/4 hour to produce. Variable manufacturing overhead is $2 per unit and total budgeted fixed overhead is $7,400. A sales commission of $5 is paid on each unit. If Bemmitt expects to produce 3,210 units and sell 1,330 units, what is the total budgeted cost of goods sold ? Round your answer to the nearest dollar.

  • ABC Manufacturing Company's costing system has two direct cost categories: direct materials and direct manufacturing labour....

    ABC Manufacturing Company's costing system has two direct cost categories: direct materials and direct manufacturing labour. Manufacturing overhead (both variable and fixed) is allocated to products on the basis of standard DMLH At the beginning of 2018, ABC adopted the following standards for its manufacturing costs: Input Cost per Output Unit S 15 75 3 kg at $5 per kg 5 hours at $15 per hour Direct materials Direct manufacturing labour Manufacturing overhead: Variable Fixed Standard manufacturing cost per output...

  • E10-33 (similar to) Racing Radars manufactures radar systems. It has just completed the manufacture of its...

    E10-33 (similar to) Racing Radars manufactures radar systems. It has just completed the manufacture of its first newly designed system, RS-32. Manufacturing data for the RS-32 follow: E (Click icon to view data) Requirement Calculate the total variable costs of producing 2, 4, and 8 units A Data Table - X mber.) Direct material cost $80,000 per unit of RS-32 Direct manufacturing labor time for first unit 3,400 direct manufacturing labor-hours Learning curve for manufacturing labor time per radar system...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT