Way Cool produces two different models of air conditioners. The
company produces the mechanical systems in their components
department. The mechanical systems are combined with the housing
assembly in its finishing department. The activities, costs, and
drivers associated with these two manufacturing processes and the
production support process follow.
Process | Activity | Overhead Cost | Driver | Quantity | ||||
Components | Changeover | $ | 470,000 | Number of batches | 770 | |||
Machining | 305,000 | Machine hours | 7,900 | |||||
Setups | 232,000 | Number of setups | 120 | |||||
$ | 1,007,000 | |||||||
Finishing | Welding | $ | 186,000 | Welding hours | 4,000 | |||
Inspecting | 221,000 | Number of inspections | 860 | |||||
Rework | 65,000 | Rework orders | 210 | |||||
$ | 472,000 | |||||||
Support | Purchasing | $ | 145,000 | Purchase orders | 471 | |||
Providing space | 34,500 | Number of units | 4,950 | |||||
Providing utilities | 62,000 | Number of units | 4,950 | |||||
$ | 241,500 | |||||||
Additional production information concerning its two product lines
follows.
Model 145 | Model 212 | |||||
Units produced | 1,900 | 3,050 | ||||
Welding hours | 1,000 | 3,000 | ||||
Batches | 385 | 385 | ||||
Number of inspections | 490 | 370 | ||||
Machine hours | 2,550 | 5,350 | ||||
Setups | 60 | 60 | ||||
Rework orders | 80 | 130 | ||||
Purchase orders | 314 | 157 | ||||
Required:
1. Determine departmental overhead rates and
compute the overhead cost per unit for each product line. Base your
overhead assignment for the components department on machine hours.
Use welding hours to assign overhead costs to the finishing
department. Assign costs to the support department based on number
of purchase orders.
2. Determine the total cost per unit for each
product line if the direct labor and direct materials costs per
unit are $200 for Model 145 and $120 for Model 212.
3. If the market price for Model 145 is $1,850 and
the market price for Model 212 is $250, determine the profit or
loss per unit for each model.
Solution 1:
Computation of Departmental Overhead rates and overhead cost per unit | ||||||||
Department | Overhead cost | Allocation Base | Qty of allocation base | Overhead rate | Model 145 | Model 212 | ||
Activity Driver | Allocated Overhead cost | Activity Driver | Allocated Overhead cost | |||||
Components | $1,007,000.00 | Machine hours | 7900 | $127.47 | 2550 | $325,044 | 5350 | $681,956 |
Finishing | $472,000.00 | Welding hours | 4000 | $118.00 | 1000 | $118,000 | 3000 | $354,000 |
Support | $241,500.00 | Purchase orders | 471 | $512.74 | 314 | $161,000 | 157 | $80,500 |
Total | $604,044 | $1,116,456 | ||||||
Nos of units | 1900 | 3050 | ||||||
Overhead cost per unit | $317.92 | $366.05 |
Solution 2:
Computation of Per unit Cost | ||
Particulars | Model 145 | Model 212 |
Direct material and labor | $200.00 | $120.00 |
Overhead cost per unit | $317.92 | $366.05 |
Cost per unit | $517.92 | $486.05 |
Solution 3:
Computation of Profit (Loss) per unit | ||
Particulars | Model 145 | Model 212 |
Selling price per unit | $1,850.00 | $250.00 |
Cost per unit | $517.92 | $486.05 |
Profit (Loss) per unit | $1,332.08 | -$236.05 |
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. Process Activity Overhead Cost Driver Quantity Components Changeover $ 472,000 Number of batches 830 Machining 304,000 Machine hours 8,700 Setups 231,000 Number of setups 120 $ 1,007,000 Finishing Welding $ 186,000...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow Process Components Activity Changeover Machining Setups Quantity 830 7.799 120 Finishing Welding Inspecting Rework Overhead Cost Driver 5454,800 Number of batches 307,000 Machine hours 229,000 Number of setups $ 990,000 $...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in their components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. Process Activity Overhead Cost Driver Quantity Components Changeover $ 470,000 Number of batches 770 Machining 309,000 Machine hours 8,490 Setups 227,000 Number of setups 160 $ 1,006,000 Finishing Welding $ 182,000...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in their components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. (Loss amounts should be Indicated with a minus sign. Round your Intermediate calculations and round "Cost per unit and OH rate" answers to 2 decimal places.) Process Activity Components Changeover Machining...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. (Loss amounts should be indicated with a minus sign. Round your intermediate calculations and round "Cost per unit and OH rate" answers to 2 decimal places.) Process Activity Overhead Cost Driver...
Cost Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow Process Overhead Activity Driver Quantity Components Changeover $462,000 Number of batches 830 Machining 302.000 Machine hours 7,840 Setups 228,000 Number of setups 60 $992,000 Finishing Welding $186,000 Welding hours 4,800...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. Process Activity Overhead Cost Driver Quantity Components Changeover $ 586,950 Number of batches 910 Machining 349,758 Machine hours 7,620 Setups 288,800 Number of setups 160 $ 1,225,508 Finishing Welding $ 370,980...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. (Loss amounts should be Indicated with a minus sign. Round your Intermediate calculations and round "Cost per unit and OH rate" answers to 2 decimal places.) Process Activity Components Changeover Machining...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow Process Activity Componente Changeover Machining Setups Overhead Cost Driver Quantity $ 500. Number of batches 300 279,000 Machine hours 6,000 225.000 Number of 120 setups $1,004,000 180, 300 Welding hours 3,000...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. Process Activity Components Changeover Machining Setups Driver Number of batches Machine hours Number of setups Quantity 750 8,600 200 Finishing Welding Inspecting Rework Overhead Cost $ 480,000 309,000 233,000 $1,022,000 $...