Answers
Components: |
|||
Overhead costs |
$ 1,022,000.00 |
118.84 |
per machine hour |
Machine hours |
8,600 |
||
Finishing: |
|||
Overhead costs |
$ 472,000.00 |
76.13 |
per weilding hour |
Weilding hours |
6,200 |
||
Support: |
|||
Overhead costs |
$ 235,000.00 |
474.75 |
per purchase order |
Purchase orders |
495 |
||
Model 145 |
Activity Driver |
Departmental OH rate |
Total Overhead cost |
Components |
3250 |
$ 118.84 |
$ 386,230.00 |
Finishing |
2200 |
$ 76.13 |
$ 167,486.00 |
Support |
330 |
$ 474.75 |
$ 156,667.50 |
$ 710,383.50 |
|||
Units |
2000 |
||
Overhead cost per unit |
$ 355.19 |
||
Model 212 |
Activity Driver |
Departmental OH rate |
Total Overhead cost |
Components |
5350 |
$ 118.84 |
$ 635,794.00 |
Finishing |
4000 |
$ 76.13 |
$ 304,520.00 |
Support |
165 |
$ 474.75 |
$ 78,333.75 |
$ 1,018,647.75 |
|||
Units |
3030 |
||
Overhead cost per unit |
$ 336.19 |
Working |
Model 145 |
Model 212 |
|
A |
Material & Labor per unit |
$ 230.00 |
$ 130.00 |
B |
Overhead cost per unit |
$ 355.19 |
$ 336.19 |
C = A + B |
Total Cost per unit |
$ 585.19 |
$ 466.19 |
Working |
Model 145 |
Model 212 |
|
A |
Price per unit |
$ 1,325.00 |
$ 320.00 |
B |
Cost per unit |
$ 585.19 |
$ 466.19 |
C = A - B |
Profit (Loss) per unit |
$ 739.81 |
$ (146.19) |
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in...
Cost Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow Process Overhead Activity Driver Quantity Components Changeover $462,000 Number of batches 830 Machining 302.000 Machine hours 7,840 Setups 228,000 Number of setups 60 $992,000 Finishing Welding $186,000 Welding hours 4,800...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in their components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. Process Activity Overhead Cost Driver Quantity Components Changeover $ 470,000 Number of batches 770 Machining 305,000 Machine hours 7,900 Setups 232,000 Number of setups 120 $ 1,007,000 Finishing Welding $ 186,000...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow Process Components Activity Changeover Machining Setups Quantity 830 7.799 120 Finishing Welding Inspecting Rework Overhead Cost Driver 5454,800 Number of batches 307,000 Machine hours 229,000 Number of setups $ 990,000 $...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in their components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. (Loss amounts should be Indicated with a minus sign. Round your Intermediate calculations and round "Cost per unit and OH rate" answers to 2 decimal places.) Process Activity Components Changeover Machining...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. Process Activity Overhead Cost Driver Quantity Components Changeover $ 472,000 Number of batches 830 Machining 304,000 Machine hours 8,700 Setups 231,000 Number of setups 120 $ 1,007,000 Finishing Welding $ 186,000...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in their components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. Process Activity Overhead Cost Driver Quantity Components Changeover $ 470,000 Number of batches 770 Machining 309,000 Machine hours 8,490 Setups 227,000 Number of setups 160 $ 1,006,000 Finishing Welding $ 182,000...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. Process Activity Components Changeover Machining Setups Driver Number of batches Machine hours Number of setups Quantity 730 8,550 40 Finishing Welding Inspecting Rework Overhead Cost $ 464,000 301,000 230,000 $ 995,000...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. Process Activity Components Changeover Machining Setups Quantity 850 8,560 60 Finishing Welding Inspecting Rework Overhead Cost Driver $ 478,000 Number of batches 308,000 Machine hours 234,000 Number of setups $1,020,000 $...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow Process Activity Componente Changeover Machining Setups Overhead Cost Driver Quantity $ 500. Number of batches 300 279,000 Machine hours 6,000 225.000 Number of 120 setups $1,004,000 180, 300 Welding hours 3,000...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. Process Components Activity Changeover Machining Setups Driver Number of batches Machine hours Number of setups Quantity 730 8,470 200 Finishing Welding Inspecting Rework Overhead Cost $ 468,000 302,000 229,000 $ 999,000...