Answer
[1]
Components: |
|||
Overhead costs |
$ 1,020,000.00 |
119.16 |
per machine hour |
Machine hours |
8,560 |
||
Finishing: |
|||
Overhead costs |
$ 486,000.00 |
99.18 |
per weilding hour |
Weilding hours |
4,900 |
||
Support: |
|||
Overhead costs |
$ 242,000.00 |
450.65 |
per purchase order |
Purchase orders |
537 |
||
Model 145 |
Activity Driver |
Departmental OH rate |
Total Overhead cost |
Components |
3250 |
$ 119.16 |
$ 387,270.00 |
Finishing |
1000 |
$ 99.18 |
$ 99,180.00 |
Support |
358 |
$ 450.65 |
$ 161,332.70 |
$ 647,782.70 |
|||
Units |
1900 |
||
Overhead cost per unit |
$ 340.94 |
||
Model 212 |
Activity Driver |
Departmental OH rate |
Total Overhead cost |
Components |
5310 |
$ 119.16 |
$ 632,739.60 |
Finishing |
3900 |
$ 99.18 |
$ 386,802.00 |
Support |
179 |
$ 450.65 |
$ 80,666.35 |
$ 1,100,207.95 |
|||
Units |
3090 |
||
Overhead cost per unit |
$ 356.05 |
[2]
Working |
Model 145 |
Model 212 |
|
A |
Material & Labor per unit |
$ 300.00 |
$ 180.00 |
B |
Overhead cost per unit |
$ 340.94 |
$ 356.05 |
C = A + B |
Total Cost per unit |
$ 640.94 |
$ 536.05 |
[3]
Working |
Model 145 |
Model 212 |
|
A |
Price per unit |
$ 2,075.00 |
$ 260.00 |
B |
Cost per unit |
$ 640.94 |
$ 536.05 |
C = A - B |
Profit (Loss) per unit |
$ 1,434.06 |
$ (276.05) |
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its comp...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow Process Components Activity Changeover Machining Setups Quantity 830 7.799 120 Finishing Welding Inspecting Rework Overhead Cost Driver 5454,800 Number of batches 307,000 Machine hours 229,000 Number of setups $ 990,000 $...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. Process Activity Components Changeover Machining Setups Driver Number of batches Machine hours Number of setups Quantity 730 8,550 40 Finishing Welding Inspecting Rework Overhead Cost $ 464,000 301,000 230,000 $ 995,000...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. Process Activity Components Changeover Machining Setups Driver Number of batches Machine hours Number of setups Quantity 750 8,600 200 Finishing Welding Inspecting Rework Overhead Cost $ 480,000 309,000 233,000 $1,022,000 $...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in their components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. Process Activity Overhead Cost Driver Quantity Components Changeover $ 470,000 Number of batches 770 Machining 309,000 Machine hours 8,490 Setups 227,000 Number of setups 160 $ 1,006,000 Finishing Welding $ 182,000...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in their components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. Process Activity Overhead Cost Driver Quantity Components Changeover $ 470,000 Number of batches 770 Machining 305,000 Machine hours 7,900 Setups 232,000 Number of setups 120 $ 1,007,000 Finishing Welding $ 186,000...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in their components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. (Loss amounts should be Indicated with a minus sign. Round your Intermediate calculations and round "Cost per unit and OH rate" answers to 2 decimal places.) Process Activity Components Changeover Machining...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. Quantity 790 Process Activity Components Changeover Machining Setupa Driver Number of batches Machine hours Number of setupa 7,900 220 Finishing Welding Inspecting Rework Overhead Cost $ 476,000 301,000 234,000 $1,011,000 $...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department The activities, costs, and drivers assocated with these two manufacturing processes and the production support process follow Process Activity Components changeover Machining Setups Overhead Cost Driver Quantity Number of $500,000 batches 300 279,000 Machine hours 6,000 Number of 225,000 120 setups $1,004,000 $ 180,300 Welding hours 3,000 Number...
Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. Process Components Activity Changeover Machining Setups Driver Number of batches Machine hours Number of setups Quantity 730 8,470 200 Finishing Welding Inspecting Rework Overhead Cost $ 468,000 302,000 229,000 $ 999,000...
Cost Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow Process Overhead Activity Driver Quantity Components Changeover $462,000 Number of batches 830 Machining 302.000 Machine hours 7,840 Setups 228,000 Number of setups 60 $992,000 Finishing Welding $186,000 Welding hours 4,800...