Which of these describe groups or pairs of projects where you can accept one but not all?

Group of answer choices

Mutually exclusive.

Normal.

Independent.

Contingent.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Mutually exclusive

Mutually exclusive projects are those where we can accept only 1 project and not all. We generally accept the project which has the higher NPV

Add a comment
Know the answer?
Add Answer to:
Which of these describe groups or pairs of projects where you can accept one but not...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Which of the following statements is INCORRECT? Select one: a. For independent projects, the decision to...

    Which of the following statements is INCORRECT? Select one: a. For independent projects, the decision to accept or reject will always be the same using either the MIRR method or the NPV method. b. The IRR method is appealing to some managers because it produces a rate of return upon which to base decisions rather than a dollar amount like the NPV method. c. One of the disadvantages of choosing between mutually exclusive projects on the basis of discounted payback...

  • when evaluating projects by the present worth method how do you know which one or ones to select if the a projects are i...

    when evaluating projects by the present worth method how do you know which one or ones to select if the a projects are independent and B alternatives are mutually exclusive 4 2 When evaluating projects by the present worth method, how do you know which one(s) to select, if the (a) projects are independent, and (b) alternatives are mutually exclusive?

  • Consider the following projects, X and Y where the firm can only choose one. Project X...

    Consider the following projects, X and Y where the firm can only choose one. Project X costs $1300 and has cash flows of $477, $111, $452, $268, $526 in each of the next 5 years. Project Y also costs $1300, and generates cash flows of $496, $293, $468, $378 for the next 4 years, respectively. WACC=7%. A) Draw the timelines for both projects: X and Y. B) Calculate the projects’ NPVs, IRRs, payback periods. C) If the two projects are...

  • The final decision on which one of two mutually exclusive projects to accept ultimately depends upon...

    The final decision on which one of two mutually exclusive projects to accept ultimately depends upon which one of the following? a) length of each projects life b) initial cost of each project c) net present value d) total cash inflows of each project e) timing of the cash inflows

  • You can only invest in one of the projects The three projects below are mutually exclusive...

    You can only invest in one of the projects The three projects below are mutually exclusive and completely essential for your firm's existence. Your firm MUST invest in one (and only one) of them. You have been charged with analyzing the projects and making a recommendation for which to pursue. You should complete the indicated computations for each project then write a short analysis and conclusion in the text box below. Make sure to clearly indicate which project you think...

  • You are considering the following two projects which are mutually exclusive. The required return on each...

    You are considering the following two projects which are mutually exclusive. The required return on each project is 14%. Which project should you accept and what is the best reason for that decision? Group of answer choices Both Project A and B since they both have positive NPV Project A, because it has the higher profitability index Project A, because it has the higher net present value Project B, because it has the higher net present value O-NM Project A...

  • Question 19 Given the following information about events A, B, and C, determine which pairs of...

    Question 19 Given the following information about events A, B, and C, determine which pairs of events, if any, are independent and which pairs are mutually exclusive. P(A)P(B)P(C)=0.26=0.5=0.45P(A|B)P(B|C)P(C|A)=0.26=0=0.26 Select all correct answers. Select all that apply: B and C are independent A and C are mutually exclusive A and B are independent A and C are independent B and C are mutually exclusive A and B are mutually exclusive

  • Projects A and B are mutually exclusive. Project A costs $10,000 and is expected to generate...

    Projects A and B are mutually exclusive. Project A costs $10,000 and is expected to generate cash inflows of $4,000 for 4 years. Project B costs $10,000 and is expected to generate a single cash flow in year 4 of $20,000. The cost of capital is 17.5%. What is the NPV of the project you should accept? Group of answer choices $865.73 $492.49 $3,911.49 $354.94

  • When do ranking conflicts arise in IRR versus NPV? Group of answer choices When the first...

    When do ranking conflicts arise in IRR versus NPV? Group of answer choices When the first cash flow is negative and the remaining cash flows are positive. When projects are independent of one another. When projects are mutually exclusive and the cost of capital is to the left of the crossover point. All of the above can result in conflicts.

  • Given the following information about events A, B. and C, determine which pairs of events,if any,...

    Given the following information about events A, B. and C, determine which pairs of events,if any, are independent and which pairs are mutually exclusive. P(A)-0.3 P(BIA) 0.3 P(B)0.5 P(CB) 0.33 P(C) 0.33 P(AIC)-0.33 Select all correct answers. Select all that apply: A and Care mutually exclusive D A and Care independent O Band C are independent 0 Band C are mutually exclusive D Aand B are mutualy exclusive A and B are independ

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT